DLP-G563 Mounting the Air Deflectors (Front-to-Front) on the ONS 15454 M6
Shelf for ETSI Rack Configuration

This task installs the air deflectors (front-to-front) on the ONS 15454 M6 shelf
for ETSI rack configuration.

The air deflectors can be installed only in the front position of the
chassis.

Note

Purpose

• #2 Phillips Dynamometric screwdriver
• Medium slot-head screwdriver
• Small slot-head screwdriver

Tools/Equipment

NTP-G305 Unpack and Inspect the ONS 15454, ONS 15454 M2, and ONS 15454
M6 Shelves, on page 20

Prerequisite Procedures

As needed

Required/As Needed

Onsite

Onsite/Remote

None

Security Level

Use only the fastening hardware provided with the ONS 15454 M6 to prevent loosening, deterioration, and
electromechanical corrosion of the hardware and joined material.

Caution

Procedure

Step 1

Place the right front air deflector flush against the right side of the chassis (see the following figure).

Step 2

Align the screw holes on the right front air deflector with the screw holes on the right side of the chassis.

Figure 206: Mounting the Air Deflectors (Front-to-Front) on the ONS 15454 M6 Shelf for ETSI Rack Configuration

Step 3

Insert the screws and tighten them to a torque value of 11.5 in-lb (1.3 N-m).

Step 4

Place the left front air deflector flush against the left side of the chassis.

Do not mount the left front deflector (exhaust air deflector), if these cards are to be installed in the ONS 15454
M6 shelf:

Cisco ONS 15454 Hardware Installation Guide

306

Installing the ONS 15454 M6 Shelf

DLP-G563 Mounting the Air Deflectors (Front-to-Front) on the ONS 15454 M6 Shelf for ETSI Rack Configuration

Summary of Contents for ONS 15454

Page 1: ...stallation Guide First Published 2016 11 26 Last Modified 2019 10 04 Americas Headquarters Cisco Systems Inc 170 West Tasman Drive San Jose CA 95134 1706 USA http www cisco com Tel 408 526 4000 800 553 NETS 6387 Fax 408 527 0883 ...

Page 2: ... 2019 Cisco Systems Inc All rights reserved ...

Page 3: ...Overview 1 C H A P T E R 1 Compliance Standards 1 Cisco ONS 15454 ANSI 1 Cisco ONS 15454 ETSI 2 Cisco ONS 15454 M2 Shelf 2 Cisco ONS 15454 M6 Shelf 4 Preparing to Install the ONS 15454 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf 7 C H A P T E R 2 Important Safety Recommendations 7 Required Tools and Equipment 9 Cisco Supplied Materials 9 User Supplied Materials 11 Ordering Solutions for ONS ...

Page 4: ... Shelf 31 DLP G3 Reverse the Mounting Bracket to Fit a 19 inch 482 6 mm Rack ANSI Only 33 DLP G4 Install the External Brackets and Air Filter ANSI Only 34 DLP G678 Mount the ONS 15454 Shelf in a Rack One Person 36 DLP G679 Mount the ONS 15454 Shelf in a Rack Two People 37 DLP G680 Mount Multiple ONS 15454 Shelf Assemblies in a Rack 39 DLP G8 Install the Air Ramp 42 Front Door 45 ONS 15454 ANSI Bac...

Page 5: ...Tray Assembly 82 ONS 15454 ANSI Alarm Expansion Panel 85 NTP G9 Install the Alarm Expansion Panel ANSI Only 91 ONS 15454 ANSI Alarm Timing LAN and Craft Pin Connections 94 Alarm Contact Connections 97 Timing Connections 98 LAN Connections 98 TL1 Craft Interface Installation 99 NTP G10 Attach Wires to Alarm Timing LAN and Craft Pin Connections 100 DLP G20 Install Alarm Wires on the MIC A P ETSI Onl...

Page 6: ...G309 Install the MS ISC 100T Card 136 Multishelf Management 137 Multishelf LAN Topologies 137 ONS 15454 Multishelf Node and Subtending Shelves 138 ONS 15454 Multishelf Node and Subtending Shelves Upgrade 138 NTP G301 Connect the ONS 15454 Multishelf Node and Subtending Shelves to an MS ISC 100T Card 138 NTP G304 Configure the MS ISC 100T Card for a ONS 15454 Multishelf Node for Non Default Public ...

Page 7: ...r Storage Tray 173 Fiber Management Using the Optional ANSI Tie Down Bar 175 Installing the ONS 15454 M2 Shelf 177 C H A P T E R 4 Installing the ONS 15454 M2 Shelf 177 ANSI Rack Installation 177 Mounting Brackets 178 Mounting a Single Node 179 ETSI Rack Installation 179 Mounting a Single Node 180 Wall Mounting the ONS 15454 M2 Shelf 180 Desktop Mounting the ONS 15454 M2 Shelf 181 Air Deflector 18...

