OPTIONAL ACCESSORIES (also refer to wiring diagram)

  RADIO TRANSMITTERS MODELS (OPTIONAL): 

  TX2EV, TX4EV, TX4UNI (remote controls), 747EV (wireless keypad), 128EV (2-channel wall control)

 FLASHING LAMP (OPTIONAL) MODEL: FLA24-2, FLA1-LED

  A 

 ashing lamp can be connected to the control board (Terminals: 24 V / 150 mA). It indicates gate movement. The 

 ashing light should be

  mounted as high as possible and in good clear view. The control board emits a constant signal that the lamp converts to a 

 ashing signal.

  KEY SWITCH (OPTIONAL) MODEL: 100010, 100027, 100034, 100041

  The system can be operated by key switch (Terminals: key symbol and COM). Also see OPEN/PED under “DIP SWITCH SETTINGS”.

  STOP SWITCH (OPTIONAL) MODEL: 600084

  A stop switch to stop the movement of the gate in any direction can be connected to this output

  SAFETY EDGE (OPTIONAL) MODEL: 600046, 600053, 600077, 600060

  (DIP  LOOP/EDGE must be off)

  A safety edge working according to the 8.2 kilo ohm principle can be connected to the control board (Terminals: Stop / 8,2 kOhm), i.e. a 8.2 kilo

  ohm test resistor is attached to the end of the safety edge. It ensures that the electric circuit is monitored permanently. The control board is

  supplied with an 8.2 kilo ohm resistor installed. Several safety edges are connected in series.

  PHOTOCELLS (OPTIONAL) MODELS: 771E, 772E

  The use of photocells is recommended. Use either model 771E or 772E which is also part of Safety Accessoy Kit APLUS-EV

  SAFETY ACCESSORY KIT (OPTIONAL): APLUS-EV

  The control board is already supplied with an antenna as standard. For special operating distances, an external antenna from the APLUS-EV

  accessory kit (includes Photocell 772E, Flashing Light FLA1-LED, and External Antenna SWG-ANT-EV) can be connected as shown in the

  wiring diagram.

  myQ (OPTIONAL)

  (only with 828EV Internet Gateway):

  Allows operating the gate opener via Internet or compatible smartphnone.

  DOOR MONITOR (OPTIONAL)

  (only with 829EV door monitor):

  allows optical and acoustical monitoring of the gate position. The gate can also be closed with the device.

  BACKUP BATTERY (OPTIONAL) : 

  The terminals serve to reload an externally installed storage battery.

  The integrated recharger is loaded and in case of power failure the battery provides power. A new fully charged storage battery may provide

  power for more than 24 hours. Storage batteries are subject to deterioration and lose capacity. Due to extensive use they lose capacity even

  faster. Replace storage batteries after approx. 2-3 years. 

  E-LOCK (OPTIONAL)

  The control board allows the use of a 12V E-lock. (instructions included with E-lock). A transformer (207399) must be connected for the Elock

  on the main board. In case the gate pushes too hard for the e-lock to open, a special function can be programmed. Activation time

  adjustment: Push P2 and P3 together and hold for approx 5 seconds, and count the number of clicks you hear. The click sound is produced

  from a relay (light relay).

  1 click = approx. 4 seconds power to e-lock (factory setting)

  2 clicks = gate closes for 1 second, then opens. Furthermore, after reaching the closed door position, the drive presses brie

 y to support the

  snap-in of the electric lock. Note: The door should be equipped with ground stops.

  GATE MONITORING or YARD LIGHTING (OPTIONAL)

  The Terminals have two functions depending on the position of the DIP Spy/Light. Refer to step “DIP SWITCH SETTINGS” in this manual.

  The output has no separate power supply and should be charged only up to 24V.

  Gate Monitoring / Status of the gate (Spy) 

  An LED or 24V/3W max lamp (or relay) can be connected to the terminals to indicate the status of the gate 

  LED OFF  

= gate close 

  LED blinking slow  = gate opening 

  LED ON  

= Gate open 

  LED blinking fast   = gate closing 

  Yard lighting / Courtesy lamp for 120 seconds 

  An 24V/3W max lamp (or relay) can be connected to have 120 seconds output to the terminals, when the gate is receiving a command  to  Open/Close.     

