12-8
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
September 2005
Chapter 12 Add and Remove Cards and Nodes
NTP-G129 Add a DWDM Node
Step 4
In network view, click the
Circuits
tab.
Step 5
Identify the OCHNCs that are carried on the fiber span that you identified in
in both the
east-to-west and west-to-east directions.
Step 6
If the OCHNC circuit is on the active path and is protected by a splitter or Y-cable protection group,
complete the
“DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch” task on page 10-35
force traffic away from the span where the node will be added. If not, continue with
.
Step 7
For each circuit identified in
that was not switched in
(unprotected circuits), complete the
following steps:
a.
Select the circuit and click
Edit
.
b.
In the Edit Circuit dialog box, click the
State
tab.
c.
In the Target Circuit Admin State field, choose choose
OOS,DSBLD
(ANSI) or
Locked,disabled
(ETSI).
Step 8
Remove the fibers from the cards at the adjacent nodes that will connect to the new node.
Step 9
At the node that will be added, complete the following procedures and tasks:
•
NTP-G22 Verify Common Card Installation, page 3-4
•
NTP-G26 Set Up CTC Network Access, page 3-11
•
NTP-G30 Install the DWDM Cards, page 3-39
•
NTP-G36 Calculate Cable Connections, page 3-80
•
NTP-G138 Import a Cisco MetroPlanner Configuration File, page 3-82
•
NTP-G37 Run Automatic Node Setup, page 3-83
•
Node acceptance tests in
Chapter 4, “Perform Node Acceptance Tests”
Step 10
Create cross-connects on the new node for all circuits identified in
:
a.
From the Tools menu, choose
Open TL1 Session
.
b.
In the Select Node dialog box, choose the new node and click
OK
.
c.
In the TL1 dialog box, use the
ENT-WLEN
command to create the OCHNC cross-connects for each
unprotected pass-through circuit as follows:
ENT-WLEN:[<TID>]:<AID>:<CTAG>:::[SIZE=<SIZE>]:[<PST>],[<SST>];
where:
–
<AID> is the wavelength AID.
–
<SIZE> is the circuit size allocated on this wavelength.
–
<PST> is the primary state.
–
<SST> is the secondary state.
For additional information and a list of valid command values, see the
Cisco ONS SONET TL1
Command Guide
or the
Cisco ONS 15454 SDH TL1 Command Guide.
d.
Close the TL1 dialog box.
e.
Repeat
to change the circuits placed in OOS-DSLBD or Locked,disabled back in service by
choosing
IS,AINS
(ANSI) or
Unlocked,automaticInService
(ETSI).in the Target Circuit Admin
State field.
Step 11
Complete the
“DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch” task on
for the circuits that were switched in
Summary of Contents for ONS 15454 DWDM
Page 38: ...Figures xxxviii Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 54: ...Procedures liv Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 64: ... 64 Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 Chapter ...