7.0. PLACING A ChipBLASTER:
7.1.
After you receive your new ChipBLASTER unit the first thing you need
to do is prepare the site where you would like to place the unit.
INSTALLATION SITE MUST BE FLAT AND LEVEL
.
7.1.1. You need to keep the unit within 3M (10’) of the machining center that you are
conncecting the ChipBLASTER to.
7.1.2. Locate the unit so the ChipBLASTER’s electrical cabinet is within 3M (10’) of
the machining center’s electrical cabinet.
7.1.3. Make sure you place the unit so maintenance can easily get to the filter housings
and electrical cabinet on the ChipBLASTER unit. Refer to footprint drawing
(Section 23) for recommended clearances.
7.2. After you have the site cleared for the ChipBLASTER unit you are
ready to prepare the ChipBLASTER.
7.2.1. Remove the lumber that is used to hold the unit in place during transporation
using a phillips screw driver or an electric screw gun.
7.2.2. Before you remove the ChipBLASTER from the skid take a moment to locate the
bags containing the casters.
7.2.3. When removing the ChipBLASTER from the skid, lift unit from the sides only!
Insure the forks extend completely under the ChipBLASTER unit.
DO NOT AT ANY TIME REACH UNDER THE ChipBLASTER UNIT
OR STAND UNDER THE ChipBLASTER UNIT WHILE IT IS
SUPPORTED BY A FORK TRUCK. IF YOU MUST REACH UNDER
THE MACHINE BLOCK IT UP FOR SAFETY.
7.2.5. After you remove the ChipBLASTER from the skid take the set of four casters
and mount them in the receptacles located at each corner of the ChipBLASTER
unit. As a safety precaution, block unit while installing casters. Note: Two
casters are rigid and two swivel. Locate both swiveling casters on same end of
unit.
7.2.6. After you have the casters in place, move the ChipBLASTER into desired
location.
!
!