(4) Procedure
a) Confirm that V1, V2, V3, B valve, SV1, SV2 are fully closed.
b) Confirm that each isolation valve for absorbent and refrigerant pumps are fully opened.
c) Connect the vacuum gauge to SV2. and open SV2.
d) Charge N
2
gas (Refer to 1-8-2).
e) Pressurize the Chiller up to 50 kPa with N2 gas. The pressure inside the Chiller can be checked by
the vacuum gauge.
f) When the pressure reaches 50 kPa, close the service valve and the valve of the N
2
gas cylinder.
g) Check the following positions with the soapy water.
g-1) All field welded portions (One shipping machine is not needed.)
g-2) Sight glass
g-3) Flare nut joints of service valves.
g-4) Flange connections ( the absorbent pumps, refrigerant pump, etc.)
g-5) Diaphragm valves
13
Summary of Contents for LJ
Page 1: ...Absorption Chiller INSTALLATION MANUAL LJ Model ...
Page 26: ...Fig 1 11 7 23 ...
Page 30: ... marks are the positions measured by the megger 27 ...
Page 36: ...33 ...
Page 37: ...34 ...
Page 46: ...13 Sampling of absorbent Sampling of absorbent Finished Unfinished 43 ...