Page 8: ...54 M2 Shelf on a Rack One Person 209 DLP G590 Mount the ONS 15454 M2 Shelf on the Wall 211 DLP G591 Mount the ONS 15454 M2 Shelf on the Desktop 214 Front Door 215 NTP G269 Install the Standard Door of the ONS 15454 M2 Shelf 216 NTP G270 Open and Remove the Standard Door of the ONS 15454 M2 Shelf 218 DLP G594 Open the Standard Door of the ONS 15454 M2 Shelf 219 DLP G595 Remove the Standard Door of ...

Page 9: ... 261 NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card 261 DLP G604 Install the TNC TNCE TSC or TSCE Card 262 DLP G605 Provision PPM and Port for the TNC and TNCE Cards 265 DLP G606 Configure UDC and VoIP for the TNC and TNCE Cards 266 NTP G275 Perform the ONS 15454 M2 Shelf Installation Acceptance Test 267 DLP G601 Inspect the ONS 15454 M2 Shelf Installation and Connections 268 DLP G60...

Page 10: ... Deflectors Front to Front on the ONS 15454 M6 Shelf for ETSI Rack Configuration 306 DLP G564 Mounting the Bracket with Air Deflectors Front to Back on the ONS 15454 M6 Shelf for ETSI Rack Configuration 307 DLP G565 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M6 Shelf for ETSI Rack Configuration 309 DLP G821 Mounting the Bracket with Air Deflectors Front to Side on the O...

Page 11: ...le 359 DLP G570 Install the DC Power Module in the ONS 15454 M6 Shelf 360 DLP G737 Replacing 15454 M6 DC With 15454 M6 DC20 Power Module 363 DLP G738 Replacing 15454 M6 DC20 With 15454 M6 DC Power Module 365 LCD Unit 366 NTP G255 Install the LCD Module in the ONS 15454 M6 Shelf 366 Power and Ground Description 368 ANSI Power and Ground 368 ETSI Power and Ground 369 NTP G256 Install Power and Groun...

Page 12: ...S 15454 in a Mixed Multishelf Configuration 409 DLP G682 Connect the ONS 15454 M6 as the Node Controller in a Mixed Multishelf Configuration Using the Catalyst 3560 410 DLP G729 Connect the ONS 15454 M6 as the Node Controller in a Mixed Multishelf Configuration without a Catalyst Switch 413 DLP G683 Connect the ONS 15454 as the Node Controller in a Mixed Multishelf Configuration 415 NTP G310 Upgra...

Page 13: ...5 DLP G261 Clean Multi Fiber Optic Cable Connectors 446 DLP G262 Clean Fiber Connectors with CLETOP 447 DLP G263 Clean the Fiber Adapters 447 NTP G40 Replace the Front Door 448 NTP G116 Replace the Fan Tray Assembly of the ONS 15454 Shelf Assembly 450 NTP G272 Replace the Fan Tray Assembly of the ONS 15454 M2 Shelf Assembly 456 NTP G260 Replace the Fan Tray Assembly of the ONS 15454 M6 Shelf Assem...

Page 14: ...face 472 Modem Interface 472 Alarm Interface 472 Passive Unit Remote Inventory 472 BITS Interface 472 System Timing 472 System Power 473 Fan Tray 473 System Environmental Specifications 473 Dimensions 474 ONS 15454 M6 Shelf Specifications 474 Bandwidth 474 Configurations 474 Cisco Transport Controller 475 External LAN Interface for EMS 475 TL1 Craft Interface 475 Modem Interface 475 Alarm Interfac...

Page 15: ...ons 476 DC Power Specifications 476 Power Supply Modules Supported by ONS 15454 M6 ECU S 478 Power Calculation 478 Fan Tray 479 System Environmental Specifications 479 Dimensions 479 Cisco ONS 15454 Hardware Installation Guide xv Contents ...

Page 16: ...Cisco ONS 15454 Hardware Installation Guide xvi Contents ...

Page 17: ...ller in multi shelf configuration from R10 5 2 6 Hence it is recommended to use TCC3 card as the node controller in multi shelf configuration However the TCC2 TCC2P cards can be used as a subtended controller and also in a stand alone configuration Note This section explains the objectives intended audience and organization of this publication and describes the conventions that convey instructions...

Page 18: ...nect the ONS 15454 M6 as the Node Controller in a Mixed Multishelf Configuration in chapter Install the Cisco ONS 15454 M6 Shelf September 2010 Added a note in the chapter Installing the ONS 15454 ANSI and ETSI Shelf Added two notes and a step in DLP G18 Connect Office Power to the ONS 15454 ANSI of the chapter Installing the ONS 15454 ANSI and ETSI Shelf Updated step 1 in DLP G19 Turn On and Veri...

