1-36
Cisco ONS 15454 DWDM Procedure Guide, Release 9.2
78-19286-01
Chapter 1 Install the Cisco ONS 15454 Shelf Assembly
Required Tools and Equipment (ETSI)
Note
If the system loses power or if both TCC2/TCC2P/TCC3 cards are reset, you must reset the
ONS 15454 ETSI clock. After powering down, the date defaults to January 1, 1970, 00:04:15. To reset
the clock, see the
“NTP-G24 Set Up Name, Date, Time, and Contact Information” procedure on
Step 1
Verify that the MIC-A/P FMEC is installed in Slot 23 and the MIC-C/T/P FMEC is installed in Slot 24 of the
EFCA.
Step 2
Attach the connector on the end of the power cable to the power FMEC.
Step 3
Tighten the screws of the connector on the power cable.
Step 4
Connect the power cable to the fuse panel or power source. Use the pin connections in
. If the
green-yellow cable is included in the power cable, it must be connected to ground.
Step 5
Return to your originating procedure (NTP).
Table 1-1
Pin Connection of the Power FMECs
Pin
Function
Cable Color
A1
Battery return
Black
A2
–48 V battery
Red
A3
Ground
Green with yellow stripes
Summary of Contents for ONS 15454
Page 48: ...Tables xlviii Cisco ONS 15454 DWDM Procedure Guide Release 9 2 78 19286 01 ...
Page 58: ...Procedures lviii Cisco ONS 15454 DWDM Procedure Guide Release 9 2 78 19286 01 ...
Page 78: ...Tasks lxxviii Cisco ONS 15454 DWDM Procedure Guide Release 9 2 78 19286 01 ...
Page 85: ...lxxxv Cisco ONS 15454 DWDM Procedure Guide Release 9 2 78 19286 01 Preface ...
Page 87: ...lxxxvii Cisco ONS 15454 DWDM Procedure Guide Release 9 2 78 19286 01 Preface ...