Step 10 (Vacuum Test) 

  Close the cylinder valve and breathe down 

(slowly) the system 

  The alarm whistle should sound at +/- 50 

bar 

  Continue breathing down the system 

  Once empty, hold breath for 8 seconds 

– 

the face mask should collapse and hold to 
face (indicating a positive seal) 

 
 

3.4. 

Doffing (taking off) the SCBA 

 

 

Step 1 

  Loosen the chin and cheek straps, by 

pressing the buckles forward using your 
thumbs 

 

 

 

 

 

Step 2 

  Reach under and pull the mask off 

backwards over your head (do not pull on 
the front port). 

  Reset Demand Valve by pushing the 

RED button (this will shut the air flow) 

  Close the cylinder valve 

  Vent system by pressing Exhaust Button 

  Check that Pressure Gauge is on Zero 

pressure 

  Press Red Button to reset system 

 

 

 

Step 3 

 

Extend waistbelt straps and open waist 
belt buckle

 
 

Summary of Contents for CTS-IB-PPE-01

Page 1: ...INSTRUCTION BOOKLET CTS IB PPE 01 SELF CONTAINED BREATHING APPARATUS SCBA ...

Page 2: ...on 5 2 4 Basic Unit Backplate pneumatic system without second connector 5 2 5 Pressure Reducer 6 2 6 The Demand Valve 7 2 7 Medium Pressure Hose 7 2 8 High Pressure Hose 8 3 USE 8 3 1 Mounting cylinder 8 3 2 Connecting cylinder 8 3 3 Donning putting on the SCBA 9 3 4 Doffing taking off the SCBA 12 4 MAINTENANCE INSTRUCTIONS 13 5 CLEANING 14 6 STORAGE 14 7 TECHNICAL SPECIFICATIONS 14 8 ACKNOWLEDGEM...

Page 3: ...missioning work that has not been carried out by authorized persons ER This product is supporting life and health Inappropriate use maintenance or servicing may affect the function of the device and thereby seriously compromise the user s life Before use the product operability must be verified The product must not be used if the function test is unsuccessful it is damaged a competent servicing ma...

Page 4: ...ut of the space he s in to fight fire or whatever purpose it is used for 2 2 6 The face mask is of soft moulded nature rubber and five adjustable head straps and a neck strap It has a foam filled or air cushion seal and a full vision visor For correct positioning of the mask the straps should be tightened in the sequence where the first two lower chin straps then the middle pair cheek straps and f...

Page 5: ...225 150 Light Work 12 20 100 60 150 90 Moderate Work 20 40 60 30 90 45 Heavy Work 40 60 30 20 45 30 Nominal Working Duration Fully Charge Cylinder Capacity 10 40 We subtract 10 as 10 minutes is when the alarm starts ringing and it is a safe period which must be taken into account So a 1200 litres cylinder will last for 1200 40 30 minutes minus the 10 20 minutes Nervousness and excitement can cause...

Page 6: ...material Materials of the shoulder strap and waist belt are flame resistant polyester webbing flame resistant fabric and flame resistant padding material Wide shoulder padding and waist protective padding make the wearing very comfortable The metal on the back plate straps and waist belt are made of stainless steel are not easily rusted 2 5 Pressure Reducer 1 High Pressure Hose 5 Cylinder Connecto...

Page 7: ... alarm is 5 L min There is also a safety release valve which is set to about 11 bar in case there is anything wrong and the medium pressure rises the valve will be opened release the over pressure to guarantee the performance of the demand valve 2 6 The Demand Valve The demand valve is a lung governed demand valve for a compressed air breathing apparatus It is connected between compressed air supp...

Page 8: ...pressure hose from exploding 3 USE The device can be used only after fully maintained and tested If malfunctions or defects were found before using do not use the device Prevent the respirator from sharp objects and prevent it from collision with any objects during the use The device shall be checked and repaired by MSA authorized service centre WARNING 3 1 Mounting cylinder 1 Insert the cylinder ...

Page 9: ...retighten if necessary 3 3 Donning putting on the SCBA Step 1 Place the SCBA in front of you with the cylinder facing down and the cylinder valve away from you Fully open the shoulder straps and waist belt Lay the shoulder straps and waist belt out to prevent them from tangling Check all components of the device for defects and malfunctions Step 2 Overhead Method Grasp the carrying frame of the ba...

Page 10: ...t pad aligns with hips Adjust the SCBA into position top of cylinder should be neck high Step 4 Connect waist belt buckle Pull adjusting straps as shown until device is secure Adjust the waist weight belt to suit the weight of the SCBA which should rest comfortably on your hips Tuck strap loose ends into belt Step 5 Press RED LDV button Fig 4 to switch off positive pressure Step 6 Fully open the c...

Page 11: ...lace chin in facemask chin cup and pull head harness over the head Tighten chin lower straps Tighten cheek upper straps Tighten centre head strap if necessary Step 8 First breathe will switch on LDV to positive pressure mode Inhale and hold breath there must be no leak audible Breathe normally and expelled air should pass free through exhalation valve Check supplementary air supply is working by p...

Page 12: ...d collapse and hold to face indicating a positive seal 3 4 Doffing taking off the SCBA Step 1 Loosen the chin and cheek straps by pressing the buckles forward using your thumbs Step 2 Reach under and pull the mask off backwards over your head do not pull on the front port Reset Demand Valve by pushing the RED button this will shut the air flow Close the cylinder valve Vent system by pressing Exhau...

Page 13: ...tus and cylinder pressure should not be lower than 250 bar Component Maintenance Item Minimum intervals for checking maintenance and repair Before use After use Every year Every 3 years Every 9 years Demand valve Cleaning disinfection X Check diaphragm X X Replace diaphragm X Tightness check X X X Check closing pressure X X Overhaul inspection X Reducer Alarm device X X X Replace high pressure sea...

Page 14: ...ld be machine washed with water not above 40 C Buckles should be well inserted during washing After washing hang them in a ventilated place for a naturally dry 6 STORAGE The apparatus should be stored in a clean dry and well ventilated place Put the apparatus into the package and keep it away from long term exposure to sunshine heat radiation electromagnetic field and devices that may produce ozon...

Reviews: