35
Chloride Active
UK
Tower units
Rack/Tower units
5) Take the new front panel with the LCD Display
and connect the at cable to the box with the LCD
Display (the cable must be in the same position as
in the old front panel)
6) Insert the new front panel in the UPS
5) Take the new front panel with the LCD Display and
pull out the box containing the LCD Display
6) Connect the at cable to the box with the LCD
Display (the cable must be in the same position as
in the old front panel)
7) Insert the box with the LCD Display in the front
panel
8) Insert the new front panel in the UPS
6.4.2 Battery disposal
The typical battery life cycle is 3 to 5 years, at an ambient temperature of 25ºC, but is also dependant on
the frequency and duration of mains failures.
Once the battery has reached the end of its useful life, follow the procedure for battery replacement (section
6.4.1).
After the batteries are replaced, a certi ed disposal/recycling company should carry out disposal/recycling
of the used batteries.
Exhausted rechargeable batteries are classi ed as “harmful toxic waste” and as such the law demands that
they be disposed of /recycled by an authorized recycling center.
The manufacturer’s service center is fully equipped to deal with such batteries, in accordance with the law
and with the greatest respect for the environment. Contact your customer service representative to arrange
for maintenance and/or battery replacement.
6.5 Front Panel with LCD Display Installation
WARNING:
Installation must be carried out only by quali ed technicians.
Depending on your local market, the UPS can include a front panel based on LED indicators or a front
panel with a LCD Display. For units which include a front panel based on LED indicators as standard, front
panels with LCD display are available as accessory. These front panels have to be ordered separately.
In order to replace the front panel with LED indicators with the front panel with LCD display, the following
steps (illustrated in the next gures) have to be followed:
WARNING:
Before performing this installation, ensure that the inverter is switched off and the input power
cord is disconnected. Wait until all LEDs turn off (this may take around 1 minute after disconnection of the
UPS) prior to performing this installation.
1) Pull out the front panel with LED indicators
2) Unscrew the box containing the LED indicators from the front panel
3) Remove the box
4) Disconnect the at cable from the box (please pay attention to the position of the cable)