  After this time, it will switch OFF automatically

  CAUTION: output can be charged only up to 24V/3W or relay must be interposed

Summary of Contents for LYN300 Series

Page 1: ...atické pohony bran modely LYN300 LYN400 série SCS300 Instrucciones Automatismos de puerta automáticos modelos LYN300 LYN400 SCS300 de las series O ËÁ Â ÙfiÌ ÙÔÈ ÌË ÓÈÛÌÔ ÁÎ Ú fi ÔÚÙ ÌÔÓÙ Ï LYN300 LYN400 SCS300 Series Útmutatók SCS300 as sorozatba tartozó LYN300 as és LYN400 as automatikus garázsajtó Upute Automatski pogoni vrata modeli LYN300 LYN400 SCS300 serije Istruzioni Automazioni per cancell...

Page 2: ... 2 0 m 3 0 m 4 0 m 5 0 m 6 0 m 250 kg 180 kg 160 kg 140 kg Wing Weight Wing Size LYN300 LYN300 LYN400 LYN400 0 m 0 5 m 1 0 m 1 5 m 2 0 m 2 5 m 3 0 m 250 kg 180 kg 160 kg Wing Weight Wing Size SCS300 3 5 m 4 0 m ...

Page 3: ...6 DESCRIPTION OF LEDS 6 FUNTIONALITY OVERVIEW OF THE PUSH BUTTONS P1 P2 P3 RESET 6 OPTIONAL ACCESSORIES 7 PHOTOCELLS 8 RADIO AND RADIO PROGRAMMING 8 PROGRAM INTERNET GATEWAY my Q DOOR MONITOR 9 LOOP DETECTOR USAGE 10 DIP SWITCH SETTINGS 11 WING DELAY ADJUSTMENT 11 INITIAL OPERATION BASIC SETTING 12 14 TIMER TO CLOSE AUTO CLOSE 14 FORCE TORQUE OF MOTOR 14 DISPOSAL BATTERY DISPOSAL 14 INDICATION OF ...

Page 4: ...o check with your gate manufacturer for an opener installation reinforcement kit Activate opener only when the gate is in full view free of obstructions Do not allow children to play near the gate Humidity and water destroy the control board Make sure under all circumstances that water humidity or dammed up water cannot penetrate the control board covering Frequently examine the installation for i...

Page 5: ...optional Is mounted on the outside The gate is opened by key or by entering a number 7 Contact strip optional Safeguards the gate on being touched Contact strips can be mounted on the gate or on the pillars If required contact strips must be mounted at a height of up to 2 5m 2 16 en CONTROL BOX The control consists of several components exterior installation box 1 cover for box 1 control 1 transfo...

Page 6: ...s C Fasten transformer on to baseplate using the large screw and large washer D Put the 4 large closure screws through cover of the box Fasten 2 of them left or right approx 2cm into the box After that the cover can be opened to the side E Close box on a trial basis turning the screws all the way in If the lid does not close completely then the box is not fitted to the wall evenly and is therefore ...

Page 7: ...h identical colours distribution box IP65 cable screw joints and fastening material 041ASWG 0482 50 Cable 50m for professional use Consists of 50m of cable 6 pole with identical colours Cut only as much as you need for the current installation General wiring sizes The numbers mentioned in the table below are minimum requirements It is always possible to use larger diameters 230Volt Supply Power to...

Page 8: ...CM475 BROWN GREEN WHITE BROWN GREEN WHITE YELLOW YELLOW RADIO MODULE Model 207399 230 VAC 50 RED RED BLUE BLUE BROWN GREEN WHITE BROWN GREEN WHITE not required not required RED RED BLUE BLUE BROWN GREEN WHITE BROWN GREEN WHITE YELLOW YELLOW ART SUB Closed position Open position external battery ...

