Rev J
Doc 01-20098
Page 32 of 44
2. PREVENTIVE MAINTENANCE INSTRUCTIONS
Figure 23. Gate Operator Disassembly and Assembly.
Gate Operator Serial Number:
UPS: Yes No
•
Refer to Figure 23 to perform the following.
1. Turn off power to the gate operator
at the circuit breaker
.
2. Remove the cover mounting bolts and remove the gate operator cover.
3. Perform preventive maintenance tasks 3 to 14, above.
4. After completing all checks, perform the procedure found in Part 2, System
Installation, Paragraph M, Post Installation Procedures.
Gate Operator
Cover (in place)
Clear Plastic
Cover
Control
Box
Cover
Mounting
Bolt
(4 places)
Gate Operator
Cover