7 - MAINTENANCE
Initial 10 hours
Air conditioning belt
Inspect the tension of a new air conditioning belt after the
first 10 hours of operation and then every 250 hours of
operation.
1.
Check the belt at the location shown with a belt ten-
sion gauge. Specification is
122 - 149 N·m
(
90 - 110
lb ft
).
RAIL11TLB0001AA
1
2.
If the belt tension does not meet specification:
A.
Loosen the pivot bolt
(1)
.
B.
Loosen the lock nut
(2)
.
C.
Turn the adjustment bolt
(3)
clockwise to
tighten the belt.
Turn the adjustment bolt
counter-clockwise belt will loosen.
D.
When adjustment is complete, tighten the lock
nut and pivot bolt.
RAIL11TLB0005AA
2
7-35
Summary of Contents for 570NXT
Page 8: ......
Page 24: ...1 GENERAL INFORMATION 1 16 ...
Page 88: ...3 CONTROLS INSTRUMENTS 3 28 ...
Page 142: ...6 WORKING OPERATIONS 6 34 ...
Page 193: ...7 MAINTENANCE Cylinder closed end Two total one on each side RCPH10TLB258AAF 3 7 51 ...
Page 252: ...7 MAINTENANCE 7 110 ...
Page 257: ...8 SPECIFICATIONS Machine overall dimensions 8 5 ...
Page 259: ...8 SPECIFICATIONS RAIL12UTL0182GA 1 8 7 ...
Page 260: ...8 SPECIFICATIONS 8 8 ...
Page 262: ...8 SPECIFICATIONS RAIL12UTL0182GA 2 8 10 ...
Page 272: ...9 ACCESSORIES 9 4 ...
Page 279: ......