7. Bubble test
With absorbe (1) cc/10min.
Refer to Section 1-11-7(2)
(2) cc/10min.
Refer to Section 1-11-7(2)
(3) cc/10min.
Refer to Section 1-11-7(2)
8. Confirmation of valve opening conditions and switch positions
(1) Change over valves :
1) B valve : In purge pipe
(Open) : Open Close
(2) Isolation valves : Open/close condition of valves shall be as follows.
1) Absorption pump
(Open) : Open Close
2) Refrigerant pump
(Open) : Open Close
(3) Diaphragm valves : Open/close condition of valves shall be as follows.
1) Manual purge Valve V1, V2, V3
(Close) : Open Close
2) Refrigerant blow valve
(Close) : Open Close
(4) Service valves : Open/close condition of valves shall be as follows.
1) Charge/discharge N2 gas
: SV1 (Close) : Open Close
2) Purge unit
: SV2 (Close) : Open Close
3) Refrigerant
: SV3 (Close) : Open Close
4) Diluted solution
: SV4 (Close) : Open Close
5) Concentrated solution
: SV6 (Close) : Open Close
6) Generator pressure gauge
: SV7 (Open) : Open Close
(5) Switch
1) Purge
: (Off) On Off
(6) Rapture Disk isolation valve
(Open) : Open Close
1) Confirmation work
: Good No-good
39
Summary of Contents for LJ
Page 1: ...Absorption Chiller INSTALLATION MANUAL LJ Model ...
Page 26: ...Fig 1 11 7 23 ...
Page 30: ... marks are the positions measured by the megger 27 ...
Page 36: ...33 ...
Page 37: ...34 ...
Page 46: ...13 Sampling of absorbent Sampling of absorbent Finished Unfinished 43 ...