Checking configuration
After applying new settings, please go to next URL from charge point in order to
check properly connection from the integration chosen:
http://<IP>/services/cpi/log?app=ocpp1.5
If “CB boot notification: success” appears then charge point is properly connected
to the back-end.
Otherwise if “Registering CB in the CS: failed” is shown then check following items:
-
Backend URL. Case sensitive. Check all the URL is correct.
-
Charge Point ID. Case sensitive. Check if the name entered is same as
backend expects to receive.
-
Connectivity. Check if modem is power up and connected to the HMI screen.
Ask to the backend provider if any request has been received from the charge point
(BootNotification, StatusNotification or HeartBeat) after upgrading.
Look especially for the following messages:
Summary of Contents for CCS
Page 1: ...Instruction Manual Raption 50 Series ...
Page 2: ......
Page 4: ......
Page 10: ...06 Raption 50 Series Instruction Manual C Dimensions Units specified in millimeters ...
Page 39: ...35 3 CONNECTOR DISABLE 4 CONNECTOR IN USE ...
Page 40: ...36 Raption 50 Series Instruction Manual 5 CONNECTOR RESERVED 6 CONNECTOR BLOCKED PER RESERVED ...
Page 41: ...37 7 CONNECTOR BLOCKED PER CHARGING ...
Page 43: ...39 ...