10
STEP 12: Continued from page 9.
d. The flat brace
➈
should be bolted to the hole in
the horizontal bag support
➅
at location GG in
Fig. 16 on page 9 . Use a
1
⁄
2
" x 1
1
⁄
4
" bolt, two flat
washers, one lock washer and nut.
e. Bolt the other end of the flat brace
➈
to the top
hole in the blower housing lug at location HH in
Fig. 17. Use a
1
⁄
2
" x 1
1
⁄
4
" bolt, two flat washers, one
lock washer and nut.
NOTE: Make sure all hardware is tightened for all
the bag support parts.
STEP 13: Installing Gasket to Drum Lid Assembly.
a. Unwind the roll of the 1
1
⁄
4
" wide x
1
⁄
4
" thick gasket
material and peel the paper backing off for about
6" of one end.
b. Apply the sticky end onto the underside of the
fiberglass drum lid with one edge being up
against the side lip of the lid as shown in Fig. 18.
c. Complete the installation of the gasket by pulling
off the paper backing and applying the gasket until
you have circled the drum lid. Cut off any excess
gasket material where they would overlap.
STEP 14: Installing Dust Collector Hose
a. Place the drum lid from Step 13 on top of a 55
gallon steel drum (not supplied).
b. See Fig. 19. Adjust two of the three hose clamps
that were in the plastic bag to about 7
1
⁄
2
" diame-
ter. Slide one clamp over each end of hose .
Slide one end of the hose over the outlet of the
cyclone separator and tighten the clamp. Slide the
bottom end of the hose over the inlet collar of the
drum lid assembly and tighten the clamp.
STEP 15: Installing the Air Flow Diverter.
NOTE: This step is only for dust collectors
with a with a 7
1
⁄
2
horsepower motor. For 3 & 5
horsepower models, go on to STEP 16.
a. Slide the air flow diverter over the outlet of the
discharge transition
➂
with the outlet openings
pointing up and down as shown in Fig. 20.
b. Align the four holes in the diverter with the four
holes in the transition. Install four #14 x 1/2" long
sheet metal screws through the four holes and
tighten.
▲