background image

iRC6800-010

(10/10)

13) Route the harness [1] through the original size detection unit [2]; then, connect it to the connector [3].

F-18

14) Mount the CCD unit cover, copyboard glass, right glass retainer, and reader right coverby following the steps

used to detach them but in reverse.

15) Connect the power cable to the power outlet, and turn on the main power switch.

16) Set '1' to the following service mode item: COPIER>OPTION>BODY>SZDT-SW (Category2); then, turn off

and then on the main power.

17) Check to make sure that the size of originals is correctly identified without the scanning lamp going on.

[3]

[2]

[1]

Summary of Contents for iR6800C

Page 1: ...ed for the machine to execute size detection using its CCD thus permitting the detection of original size without having to turn on the scanning lamp It is important that the user be fully informed of the following changes in regard to detection size Moreover the installation of the vertical size sensor kit Inch FM2 0647 calls for upgrading the reader controller software to version 9 02 iR C6800 S...

Page 2: ...onfiguration absence of paper STMT STMT R Installation Procedure When installing the Vertical Size Sensor Kit Inch FM2 0647 be sure to upgrade the reader controller software to version 9 02 or later iR C6800 Series 1 Check the contents of the kit F 1 1 Vertical size sensor unit 1 pc 2 Horizontal size sensor 1 pc 3 Clamp 5 pc 4 Edge saddle 1 pc 5 RS tightening screw M4x8 1 pc 1 2 3 5 4 ...

Page 3: ...strict sequence before starting the work 1 Turn off the control panel power switch 1 2 Turn off the main power switch 2 3 Disconnect the power cable 3 from the power outlet F 2 1 Remove the 2 screws and detach the right glass retainer 2 then detach the copyboard glass 3 F 3 2 OFF ON OFF 1 OFF 3 1 2 3 1 2 3 ...

Page 4: ...iRC6800 010 4 10 2 Remove the 2 screws 1 and detach the reader unit right cover 2 F 4 3 Remove the 9 screws 1 and detach the CCD unit cover 2 F 5 F 6 2 1 1 1 1 2 ...

Page 5: ...iRC6800 010 5 10 4 Remove the 3 screws 1 F 7 5 Lift the original size detection unit 1 slightly then disconnect the connector 2 F 8 1 1 2 1 ...

Page 6: ...ncluded horizontal size sensor 1 to the original size detection unit 2 Note Pay attention to the location of mounting as it differs between AB configuration and Inch configuration AB Configuration F 9 Inch Configuration F 10 1 2 1 2 ...

Page 7: ...iRC6800 010 7 10 7 Fit the harness 1 to the connector 2 AB Configuration F 11 Inch Configuration F 12 8 Secure the original size detection unit 1 in place using 3 screw 2 F 13 1 2 1 2 1 1 ...

Page 8: ...ure the vertical size sensor unit 1 in place using a screw 2 F 14 10 Fit the included clamp 1 into the hole 2 There are multiple holes Be sure to use the correct hole Do not use the hole identified as 3 F 15 1 2 1 2 2 1 3 3 ...

Page 9: ...iRC6800 010 9 10 11 Fit the included edge saddle 1 as shown F 16 If an edge saddle already exists skip this step 12 Fix the harness 1 in place using 5 clamps 2 and the edge saddle 3 F 17 1 1 2 3 ...

Page 10: ... reader right coverby following the steps used to detach them but in reverse 15 Connect the power cable to the power outlet and turn on the main power switch 16 Set 1 to the following service mode item COPIER OPTION BODY SZDT SW Category2 then turn off and then on the main power 17 Check to make sure that the size of originals is correctly identified without the scanning lamp going on 3 2 1 ...