E1200 HT 260-3
8BMaintenance
23.04.07
00401010_41087
9-41
9.4.2
Installing the Process Tube
9.4.2.1
Installing the Quartz Process Tube
Keep ready for the installation:
—
quartz parts for thermocouple and tube case
—
insulating rings
—
insulating package of plies, 5 slices per process tube
Proceed as follows to install the process tube:
1. De-energize the heating after baking out the heating cassette, then wait until the
heating cassette has cooled down to room temperature.
2. Pull the spike thermocouples back by 10 mm at the heating cassette.
3. Use foil or other suitable materials to cover the process tube openings to avoid
process tube contamination.
4. Slide the process tube into the heating cassette.
5. The process tube must be positioned in the heating cassette as follows:
—
centrically towards the seal on the toxic gas exhaust side
—
protruding by at least 25 mm over the toxic gas exhaust edge
—
the position of the connections at the process tube aligned according to
drawing, see chapter 12.2 Drawings, Circuit Diagrams, Overviews, page 12-1
—
at the backside centrically towards the covering plate
—
horizontally aligned, use spirit level to check
6. Install the insulating ring at the toxic gas exhaust side. Avoid hollows to achieve
good insulation.
7. Install the insulating ring at the gas cabinet side. Avoid changing the process tube
position during installation. The insulating ring must be flush mounted against the
heating cassette. If necessary, adapt the insulating ring.
8. Install the covering plate on the gas cabinet side.
9. Check if the process tube protrudes into the toxic gas exhaust by at least 25 mm. If
necessary, press the process tube towards the gas cabinet side.
10. Avoid hollows.
11. Install the insulating package to the toxic gas exhaust.
12. Slide the spike thermocouples into the heating cassette until they touch the
process tube. Use spring clips to secure the spike thermocouples against sliding
out.
13. Install the tube case.
Summary of Contents for E1200 HT 260-3
Page 1: ...Operating Instructions for Horizontal Furnace Equipment E1200 HT 260 3 Version 1 0 1_41087 11 ...
Page 2: ...E1200 HT 260 3 23 04 07 00401010_41087 ...
Page 4: ...E1200 HT 260 3 Document Information 23 04 07 00401010_41087 ...
Page 16: ...E1200 HT 260 3 Index 23 04 07 00401010_41087 ...
Page 18: ...E1200 HT 260 3 List of Figures 23 04 07 00401010_41087 ...
Page 20: ...E1200 HT 260 3 List of Tables 23 04 07 00401010_41087 ...
Page 26: ...E1200 HT 260 3 0BOperating Instruction Remarks 23 04 07 1 6 00401010_41087 ...
Page 34: ...E1200 HT 260 3 1BIntroduction 23 04 07 2 8 00401010_41087 ...
Page 50: ...E1200 HT 260 3 2BSafety 23 04 07 3 16 00401010_41087 ...
Page 78: ...E1200 HT 260 3 4BTransport 23 04 07 5 4 00401010_41087 ...
Page 180: ...E1200 HT 260 3 8BMaintenance 23 04 07 9 76 00401010_41087 ...
Page 228: ...E1200 HT 260 3 10BSpare and Wearing Parts 23 04 07 11 2 00401010_41087 ...