12-10
Cisco ONS 15454 DWDM Installation and Operations Guide, R6.0
September 2005
Chapter 12 Add and Remove Cards and Nodes
NTP-G130 Remove a DWDM Node
Step 5
If OCHNC circuits pass through the node to be removed on the active path and are protected by a splitter
or Y-cable protection group, navigate to a node connected to the node that will be removed and complete
the
“DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch” task on page 10-35
. Otherwise,
continue with
.
Step 6
Complete the following steps for each circuit identified in
that was not switched in
:
a.
Select the circuit and click
Edit
.
b.
In the Edit Circuit dialog box, click the
State
tab.
c.
In the Target Circuit Admin State field, choose
OOS,DSBLD
(ANSI) or
Locked,disabled
(ETSI).
Step 7
Delete the cross-connects on the node that will be removed for each circuit placed in the OOS-DSLBD
or Locked,disabled state in
a.
From the Tools menu, choose
Open TL1 Session
.
b.
In the Select Node dialog box, select the new node and click
OK
.
c.
In the TL1 dialog box, use the
DLT-WLEN
command to delete the OCHNC cross-connects for each
unprotected pass-through circuit as follows:
DLT-WLEN:[<TID>]:<AID>:<CTAG>:::[SIZE=<SIZE>]:[<PST>],[<SST>];
where:
–
<AID> is the wavelength AID.
–
<SIZE> is the circuit size allocated on this wavelength.
–
<PST> is the primary state.
–
<SST> is the secondary state.
For additional information and a list of valid command values, see the
Cisco ONS SONET TL1
Reference Guide
or the
Cisco ONS 15454 SDH TL1 Reference Guide.
d.
Close the TL1 dialog box.
e.
Repeat
to change the circuits placed in OOS-DSLBD back in service by changing the Target
circuit Admin State field to
IS,AINS
(ANSI) or
Unlocked,automaticInService
(ETSI).
Step 8
Complete the
“DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch” task on
for the circuits that were switched in
Step 9
Complete the
“DLP-G106 Delete Optical Channel Network Connections” task on page 7-12
to delete
circuits identified in
that will terminate (add/drop) on the new DWDM node.
Step 10
Complete the
“DLP-G105 Provision DWDM Optical Channel Network Connections” task on page 7-10
to recreate circuits identified in
that will terminate on the new DWDM node. Choose the new
DWDM node as the start/end (add/drop, respectively) for each circuit.
Step 11
Complete the
“DLP-G105 Provision DWDM Optical Channel Network Connections” task on page 7-10
to create new circuits that originate or terminate in the new DWDM node.
Stop
.
You have completed this procedure
.
Summary of Contents for ONS 15454 DWDM
Page 38: ...Figures xxxviii Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 54: ...Procedures liv Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 64: ... 64 Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 Chapter ...