28
Chapter 4 Operation
When the high DC capacity being charged by PV panels
is completed, the LCD will indicate that the DC circuit
breaker is ready to be turned on, as shown in Figure 4-3 and
4-4.
Figure 4-3 Prompt of circuit breaker Figure 4-4 Prompt of circuit breaker
connection of CPS SC500KTL connection of CPS SC250KTL-H
When the DC circuit breaker is turned on, the indication
on the LCD is shown in Figure 4-5 and 4-6. If charging is
NOT successfully completed, the DC circuit breaker can
NOT be turned on manually.
Figure 4-5 Connection status of Figure 4-6 Connection status of
circuit breaker of CPS SC500KTL circuit breaker of CPS SC250KTL-H
Afterwards, CPS SC500KTL/CPS SC250KTL-H will run
the automatic start-up program.
Automatic start-up
: When the inverter is energized or
under normal operation after the installation and if the inside
3 phase output AC is not cut off or the outside 220V AC is
not interrupted, the inverter will enter the state of automatic
CloseOk
>>>>>>>>>>>>>>
8/31/2011 7:15:20
001# CloseOk
002# CloseOk
>>>>>>>>>>>>>>
8/31/2011 7:15:20