Chapter 4 Perform Node Acceptance Tests
DLP-G82 Verify the OSC-CSM Power
DLP-G82 Verify the OSC-CSM Power
Step 1
Display the OSC-CSM card in card view.
Step 2
Click the
Provisioning > Optical Line > Parameters
tabs.
Step 3
If an OPT-PRE is not installed on the same side of the shelf as the OSC-CSM, verify that the Port 3
Power value is higher than the default no-power value of –30 dBm. If the power is not higher than
–30 dBm, contact your next level of support.
Step 4
Return to your originating procedure (NTP).
DLP-G83 Verify the OSC-CSM Power on OADM Nodes
Step 1
Display the OSC-CSM card in card view.
Step 2
Click the
Provisioning > Optical Line > Parameters
tabs.
Step 3
Verify that the Power value for Port 3 is higher than the default no-power value of –30 dBm. The
calculated expected power value for Port 3 is:
Pout COM TX of last AD-xy-xx.x – IL02 OSC-CSM (COM RX > LINE TX) – 10 dB (bulk attenuator)
Step 4
Double-check the value.
Note
Actual output power is affected by many factors. Always consider the calculated expected power
to be a general guideline and not a precise value.
Step 5
Return to your originating procedure (NTP).
Purpose
This task verifies the OSC-CSM card power.
Tools/Equipment
None
Prerequisite Procedures
DLP-G46 Log into CTC, page 2-25
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Superuser
Purpose
This task verifies the OSC-CSM card power on OADM nodes.
Tools/Equipment
None
Prerequisite Procedures
DLP-G46 Log into CTC, page 2-25
Required/As Needed
As needed
Onsite/Remote
Onsite or remote
Security Level
Superuser
Summary of Contents for ONS 15454 DWDM
Page 38: ...Figures xxxviii Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 54: ...Procedures liv Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 ...
Page 64: ... 64 Cisco ONS 15454 DWDM Installation and Operations Guide R6 0 August 2005 Chapter ...