Chapter 4 Operation
35
Warning:
Before opening the inverter for maintenance, shut
down the inverter through LCD operation. Turn off the
DC circuit breaker, execute the De-energy program and
then turn off the AC circuit breaker. The inverter should
not be maintained until the voltmeter shows that there is
no electric charge left in the DC bus capacitor
!
4.3 Grid connection and power generation
The grid connection and power generation process of
CPS SC500KTL/CPS SC250KTL-H grid-tie PV inverters are
automatic. It will check automatically whether AC power grid
meets the grid connection and power generation conditions.
At the same time, it will also check whether photovoltaic
array has sufficient energy. The inverter will enter grid
connection and power generation mode when everything is
ready. The inverter will maximize the photovoltaic array
output power in the way of MPPT (Maximum Power Point
Tracking) during the grid connection and power generation.
Meanwhile, the inverter will check the power grid at any time.
It will enter protection sequence in the event of abnormal
conditions. The inverter will enter standby mode when the
sunlight is weak and power generation is insufficient. The
two independent 250KW modules of CPS SC500KTL adopt
the advanced cascade control to realize the high efficiency
and reliability of the inverter by putting one DC cabinet into