65
Conditional Maintenance
Replacing A Primary Actuation Kit
If a PAK fails to operate during system testing, follow these steps to replace the PAK:
1. Ensure the primary actuation hose is not connected to the primary cylinder or a nitrogen pressure
supply system.
2. Remove the supervisory pressure switch installed on the PAK.
3. If applicable, disconnect the secondary actuation hose from the PAK.
4. Loosen the PAK shipping bolts from the top of the bracket, slide the unit back and remove it from the
bracket.
5. Loosen the shipping bolts on the new PAK. Slide the unit into the bracket. Tighten the shipping bolts to
ensure the PAK is held firmly but can still be slid back for installation to the cylinder valve.
6. If applicable, remove the side plug on the PAK and install in the secondary actuation hose.
7. Install the supervisory pressure switch onto the new PAK.
Replacing A Secondary Valve Actuator
If an SVA fails to operate during system testing, follow these steps to replace the SVA:
1. Ensure the primary actuation hose is not connected to the primary cylinder or a nitrogen pressure
supply system.
2. Disconnect any secondary actuation hose connecting the SVA to the PAK or other SVAs.
3. Loosen the SVA shipping bolts from the top of the bracket, slide the unit back and remove it from the
bracket.
4. Loosen the shipping bolts on the new SVA. Slide the unit into the bracket. Tighten the shipping bolts to
ensure the SVA is held firmly but can still be slid back for installation to the cylinder valve.
5. If applicable, remove the side plugs on the SVA and connect the SVA to any applicable secondary
actuation hoses.