8200-M628-O1 Rev A
212G/212GX Installation & Technical
Page 8
INSTALLATION, CONT.
Load Cell Connections with Over 30 Feet of Cable
For installations with over 30 feet of cable between the indicator and the load cells, sense
wires should be used. The sense wires must be connected between the +SENS, -SENS
terminals on the indicator and the +EXCITATION, -EXCITATION wires of the load cells or the
+SENS, -SENS terminals of the load cell trim board or the section seal trim board.
Figure No.4