Page 19: ... Wires to Timing LAN and Craft Pin Connections in ONS 15454 M2 in chapter Install the Cisco ONS 15454 M2 Shelf June 2011 Added additional information in the External LAN Interface for EMS section in appendix Hardware Specifications Updated the values for total maximum power consumption ONS 15454 M6 in the section System Power of the appendix Hardware Specifications Updated the Alarm Connectors sec...

Page 20: ... ONS 15454 Multishelf Configuration using the ONS 15454 M6 in the chapter Installing the ONS 15454 M6 Shelf June 2012 Added a section Cooling Profile in the chapter Installing the ONS 15454 M6 Shelf Updated the section Multishelf LAN Topologies in the chapter Installing the ONS 15454 M6 Shelf July 2012 Updated the table Multishelf LAN Topologies in Cisco ONS 15454 M6 and Cisco ONS 15454 in the cha...

Page 21: ...the ONS 15454 M6 DLP G687 Upgrade the ONS 15454 Multishelf with the Catalyst 2950 Switch Configuration DLP G688 Upgrade the ONS 15454 Multishelf with MS ISC Card Configuration NTP G264 Perform the ONS 15454 M6 Shelf Installation Acceptance Test Updated the figures Mixed Multishelf Configuration with the ONS 15454 M6 as the Node Controller and Mixed Multishelf Configuration with the ONS 15454 as th...

Page 22: ... was generated April 2014 Added information for the 15454 M6 DC40 power module December 2014 Added a note to the section Alarm Connectors in the chapter Installing the ONS 15454 M6 Shelf June 2015 Updated for R10 5 2 January 2016 Added the following note Due to memory limitations TCC2 TCC2P cards are not supported as the node controller in multi shelf configuration from R10 5 2 6 Hence it is recom...

Page 23: ...Line Card Configuration Guide Cisco ONS 15454 DWDM Network Configuration Guide Installing the Cisco ONS 15454 M2 and ONS 15454 M6 Passive Optical Modules Regulatory Compliance and Safety Information for Cisco ONS Products Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Installing the GBIC SFP SFP QSFP XFP CXP CFP and CPAK Optical Modules in Cisco ONS Platforms Cis...

Page 24: ...he end of each warning to l its translation in the translated safety warnings that accompanied this device Statement 1071 SAVE THESE INSTRUCTIONS Warning BELANGRIJKE VEILIGHEIDSINSTRUCTIES Dit waarschuwingssymbool betekent gevaar U verkeert in een situatie die lichamelijk letsel kan veroorz Voordat u aan enige apparatuur gaat werken dient u zich bewust te zijn van de bij elektrische schakel betrok...

Page 25: ...te alla fine di ciascuna avvertenza per individuare le traduzioni delle avvertenze riportate in documento CONSERVARE QUESTE ISTRUZIONI Avvertenza VIKTIGE SIKKERHETSINSTRUKSJONER Dette advarselssymbolet betyr fare Du er i en situasjon som kan føre til skade på person Før du b å arbeide med noe av utstyret må du være oppmerksom på farene forbundet med elektriske kretser o til standardprosedyrer for ...

Page 26: ...trustning måste du vara medveten om farorna med elkretsar och känna till van förfaranden för att förebygga olyckor Använd det nummer som finns i slutet av varje varning för att dess översättning i de översatta säkerhetsvarningar som medföljer denna anordning SPARA DESSA ANVISNINGAR Varning Cisco ONS 15454 Hardware Installation Guide xxvi Preface Preface ...

Page 27: ... acompanham o dispositivo Warning GUARDE ESTAS INSTRUÇÕES Warning Aviso Warning VIGTIGE SIKKERHEDSANVISNINGER Warning Dette advarselssymbol betyder fare Du befinder dig i en situation med risiko for legemesbeskadigelse Før du begynder arbejde på udstyr skal du være opmærksom på d involverede risici der er ved elektriske kredsløb og du skal sætte dig ind i standardproc til undgåelse af ulykker Brug...

Page 28: ...Cisco ONS 15454 Hardware Installation Guide xxviii Preface Preface ...

Page 29: ... also includes translations of the safety warnings that appear in the Cisco ONS 15454 system documentation Obtaining Documentation Obtaining Support and Security Guidelines For information on obtaining documentation submitting a service request and gathering additional information see the monthly What s New in Cisco Product Documentation which also lists all new and revised Cisco technical documen...

Page 30: ...Cisco ONS 15454 Hardware Installation Guide xxx Preface Obtaining Documentation Obtaining Support and Security Guidelines ...

