background image

030‐300377 Rev. A

Section LTCMPH-75-802

0316P4

Page 3 of 5

 16.  

h

Position the base on top
of the gravel and level the
base. Alternately backfill
the base on the inside
first then the outside,
tamping the soil as it is
added. This equalizes the
pressure inside/outside
the base and makes the
base more stable. The
backfill on the outside of
the base should be even
with the Ground Line on
the front of the base.
Inside, add backfill soil to
a point midway between
the first and second ribs.

2 to 3" gravel inside

the base (Step 18)

Base

Top

ÏÏÏÏÏÏÏÏÏ

ÏÏÏÏÏÏÏÏÏ

ÏÏÏÏÏÏÏÏÏ

ÏÏÏÏÏÏÏÏÏ

ÏÏÏÏÏÏÏÏÏ

ÎÎÎÎÎÎ

ÎÎÎÎÎÎ

ËËËËËË

Soil

Pea Gravel

Soil

Backfill and tamp inside/outside the base.

 Once the hole has been dug to

the proper depth, a layer of pea rock /gravel must be placed at the bottom of
the hole. 

Note: The base can be leveled more easily if it is placed on

gravel first.

8"

7"

Side View

Moisture

Barrier 

(see

Step 17)

Base

Bottom

Ground

Line

2"

above

vapor

barrier

1st

Rib

of

Base

ÎÎÎÎÎÎÎÎÎ

ÎÎÎÎÎÎÎÎÎ

Gravel layer

 17.  

h

Place the red plastic moisture barrier. 

The provided moisture barrier sheet

or bag must be placed on top of the tamped backfill soil inside the base. If it is
supplied as a bag, cut the sides so it can be spread over the backfill soil. Bring
it to the edges of the base so it covers as much of the backfill as possible. The
sheet can be cut to fit around any duct or cable entering the base, or an X can
be cut in the center to allow the sheet to be fitted over the cable or conduits.
The sheet serves to prevent excessive moisture from entering the CMPH.

Failure to use the plastic moisture barrier on top of the soil significantly
increases the risk of condensation inside the pedestal.

 18.  

h

Add gravel to the inside of the base.

 Pour approximately 2 to 3 inches of

5/8", or smaller, pea rock or gravel into the base up to the second rib or 2
inches below any innerduct or conduit opening. Keep the duct openings
sealed when adding gravel. Spread out and level the gravel.

 19.  

h

End of base installation - determine next procedure. 

If cable work will

now be performed, continue with the next steps and consult local practices
and equipment manufacturer instructions for the proper procedures. If
further cable work will NOT be performed at this time, skip to Step 24 to
close the CMPH enclosure.

 20.  

h

Perform cable routing and mounting.

 Per company practice and local

codes

perform all cable routing, mounting, and management procedures.

 21.  

h

Bond and strain‐relief the cables.

Ground or bond the cable(s) to the
ground posts provided on the ground
plate. Perform cable strain relief and
bonding per company practice.

Attach earth ground

to ground lug

Attach cable bond

straps to posts

Ground Plate

Posts to attach plate to ground bracket

 22.  

h

Finish cable work

 & 

equipment mounting.

 Per company practice

perform

all cable opening

 

and splicing procedures

and equipment mountings and

connections

.

 23.  

h

Re‐check cable management.

 Verify all equipment and cabling is organized

and will not contact the interior walls of the dome when installed (keep items
at least 1" from the vertical plane of the base collar). This assures safe and
smooth dome placement.

 24.  

h

Install dome.

 Locate the dome and lift it

up and over the interior framework and
equipment. When replacing the dome,
make sure the lock side of the dome is
facing the catch side of the base. Lower
the dome until it overlaps and
self‐latches to the base.

Lower dome

onto base,

latch will

self‐lock

Align bottom of

dome with top

of base

 25.  

h

Verify the CMPH is locked.

 The

dome design allows the dome to
self‐lock on the base. Verify the
dome is locked by attempting to
lift the dome.

 26.  

h

(Optional) Padlock the CMPH.

 For models equipped with an optional

hasp, the CMPH also can be locked by inserting a padlock through the
holes in the hasp provided at the front of the enclosure.

Hasp for padlock

(orderable option)

 27.  

h

Label outer dome.

 Place all ID/warning labels on the dome, per company

practice.

 28.  

h

End of CMPH placement. Clean up site.

 If no more equipment or cable

work will be performed at this time, clean up the site, fill and tamp any
trenches, replace any removed sod, restore the landscape to it's original
condition, pick up all equipment, and optionally leave this document inside
the CMPH for future reference.

Table 2.  Installing the CMPH with New Charles Stakes

Step #

Instructions

Charles offers some CMPH models that include 2 mounting stakes (either 30", 36", or 42" long).
All stakes have identical hole patterns. This table describes how to install these models. 

 1.  

h

Prepare the CMPH, trench, and cable. 

 Perform Steps 1‐10 of Table 1 to

open the enclosure and prepare the hole or trench and the cables or
conduit. Verify the base installation site is ready and suitable for metallic
stakes.

 2.  

h

Remove stakes from
CMPH framework.

 Two

mounting stakes are
packed with the CMPH;
detach them from the base
lag bolts by removing the
nuts and washers which
secure them. Take care to
retain the hardware which
will be re‐used in
subsequent steps.

Remove but retain the nuts

that secure the stakes to

the inside of the enclosure

Fiber‐type bracket
(note offset depth)

Summary of Contents for CMPH

Page 1: ...l equipment and cable storage capacity and protection against corrosion floods fire weather dirt insects intrusion dents and impact The CMPH contains a base a dome and internal frame work The base has corrugated or ribbed walls internal dual purpose molded in channel grooves which accept most metallic stakes as well as the vertical channels of the internal framework see Figure 2 an open top and an...

Page 2: ...mpany practice to lay place and cut any cables and innerduct or conduit 4 h Unpack and inspect equipment Remove the CMPH from its packaging Inspect the unit upon delivery if damaged in transit report the damage to the shipping company 5 h Disengage the CMPH lock Unlock the CMPH using a 216 tool or can wrench at the front hex nut in cup washer screw turn the cup washer screw counterclockwise approx...

Page 3: ...train relief the cables Ground or bond the cable s to the ground posts provided on the ground plate Perform cable strain relief and bonding per company practice Attach earth ground to ground lug Attach cable bond straps to posts Ground Plate Posts to attach plate to ground bracket 22 h Finish cable work equipment mounting Per company practice perform all cable opening and splicing procedures and e...

Page 4: ...sure such as the UPC 1200 series to be replaced Perform Steps 1 7 of Table 1 to prepare the new Charles CMPH enclosure the hole or trench and the cables or conduit skip Steps 2 3 if trenching and new cable placement is not required 2 h Dig around existing enclosure Remove the dirt from around the existing enclosure Dig deep enough to allow the enclosure to be lifted and removed 3 h Prepare existin...

Page 5: ...work for mounting equipment and cabling a ground plate with a ground lug and bond posts instructions and a plastic moisture barrier sheet Order model CMPH 75 A B C D where A B C or D represents one of the features as listed below A stake size 0 No stakes 1 30 stakes 2 36 stakes 3 42 stakes B bar or bracket type 0 Standard copper type F Fiber type offset see Step 2 Table 2 C material F Flame retard...

Reviews: