C H A P T E R
3
Installing the Device
•
Unpacking the Device, on page 15
•
Installing the Cisco 5100 ENCS, on page 15
•
Grounding the Chassis, on page 18
•
Powering On the Server, on page 19
•
Initial Server Setup, on page 19
Unpacking the Device
The device, accessory kit, publications, and any optional units may be shipped in more than one container.
When you unpack the containers, check the packing list to ensure that you have received all the items on the
list.
Only unpack the product when you are ready to install it. This will help prevent accidental damage.
Installing the Cisco 5100 ENCS
If not already installed, the DIMMs and the M.2 storage module must be installed before rack-mounting or
wall-mounting the chassis.
Only trained and qualified personnel should be allowed to install, replace, or service this equipment. Statement
1030
Warning
Rack-Mounting the Chassis
The Cisco 5100 ENCS can be installed in 19-inch (48.26-cm) racks. Use the standard brackets shipped with
the chassis for mounting the chassis in a 19-inch EIA rack.
To prevent airflow restriction, allow clearance around the ventilation openings to be at least: 1-inch (25.4-mm)
Statement 1076
Warning
You can mount the device in the following ways:
Cisco 5100 Enterprise Network Compute System Hardware Installation Guide
15