8
Connect data cables to the local and external ports.
9
Connect power cables to the PFU terminals at the top rear of the chassis.
10
Apply power to the chassis.
11
Verify that the system powers up successfully.
The actual sequence for completing some of the above procedures may be adapted to suit local requirements
and the availability of resources. For example, power cabling may be completed before circuit cards are
installed in the chassis. However, the chassis must always be grounded immediately after being mounted in
the rack or cabinet.
For personal safety and to minimize the risk of equipment damage, power must not be applied to the
chassis until all other procedures have been completed.
Caution
Required Tools and Equipment
This section lists the tools and equipment needed for installation.
Hand Tools
The following hand tools are required for installation of the chassis circuit cards and PFUs:
•
Cable/wire stripping tool
–
used to prepare the ends of power and ground cables for attachment to
two-hole lugs.
•
Knife, scissors or tin snips to cut shipping straps on the chassis container.
•
Panduit crimping tool with 4 AWG die
–
used to crimp two-hole lugs on the ends of power feed cables.
•
Phillips #2 and #1 screwdrivers
–
used to tighten thumb-screws on cards, fan trays, PFUs, and mounting
brackets.
•
7/16-inch nut driver or ratchet and socket set
–
used to connect power and return, as well as chassis
grounding cable lugs to PFU terminals.
•
Torque wrench (rated 50 in-lb [5.65 N-m]) with 7/16-inch socket for tightening lugs to power terminals.
•
Grounding wrist and/or heel straps for prevention of Electro-Static Discharge (ESD).
The inappropriate use of electric or pneumatic torque drivers, or power drill/impact drivers to loosen or
tighten fasteners may result in damage to system components.
Caution
During installation, maintenance, and/or removal, wear a grounding wrist strap connected to the ASR
5500 chassis to avoid ESD damage to the components. Failure to do so could result in damage to sensitive
electronic components and potentially void your warranty.
Caution
ASR 5500 Installation Guide
26
Installation Procedure Overview
Required Tools and Equipment
Summary of Contents for ASR 5500
Page 12: ...ASR 5500 Installation Guide xii Contents ...
Page 16: ...ASR 5500 Installation Guide xvi About this Guide Contacting Customer Support ...
Page 40: ...ASR 5500 Installation Guide 24 Technical Specifications Chassis Grounding ...
Page 74: ...ASR 5500 Installation Guide 58 Card Installation Save Shipping Cartons ...
Page 88: ...ASR 5500 Installation Guide 72 MIO Port Cabling Cleaning Fiber Optic Connectors ...
Page 112: ...ASR 5500 Installation Guide 96 System Power up show leds Command ...
Page 130: ...ASR 5500 Installation Guide 114 Initial System Configuration Additional Configuration Tasks ...
Page 164: ...ASR 5500 Installation Guide 148 Replaceable Components Returning Failed Components ...
Page 186: ...ASR 5500 Installation Guide 170 Console Port to Cisco Server Cabling Configuration ...
Page 192: ...ASR 5500 Installation Guide 176 RMA Shipping Procedures Rear Cards ...