page 20
Mount the gearbox
1. Fit the M10 nuts and washers to the
mounting bolts as shown in Figure 15.
2. Adjust the nuts to be 7mm clear from the
base to allow for later adjustment.
Remember to fit the washers onto
each nut before installing the
gearbox.
FIGURE 17
3. Remove the knock-outs for the cables
from the gearbox.
4. Feed the cables through these holes
while fitting the gearbox to the
baseplate.
5. Note how the cables route up onto the
control card.
6. Check that the operator is level.
7. Secure the gearbox in place fitting a
washer, spring washer and nut onto each
gearbox mounting.
8. Seal the conduit and knock-out holes in
the operator with silicone sealer to
prevent ants from entering the operator
through these cable entry points.
FIGURE 16