Craft panel display cover
6
Three door latches:
Door stop latch, top and bottom (700-39150-01)
Door latch, middle (700-46854-01)
3
For each vertical cable trough
1
Align the guide pins on the rear of the vertical cable trough with the positioning holes on the front of the FCC.
2
Loosely insert eight pan-head screws, and then use the screwdriver to tighten them clockwise to attach the vertical
cable troughs firmly to the front of the FCC. You might need to use a ladder to reach the upper screws.
3
Attach two trough retention brackets to each vertical trough with two 8-32 flat-head screws (two per trough).
4
Using the captive screw, insert the trough retention brackets into each upper and lower horizontal cable troughs (two
screws per side).
Step 3
Reattach the upper and lower horizontal cable management brackets by inserting and tightening the eight pan-head
screws (four per bracket).
Step 4
Attach the three door hinges and the three door latches by using two pan-head screws each.
Step 5
Align the front door (see the following figure) with the three door hinges on the FCC. The door will then drop into
position onto the hinge attachment pins.