1-9-1. Connect each pipe according to
Exhibit LE
.
(1) Make all necessary connections to the building water systems: chilled and cooling water.
Ensure that all piping is adequately supported and that no strain is placed on the Chiller
nozzles and connecting flanges.
(2) Provide adequate temperature and pressure sockets or taps on all supply and return piping.
1-9-2. Flashing
It is necessary to flash in the pipe of all water system before through the water in the Chiller.
1-9-3. Furnishing of rupture disk
(1) Confirm to close the isolation valve.
(2) Take off the end plate.
(3) Install rupture disk according to
Exhibit LE
. Furnishing of Rupture Disk.
(4) Open isolation valve.
(5) Close isolation valve cap.
(6) Fix the cap by wire with label after leak test of the Chiller.
1-9.PIPING
18
Summary of Contents for LJ
Page 1: ...Absorption Chiller INSTALLATION MANUAL LJ Model ...
Page 26: ...Fig 1 11 7 23 ...
Page 30: ... marks are the positions measured by the megger 27 ...
Page 36: ...33 ...
Page 37: ...34 ...
Page 46: ...13 Sampling of absorbent Sampling of absorbent Finished Unfinished 43 ...