1-2. SAFETY INSTALLATION
A proper skilled installer should carry out the equipment installation.
Take safety measures during installation works.
Take measures to prevent unauthorized people from entering installation site
during installation work.
1-3. DELIVERY INSPECTION
Upon delivery of the Carrier Chiller/Heater(s) to the job site, the owner or his designated
representative should carefully inspect the Chiller for the following items:
1-3-1. Check for physical damage to the Chiller
(1) Main shell
(2) Valves
(3) Control panel
(4) Wiring and connection
(5) Accessory
(6) Solution (In case of dry shipment )
1-3-2. Check the shipping or packing slip sent with the Chiller and note any missing items.
1-3-3. Check any separate boxes or crates shipping with the Chiller for any missing items.
NOTE 1. Isolation pads are not required for most installations.
NOTE2. Inform Carrier within 24 hours of any damage or missing items.
SOLUTION VOLUME
Model name Absorbent Refrigerant
Alcohol
LJ-01E
113kg
36kg
206cc
LJ-02E
154kg
60kg
280cc
LJ-03E
180kg
74kg
328cc
NOTE
Absorbent : LiBr 50wt%
Inhibitor : Li
2
MoO
4
20wt%
150ppm (Total Concentration)
Alcohol : Octyle Alcohol CH
3
(CH
2
)
5
CH(OH)CH
3
7
Summary of Contents for 16LJ-01
Page 1: ...Absorption Chiller INSTALLATION MANUAL 16LJ 01 02 03 Original instructions ...
Page 28: ...Exhibit H LiBr solution material safty data sheet ...
Page 29: ......
Page 30: ......
Page 31: ......