Page 31: ... States National Fire Protection Association NFPA 70 United States National Electrical Code Canada Canadian Electrical Code Part I CSA C22 1 Other countries If local and national electrical codes are not available refer to IEC 364 Part 1 through Part 7 Cisco ONS 15454 ANSI When installed in an equipment rack the ONS 15454 ANSI assembly is typically connected to a fuse and alarm panel to provide ce...

Page 32: ...y assembly and fiber storage area The FMEC cover at the top of the shelf allows access to power connectors external alarms and controls timing input and output and craft interface terminals You can mount the ONS 15454 ETSI in an ETSI rack The shelf weighs approximately 26 kg 57 pounds with no cards installed The shelf includes a front door and a Front Mount Electrical Connection FMEC cover for add...

Page 33: ...82 6 or 584 2 mm or on a 600 x 600 mm 23 6 x 23 6 inch or 600 x 300 mm 23 6 x 11 8 inch ETSI standard equipment rack The ONS 15454 M2 shelf can also be wall mounted or desktop mounted The shelf weighs approximately 11 02 pounds 5 kg with no cards installed It is mandatory that the correct type of 19 inch ANSI rack is chosen to mount the ONS 15454 M2 shelf The recommended shape of the rack post is ...

Page 34: ...54 M6 shelf allows access to the shelf fan tray assembly fiber routing area power connectors external alarms and controls timing input and output and craft interface terminals Two types of front doors can be attached to the ONS 15454 M6 shelf the standard door and the deep door The front door provides access to the shelf and acts as a protective panel The deep door provides additional space in fro...

Page 35: ...ls as shown in Figure 2 19 inch Rack Opening for Air Flow on page 4 When installed in an equipment rack the Cisco ONS 15454 M6 shelf is typically connected to a fuse and alarm panel to provide centralized alarm connection points and distributed power for the ONS 15454 M6 Fuse and alarm panels are third party equipment and are not described in this documentation If you are unsure about the requirem...

Page 36: ...Cisco ONS 15454 Hardware Installation Guide 6 Overview Cisco ONS 15454 M6 Shelf ...

Page 37: ...S 15454 M6 or NCS 20015 chassis The TCC2P card can also be used as a node controller in a stand alone configuration Note Important Safety Recommendations on page 7 Required Tools and Equipment on page 9 Ordering Solutions for ONS 15454 M2 and ONS 15454 M6 on page 15 Card Slot Requirements on page 15 NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Importan...

Page 38: ...ould be handled according to all national laws and regulations Statement 1040 Warning A readily accessible two poled disconnect device must be incorporated in the fixed wiring Statement 1022 Warning The ONS 15454 ONS 15454 M2 and ONS 15454 M6 are suitable for mounting on concrete or other noncombustible surfaces only Note In this chapter shelf refers to the steel enclosure that holds cards and con...

Page 39: ...rdered a temporary front door is preinstalled Note Table 1 Cisco Supplied Materials Required to Install ONS 15454 M6 ONS 15454 M2 ONS 15454 Cisco Supplied Material ANSI Sheet metal backplane cover installed 1 Backplane Cover ANSI RJ LAN bracket 1 ANSI RJ LAN bracket 1 ANSI External bottom brackets for the fan tray air filter ETSI Bottom brackets for the fan tray air filter Brackets ANSI RJ LAN cab...

Page 40: ... 6 AWG multistrand copper wire 1 Double hole grounding lug for ground connection with a wire receptacle to accommodate the recommended 13 3 mm 6 AWG multistrand copper wire angled at 45 degree 1 ETSI Double hole grounding lug for ground connection with a wire receptacle to accommodate the recommended 13 3 mm 6 AWG multistrand copper wire 1 Grounding Lug ANSI Pinned hex Allen key for front door 1 E...

Page 41: ...head Phillips screws 8 Screws ANSI Spacers 50 1193 XX 4 Spacers ANSI Standoff kit 53 0795 XX Plastic fiber management guides 2 Fan filter bracket screws 53 48 0003 6 Standoff Kit Tie wraps 10 Tie wraps 10 ANSI Tie Wraps 10 ETSI Tie wraps 0 125 inch 3 2 mm W x 6 0 inch 152 mm L 24 Tie Wraps Only use the power cables that are designed to be used with the ONS 15454 ANSI or ETSI the ONS 15454 M2 or ON...

Page 42: ... or 24 AWG 0 51 mm or 0 64 mm solid tinned 100 ohm shielded building integrated timing supply BITS clock cable pair 22 or 24 AWG 0 51 mm or 0 64 mm twisted pair T1 type ETSI Copper ground cable 13 3 mm 6 AWG stranded specified for up to 90 degrees Celsius 194 degrees Fahrenheit Alarm cable pairs for all alarm connections 0 51 mm or 0 64 mm 22 or 24 AWG solid tinned ANSI Power cable from fuse and a...

