S e n d d o c u m e n t c o m m e n t s t o n e x u s 7 k - d o c f e e d b a c k @ c i s c o . c o m
4-7
Cisco Nexus 7000 Series Hardware Installation and Reference Guide
OL-23069-06
Chapter 4 Installing a Cisco Nexus 7018 Chassis
Installing the Chassis
Note
At least three of the screw holes on each end of the bottom-support rail align to the mounting rail. Use
at least three screws (four if possible) on each end of each bottom support rail.
Figure 4-2
Attaching a Bottom-Support Rail to a Rack
Installing the Chassis
This section describes how to install the chassis (transporting and elevating the chassis to the rack using
a mechanical lift, pushing it onto the rack, and then securing it to the rack).
This section includes the following topics:
•
Prerequisites for Installing the Chassis, page 4-7
•
Required Tools and Equipment, page 4-8
•
Installing the Chassis, page 4-9
Prerequisites for Installing the Chassis
Before you install the chassis, you must make sure that the following items are available for the
installation:
•
Data center ground is accessible where you are installing the Cisco Nexus 7018 chassis.
•
Four-post, 19-inch EIA rack or cabinet that includes such a rack.
For more information on the rack or cabinet, see the
“Installing a Four-Post Rack or Cabinet” section
.
1
Four sets of four M6 x 19 mm Phillips screws or
four sets of four 12-24 x 3/4 in. Phillips screws
2
Adjustable bottom-support rails (2)