43
6.
Install the new battery pack into the UPS.
7.
Screw the battery bracket back into the UPS and reconnect the battery cable
A and B.
8.
Re-install the front panel on the UPS.
6.5 Testing New Batteries
For a battery test, please check:
The batteries must be fully charged.
The UPS must be in Normal mode with no active alarms.
Don’t connect/disconnect equipment to/from the UPS.
To test batteries:
1.
Connect the UPS to mains power for at least 48 hours to charge the batteries.
2.
Press and hold the
button for 10 seconds to start the battery test. The
status display string will show “TEST”