13
M O U N T I N G O P E R A T O R ( C O N T I N U E D )
M O U N T I N G C O N T R O L B O X
After permanently mounting operator back on
brackets, lock the operator by turning the key to
the vertical position while pushing or pulling on
the gate until you hear the key release click into
place. The gate should not move after the
operator has been locked.
Remove control box cover, control board, surge suppressor, radio
receiver board and battery rack from control box. The 3 radio
receiver wires can be unplugged from the surge suppressor using
the removable terminal connector.
Use the four mounting holes provided with four screws
and washers (recommend #10 thru 1/4-20 Bolts or
Screws) Do Not enlarge existing holes, drill new holes
or over tighten mounting screws.
Continued on next page.
Single Control Board
OR
Master/Second
Control Board
Control Box
Cover
Battery
Rack
Radio Receiver Board
Surge Suppressor
Removable
Terminal