Page 43: ...conductors Connectors Crimping tool This tool must be large enough to accommodate the girth of the grounding lug when you crimp the grounding cable into the lug Crimping tool This tool must be large enough to accommodate the girth of the grounding lug when you crimp the grounding cable into the lug Crimping tool This tool must be large enough to accommodate the girth of the grounding lug when you ...

Page 44: ...ordia GR 63 CORE 584 2 mm rack total width 26 inches 660 4 mm ETSI Equipment rack ETSI rack 2200 mm 86 6 inch H x 600 mm 23 6 inch Wx 300 mm 11 8 inch D Rack 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screw driver 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screw driver 2 Phillips Dynamometric screwdriver Medium slot head s...

Page 45: ...e ONS 15454 M2 shelf Note Two ordering solutions for the Cisco ONS 15454 M6 shelf are offered Select one of these solutions Shelf assembly that is preinstalled with all the ancillary units such as fan tray assembly LCD unit power module and ECU or ECU2 Shelf assembly that is not preinstalled with the ancillary units but can be ordered separately Card Slot Requirements The cards have electrical plu...

Page 46: ...he ONS 15454 ANSI The following figure shows card installation in the ONS 15454 ETSI shelf Cisco ONS 15454 Hardware Installation Guide 16 Preparing to Install the ONS 15454 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf ONS 15454 ...

Page 47: ...tall in them Each ONS 15454 card has a corresponding symbol The symbol on the card must match the symbol on the slot The following table shows the slot and card symbol definitions Table 3 Slot and Card Symbols Definition Symbol Color Shape Slots 1 to 6 and 12 to 17 Only install cards with a circle symbol on the faceplate Orange Circle Slots 5 6 12 and 13 Only install cards with circle or a triangl...

Page 48: ...ds TNC TNCE TSC TNCS 2 TNCS 2O or TSCE Slot 2 and Slot 3 are dedicated for common line cards The ONS 15454 M2 shelf must be equipped with a TNC TNCE TSC TNCS 2 TNCS 2O or TSCE card Caution Shelf slots have symbols indicating the type of cards that you can install in them Each ONS 15454 M2 card has a corresponding symbol The symbol on the card must match the symbol on the slot Figure 5 Slot Symbols...

Page 49: ... symbol on the faceplate Purple Square Slots 2 to 7 Install cards only with a circle symbol on the faceplate Orange Circle Slots 2 to 7 New line cards with high speed backplane connectors Orange Hollow Circle Slots 4 and 5 New Uplink card Pink Pentagon When the ONS 15454 M6 shelf is powered at 60 VDC nominal only TNC OPT AMP C OPT AMP 17 C OPT EDFA 17 OPT EDFA 24 and 15454 M6 ECU 60 can be install...

Page 50: ...elves and verify their contents Purpose Pinned hex Allen key for front door ONS 15454 only Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Complete the DLP G676 Unpack and Verify the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Step 2 Complete the DLP G677 Inspect the ONS 15454 ONS 15454 M2 and ONS 154...

Page 51: ... separately then the power modules LCD module ECU or ECU2 module fan tray assembly and mounting brackets are shipped separately Note Step 5 Return to your originating procedure NTP DLP G677 Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves This task verifies that all parts of the shelf are in good condition Purpose Pinned hex Allen key for front door Tools Equipment DLP G676 Unpack and V...

Page 52: ...replacement Step 4 ONS 15454 only Close the front door before installing Step 5 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 22 Preparing to Install the ONS 15454 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf DLP G677 Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves ...

Page 53: ...tallation on page 24 ONS 15454 ETSI Rack Installation on page 27 NTP G306 Install the ONS 15454 Shelf on page 31 Front Door on page 45 ONS 15454 ANSI Backplane Covers on page 53 NTP G3 Open and Remove the Front Door on page 56 NTP G4 Open and Remove the FMEC Cover ETSI Only on page 60 NTP G5 Remove the Backplane Covers ANSI Only on page 63 ONS 15454 ETSI Front Mount Electrical Connection on page 6...

Page 54: ...gement on page 157 ONS 15454 ANSI Rack Installation The ONS 15454 ANSI shelf is mounted in a 19 or 23 in 482 6 or 584 2 mm equipment rack The shelf projects five inches 127 mm from the front of the rack It mounts in both Electronic Industries Alliance EIA standard and Telcordia standard racks The shelf is a total of 17 inches 431 8 mm wide with no mounting ears attached Ring runs are not provided ...

Page 55: ...ame with a nonconductive coating such as paint lacquer or enamel either use the thread forming screws provided with the ONS 15454 ANSI shipping kit or remove the coating from the threads to ensure electrical continuity Caution The shelf comes preset for installation in a 23 inch 584 2 mm rack but you can reverse the mounting bracket to fit the smaller 19 inch 482 6 mm rack Cisco ONS 15454 Hardware...

