C H A P T E R
1-1
Cisco Network Convergence System 4000 Series Hardware Installation Guide
1
Installation Roadmap
lists the steps to install the Cisco NCS 4016 chassis and its components and prepare the system
for operation. Use this table as a checklist to ensure that all components are properly installed in the
correct order. For information about a step, see the respective book or section of this installation guide.
Table 1-1
Overview of Installation Steps
Step See
Check
1.
Verify that the chassis is secured in the rack.
Note
For ease of installation, the cosmetic door should be
removed.
Cisco Network
Convergence System
4000 Series Unpacking,
Moving, and Securing
Guide
2.
Ground the chassis.
“Installing the Chassis
Ground Cable” section
on page 4-8
3.
Verify that the power components are installed.
Chapter 4, “Installing
Power Components”
4.
Verify that the ECU is installed.
Replacing the External
Connection Unit,
page 6-28
5.
Verify that the fan trays are installed.
“Replacing the Fan
Tray” section on
page 6-23
6.
Connect the AC or DC power cord.
Disconnecting AC or
DC Power, page 4-28
7.
Power on the chassis.
“Powering On the
Chassis” section on
page 4-30
8.
Install cards and remaining components in the chassis.
Chapter 5, “Installing
Route Processor Cards,
Fabric Cards, and Line
Cards”
9.
Re-install the cosmetic door.