ChipBLASTER Inc
19
10.0. START – UP (Cont.):
10.0.7. Reconnect hose to sump and tighten hose clamp.
10.0.8. Verify high-pressure hose is connected to machine center and is plumbed to an
appropriate nozzle.
CHECK MOTOR ROTATIONS
. SEE BELOW.
CHECK MAIN PUMP ROTATION. ROTATION IS COUNTER
CLOCKWISE VIEWED FROM THE SHAFT END.
CHECK RETURN PUMP ROTATION. ROTATION IS
CLOCKWISE VIEWED FROM FAN END.
DO NOT RUN THE HIGH-PRESSURE PUMP DRY FOR ANY
PERIOD OF TIME. CAVITATION WILL RESULT IN
FAILURE OF THE PUMP. ALWAYS REMEMBER TO CHECK
THAT ALL PLUMBING VALVES ARE OPEN AND THAT
PUMPED COOLANT CAN FLOW FREELY TO THE INLET
OF THE HIGH- PRESSURE PUMP.
11.0. SYSTEM AIR PURGE:
11.1
SINGLE AND DUAL FILTER
11.1.1 Loosen the thumb screw on each automatic vent valve two turns so that trapped
air can escape both filters.
11.1.2 Press the
AIR PURGE
push button to remove the air from the filters. Continue
to hold the button until you no longer hear air escaping from the automatic vent
valve. Close the thumb screws.
11.1.3 Start the Chipblaster and check for any coolant leaks.
11.1.4 Insure that all electrical circuits are operating correctly.
11.1.5 The coolant outlet pressure is factory preset to run at 1000 PSIG (69 bar), or a
customer specified pressure. Refer to Pressure Adjustment Procedure.
!
!
!
!