Page 56: ...four ONS 15454 ANSI shelves and a fuse and alarm panel However unequal flange racks are limited to three ONS 15454 ANSI shelves and a fuse and alarm panel or four ONS 15454 ANSI shelves using a fuse and alarm panel from an adjacent rack If you are using the external bottom brackets to install the fan tray air filter you can install three shelf assemblies in a standard seven foot 2 133 m rack If yo...

Page 57: ...high 535 mm 21 06 inches wide and 280 mm 11 02 inches deep You can install up to three ONS 15454 ETSI shelves in a seven foot 2133 6 mm equipment rack The ONS 15454 ETSI must have one inch 25 4 mm of airspace below the installed shelf to allow air flow to the fan intake If a second ONS 15454 ETSI is installed below the first shelf an ETSI air ramp unit must be assembled between the two shelves to ...

Page 58: ...ed above a shelf the air ramp between the shelves provides space for air flow To ensure the mounting is secure use two to four M6 mounting screws for each side of the shelf A shelf should be mounted at the bottom of the rack if it is the only unit in the rack The following figure shows the rack mounting position for the ONS 15454 ETSI shelf Cisco ONS 15454 Hardware Installation Guide 28 Installing...

Page 59: ...t door can also be removed to lighten the shelf Mounting Multiple Nodes Most standard Telcordia GR 63 CORE 23 inch 584 2 mm seven foot 2 133 mm racks can hold three ONS 15454 ETSI shelves two air ramps and a fuse and alarm panel The following figure shows a three shelf ONS 15454 ETSI bay assembly Cisco ONS 15454 Hardware Installation Guide 29 Installing the ONS 15454 M12 ANSI and ETSI Shelf Mounti...

Page 60: ... wiring regulations Statement 1045 Warning This product relies on the building s installation for short circuit overcurrent protection Ensure that the protective device is rated not greater than 10A 20A 100 240 VAC Statement 1005 Warning To prevent the system from overheating do not operate it in an area that exceeds the maximum recommended ambient temperature of 45 degrees C 113 degrees F Stateme...

Page 61: ... must have 1 inch 25 4 mm of airspace below the installed shelf assembly to allow air flow to the fan intake The air ramp the angled piece of sheet metal on top of the shelf assembly provides this spacing and should not be modified in any way Statement 385 Warning Voltages that present a shock hazard may exist on Power over Ethernet PoE circuits if interconnections are made using uninsulated expos...

Page 62: ... with the 19 inch 482 6 mm mounting brackets that shipped in the ship kit Note Procedure Step 1 ANSI shelves only Complete the DLP G3 Reverse the Mounting Bracket to Fit a 19 inch 482 6 mm Rack ANSI Only on page 33 if you need to convert from a 23 inch 584 2 mm to a 19 inch 482 6 mm rack Step 2 ANSI shelves only To install the air filter on the bottom of the shelf rather than below the fan tray as...

Page 63: ...hip kit or remove the coating from the threads to ensure electrical continuity Caution Procedure Step 1 Remove the screws that attach the mounting bracket to the side of the shelf Step 2 Flip the detached mounting bracket upside down Text imprinted on the mounting bracket will now also be upside down Step 3 Place the widest side of the mounting bracket flush against the shelf see Figure 12 Reversi...

Page 64: ... This task applies to the ONS 15454 ANSI shelf only Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment DLP G3 Reverse the Mounting Bracket to Fit a 19 inch 482 6 mm Rack ANSI Only on page 33 if applicable Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level To install the air filter inside th...

Page 65: ...racing facing up to preserve the surface of the filter You must install the air filter with the metal bracing facing up with 15454 CC FTA Caution Step 2 Locate the three screw holes that run along the left and right sides of the bottom of the shelf Step 3 Secure each bracket to the bottom of the shelf using the screws 48 0003 provided in the backplane standoff kit 53 0795 XX Each bracket has a fil...

Page 66: ...o allow air flow to the fan intake If a second ONS 15454 ETSI is installed above a shelf the air ramp between the shelves provides space for air flow To ensure that the mounting is secure use two to four M6 mounting screws for each side of the shelf A shelf should be mounted at the bottom of the rack if it is the only unit in the rack Note Procedure Step 1 Verify that the proper fuse and alarm pan...

Page 67: ...river install one mounting screw in each side of the assembly When the shelf is secured to the rack install the remaining mounting screws Step 7 When the shelf is secured to the rack install the remaining mounting screws Use at least one set of the horizontal screw slots on the shelf to prevent slippage Note Step 8 Using the hex tool remove the temporary set screws Step 9 Return to your originatin...