Page 9: ...D motor 2 Second opens second red blue To check correct polarity refer to section basic setting and functionality P1 P2 P3 RESET 24V 150mA flashing light accessory Motor1 MASTER BRN brown cable GRN green cable WHT white cable YEL yellow cable Motor2 SECOND BRN brown cable GRN green cable WHT white cable YEL yellow cable Light Contact gate monitor yard lighting PED key switch COM negative pole STOP ...

Page 10: ...ith 829EV door monitor allows optical and acoustical monitoring of the gate position The gate can also be closed with the device BACKUP BATTERY OPTIONAL The terminals serve to reload an externally installed storage battery The integrated recharger is loaded and in case of power failure the battery provides power A new fully charged storage battery may provide power for more than 24 hours Storage b...

Page 11: ... LED flashes photocell disables control board Connection between 1 COM Active when gate is closing reverses gate to open Connection between 2 COM Active when gate is closing and opening Connection between 3 COM Active when gate is opening holds gate in present position until photocell is cleared continues when cleared RADIO AND RADIO PROGRAMMING PROGRAM DELETE REMOTE CONTROLS The receiver has two c...

Page 12: ...the LEDs will blink 3 times and go out 7 The App will tell you if programming was successful and will prompt you to assign a name to the gate PROGRAM DOOR MONITOR Using the RESET Button on the control board 1 Connect power to the door monitor Position the door monitor in a convenient visible place inside the house If this place is too far from the gate opener the connection may not be possible or ...

Page 13: ... truck but do not comply with regulations as single protection since they do not detect people The loop detector control board output is wired as NO signal to the 8 2KOhm safety edge output In case you use safety edges as well Check the functionality you need before installation Interrupt loop DIP OPEN STEP must be on Shadow loop DIP OPEN STEP must be off Other options for loop detectors can be re...

Page 14: ...CS SUB RADIO The DIP RADIO is required to program remote controls For programming procedure please refer to page 8 section radio OFF No programming of remote controls possible ON Programming of remote controls possible Important Switch off DIP RADIO if not in use Wing Delay Adjustment The delay of one wing is required to open and close the wings correctly and to operate the wings with a safe dista...

Page 15: ...anged any time later after completion of the installation Now connect the mains supply 230V to the control board BASIC SETTING 1 Press buttons P1 P2 and P3 simultaneously for approx 2 3 seconds until yellow LED flashes 2 Monitor the gate Press and hold P1 for 1 2 seconds The wing with motor 1 opens If motor 1 closes it is wired incorrectly and the red and blue wires of the motor cable must be rever...

Page 16: ...When the learn LED goes out the programming has finished PROGRAMMING TRAVEL DISTANCES ADVANCED NOTE In this mode P1 must be pressed 9 times With every time the button is pressed a position time is stored This allows programming of SOFT STOP slow travel in order to adjust to application Long or short phases of SOFT STOP are possible 1 Both wings must be closed 2 Press P1 and P2 for approx 5 6 second...

Page 17: ...r changes to the installation rust or inappropriate lubrication it may have to be repaired The control board complies with the latest EU guidelines One of these guidelines specifies that the closing forces at the gate edge must not exceed 400N 40 kg for the last 500 mm before the door is CLOSED Above 500 mm the maximum force at the gate edge must not exceed 1400 N 140 kg If this cannot be ensured a...

Page 18: ...nstallation A Object obstructs safety edge B Defective safety edge C Power too low or broken wire in supply Power supply to control board is too low A Defective supply 230V or malfunctioning contact B Broken wire in supply cable copper cable C The battery accessory to operate the gate whilst power failure is dead EEPROM Fault Power up failed Only LYN SCS Release lever OPEN Defect on relay or major...

Page 19: ... 2 Find and rectify fault s see description of diagnostic LEDs 3 Check photocell connection programming 4 Check terminals and connections 1 Program transmitter 2 Check photocells check diagnostic LEDs 3 DIP RADIO must be off Program travel distance See initial operation diagnosis LED re program travel distance consult dealer specialist 1 Check manual especially 1 2 Motor 2 If motor is moving check...