Checking the Assembly Groups of the Loading Box
Damaged SiC/quartz parts must be replaced to prevent particle production in the
equipment and wafer breaks.
Check process boats, paddle, lift and slider storage places (option) for cracks and
damage. Replace damaged SiC/quartz parts.
Tighten the nuts and locknuts of process boats for PECVD processes, see chapter
12.4 Information on the Load Unit, page 12-2.
10.7.5
Checking the Filter of the Laminar Flow Box
Check the filter contamination level and the set flow rate.
10.7.6
Checking the Toxic Gas Exhaust
1. Clean process gas residues off the tube door sealing faces and the toxic gas
exhaust, then check.
2. Use a flow meter to check the exhaust suction adjustment.
3. For vacuum systems (option), check the cooling system of the tube closures for
leaks.
4. Check the toxic gas exhaust for corrosion and deposition.
Summary of Contents for E1200 HT 260-3
Page 1: ...Operating Instructions for Horizontal Furnace Equipment E1200 HT 260 3 Version 1 0 1_41087 11 ...
Page 2: ...E1200 HT 260 3 23 04 07 00401010_41087 ...
Page 4: ...E1200 HT 260 3 Document Information 23 04 07 00401010_41087 ...
Page 16: ...E1200 HT 260 3 Index 23 04 07 00401010_41087 ...
Page 18: ...E1200 HT 260 3 List of Figures 23 04 07 00401010_41087 ...
Page 20: ...E1200 HT 260 3 List of Tables 23 04 07 00401010_41087 ...
Page 26: ...E1200 HT 260 3 0BOperating Instruction Remarks 23 04 07 1 6 00401010_41087 ...
Page 34: ...E1200 HT 260 3 1BIntroduction 23 04 07 2 8 00401010_41087 ...
Page 50: ...E1200 HT 260 3 2BSafety 23 04 07 3 16 00401010_41087 ...
Page 78: ...E1200 HT 260 3 4BTransport 23 04 07 5 4 00401010_41087 ...
Page 180: ...E1200 HT 260 3 8BMaintenance 23 04 07 9 76 00401010_41087 ...
Page 228: ...E1200 HT 260 3 10BSpare and Wearing Parts 23 04 07 11 2 00401010_41087 ...