Page 68: ...f to allow air flow to the fan intake If a second ONS 15454 is installed underneath a shelf the air ramp on top of the bottom shelf provides the desired space However if the ONS 15454 is installed above third party equipment you must provide a minimum spacing of one inch 25 4 mm between the third party shelf and the bottom of the ONS 15454 The third party equipment must not vent heat upward into t...

Page 69: ... ETSI only Two M6 x 20 socket set screws per shelf Eight M6 x 20 pan head Phillips mounting screws per shelf ANSI only Two 12 24 x 3 4 set screws 48 1003 XX per shelf Eight 12 24 x 3 4 pan head Phillips mounting screws 48 1004 XX 48 1007 XX per shelf Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required...

Page 70: ...installed above third party equipment you must provide a minimum spacing of one inch 25 4 mm between the third party shelf and the bottom of the ONS 15454 The third party equipment must not vent heat upward into the ONS 15454 Note Procedure Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space If a fuse and alarm panel is not present you must install one a...

Page 71: ...mp is needed if you install more than one ONS 15454 ETSI shelf in a rack To ensure that the air ramp is secure use one or two M6 mounting screws for each side of the shelf The following figure shows how to mount an air ramp in the rack Cisco ONS 15454 Hardware Installation Guide 41 Installing the ONS 15454 M12 ANSI and ETSI Shelf DLP G680 Mount Multiple ONS 15454 Shelf Assemblies in a Rack ...

Page 72: ...NS 15454 Purpose 2 Phillips Dynamometric screwdriver Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level To install the air filter inside the air ramp unit 15454E AIR RAMP or 15454 AIR RAMP use the ETSI version of the air filter 15454 FTF2 or 15454E FTF4 Note Cisco ONS 15454 Hardware Installation Guide 42 Installing the ONS 15454 M12 A...

Page 73: ...verse the Mounting Bracket to Fit a 19 inch 482 6 mm Rack ANSI Only on page 33 as required Step 4 Align the chassis with the rack mounting screw holes insert and tighten the four screws In an ETSI configuration the air ramp comes with pre installed brackets as illustrated in the following figure Figure 17 Air Ramp with Brackets in an ETSI Configuration Step 5 To install the 19 inch and 23 inch bra...

Page 74: ...ts in an ONS 15454 ANSI deep door remove the screws that attach the mounting bracket to the side of the shelf Step 9 Align the mounting bracket screw holes against the shelf screw holes according to the following figure Step 10 The bracket mounting holes will align with the forward most mounting holes on the air ramp When aligned properly the mounting flange will be 80 mm from the front edge of th...

Page 75: ...l major or minor alarm is present anywhere on the ONS 15454 shelf These LEDs must be visible so that technicians can quickly determine if any alarms are present on the ONS 15454 shelf or the network You can use the LCD to further isolate alarms The front door as shown in the following figure provides access to the shelf fiber storage tray fan tray assembly and LCD screen Cisco ONS 15454 Hardware I...

Page 76: ...o accommodate a deep door and extended fiber clips 15454 DOOR KIT to provide additional room for cabling as shown in the following figure The ONS 15454 ETSI does not support the deep door Cisco ONS 15454 Hardware Installation Guide 46 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 77: ...nrestricted access to the front of the shelf To mount the air ramp on an ONS 15454 ANSI with a deep door mounting brackets Cisco P N 700 25319 01 for 19 deep door and 700 25287 01 for 23 deep door are provided Note Before you remove the ONS 15454 front door you must remove the ground strap of the front door Cisco ONS 15454 Hardware Installation Guide 47 Installing the ONS 15454 M12 ANSI and ETSI S...

Page 78: ...S 15454 ANSI Front Door Ground Strap The following figure shows how to remove the ONS 15454 ANSI front door Cisco ONS 15454 Hardware Installation Guide 48 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 79: ...moving the ONS 15454 ANSI Front Door The following figure shows how to remove the ONS 15454 ETSI front door Cisco ONS 15454 Hardware Installation Guide 49 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 80: ... You can use the label to record slot assignments port assignments card types node ID rack ID and serial number for the ONS 15454 The following figure shows the erasable label on the ONS 15454 ANSI shelf Cisco ONS 15454 Hardware Installation Guide 50 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 81: ...5454 ANSI Front Door Erasable Label The following figure shows the erasable label on the ONS 15454 ETSI shelf Cisco ONS 15454 Hardware Installation Guide 51 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 82: ...s 1M laser warning The following figure shows the ONS 15454 ANSI laser warning Figure 27 Laser Warning on the ONS 15454 ANSI Front Door Label The following figure shows the ONS 15454 ETSI laser warning Cisco ONS 15454 Hardware Installation Guide 52 Installing the ONS 15454 M12 ANSI and ETSI Shelf Front Door ...

