Stop. You have completed this procedure.
NTP-G329 Remove the Deep-Front Panel of the ONS 15454 M6
Shelf
This procedure removes the deep-front panel of the ONS 15454 M6 system.
Purpose
• #2 Phillips Dynamometric screwdriver
• Socket (6/32 standard) and socket wrench to tighten or loosen the ground
nut
Tools/Equipment
•
NTP-G252 Install the ONS 15454 M6 Shelf , on page 294
•
NTP-G327 Install the Deep-Front Panel of the ONS 15454 M6 Shelf, on
page 332
• Connect the chassis to the office ground. For detailed instructions on how
to ground the chassis, see the
Electrostatic Discharge and Grounding Guide
for Cisco CPT and Cisco ONS Platforms
.
Prerequisite Procedures
Required
Required/As Needed
Onsite
Onsite/Remote
None
Security Level
The deep-front panel does not have a hinge and cannot be rotated like a standard door. Rotating the deep-front
panel can damage the deep-front panel, shelf hinges, other devices and cables placed below the ONS 15454
M6 shelf.
Caution
When the deep front-panel is installed, the total chassis depth is 12.9 inches. The deep front-panel extends
from the rack by 1.8 inches.
Note
Procedure
Step 1
Remove the end of the ground strap cable that is connected to the exterior of the deep-front panel (see the
following figure).
Cisco ONS 15454 Hardware Installation Guide
339
Installing the ONS 15454 M6 Shelf
NTP-G329 Remove the Deep-Front Panel of the ONS 15454 M6 Shelf
Summary of Contents for ONS 15454
Page 2: ... 2019 Cisco Systems Inc All rights reserved ...
Page 16: ...Cisco ONS 15454 Hardware Installation Guide xvi Contents ...
Page 28: ...Cisco ONS 15454 Hardware Installation Guide xxviii Preface Preface ...
Page 36: ...Cisco ONS 15454 Hardware Installation Guide 6 Overview Cisco ONS 15454 M6 Shelf ...
Page 510: ...Cisco ONS 15454 Hardware Installation Guide 480 Hardware Specifications Dimensions ...