Page 83: ...terface assembly EIA panel installed it should have two sheet metal backplane covers one on each side of the backplane See the following figure Each cover is held in place with nine 6 32 x 3 8 inch Phillips screws Cisco ONS 15454 Hardware Installation Guide 53 Installing the ONS 15454 M12 ANSI and ETSI Shelf ONS 15454 ANSI Backplane Covers ...

Page 84: ...ve the lower backplane cover to access the alarm interface panel AIP alarm pin fields frame ground and power terminals Figure 30 Removing the Lower Backplane Cover Rear Cover The ONS 15454 ANSI has an optional clear plastic rear cover This clear plastic cover provides additional protection for the cables and connectors on the backplane Cisco ONS 15454 Hardware Installation Guide 54 Installing the ...

Page 85: ...tional spacers if more space is needed between the cables and rear cover as shown in the following figure Figure 32 Installing the Plastic Rear Cover with Spacers Cisco ONS 15454 Hardware Installation Guide 55 Installing the ONS 15454 M12 ANSI and ETSI Shelf Rear Cover ...

Page 86: ...u must contact the Cisco Technical Assistance Center Cisco TAC For contact information see the Obtaining Documentation Obtaining Support and Security Guidelines on page xxix You can replace the AIP on an in service system without affecting traffic except Ethernet traffic on nodes running a release earlier than Software Release 4 0 The circuit repair feature allows you to repair circuits affected b...

Page 87: ... Compartment Door This task opens the front door Purpose Pinned hex Allen key Tools Equipment NTP G306 Install the ONS 15454 Shelf on page 31 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level The ONS 15454 shelf has an ESD plug input and is shipped with an ESD wrist strap The ESD plug input is located on the outside of the shelf on the right side It is la...

Page 88: ... Step 2 Press the door button to release the latch A button on the right side of the shelf releases the door Step 3 Swing the door open Step 4 Return to your originating procedure NTP DLP G10 Remove the Front Door This task removes the front cabinet compartment door Purpose Open end wrench Tools Equipment DLP G9 Open the Front Cabinet Compartment Door on page 57 Prerequisite Procedures Cisco ONS 1...

Page 89: ...es as shown in the following figure Figure 34 Removing the ONS 15454 ETSI Front Door Step 2 For ONS 15454 ANSI shelves a To remove the door ground strap perform the following To detach the ground strap from the front door loosen the 6 Kepnut 49 0600 01 using the open end wrench Detach the end of the ground strap terminal lug 72 3622 01 from the male stud on the inside of the door Cisco ONS 15454 H...

Page 90: ...edure NTP NTP G4 Open and Remove the FMEC Cover ETSI Only This procedure opens and removes the FMEC cover on the ONS 15454 ETSI The ONS 15454 ETSI has a screw in panel over the EFCA The FMEC cover protects the FMEC cards Purpose Medium slot head screwdriver Tools Equipment NTP G306 Install the ONS 15454 Shelf on page 31 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None ...

Page 91: ...ver This task opens the FMEC cover The FMEC cover must be opened to install the MIC A P and the MIC C T P Purpose Medium slot head screwdriver Tools Equipment DLP G9 Open the Front Cabinet Compartment Door on page 57 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Unscrew the screws on the FMEC cover Cisco ONS 15454 Hardware Installatio...

Page 92: ...ium slot head screwdriver Tools Equipment DLP G11 Open the FMEC Cover on page 61 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Unscrew the nut holding the ground wire to the shelf Remove the nut and washer Step 2 Remove the ground wire from the left side of the shelf Cisco ONS 15454 Hardware Installation Guide 62 Installing the ONS 1...

Page 93: ...I backplane by removing the covers The backplane has two sheet metal covers one on either side and a lower backplane cover at the bottom Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G306 Install the ONS 15454 Shelf on page 31 NTP G3 Open and Remove the Front Door on page 56 Prerequisite Procedures Required Required As Need...

Page 94: ... the lower backplane cover of the ONS 15454 ANSI shelf Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Unscrew the five retaining screws that hold the cover in place as shown in the following figure Figure 38 Lower B...

Page 95: ... Store the panel for later use Attach the backplane cover s whenever electrical interface assemblies EIAs are not installed Step 5 Return to your originating procedure NTP ONS 15454 ETSI Front Mount Electrical Connection The ONS 15454 ETSI positive and negative power terminals are located on FMEC cards in the Electrical Facility Connection Assembly EFCA The ground connection is the grounding recep...

Page 96: ... wristband when working with a powered ONS 15454 ETSI For detailed instructions on how to wear the ESD wristband refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution The ONS 15454 ETSI EFCA has 12 FMEC slots numbered sequentially from left to right beginning with Slot 18 Slots 18 to 22 and 25 to 29 provide electrical connections for the correspondi...

Page 97: ...tened The following figure shows FMEC installation Figure 39 Installing FMECs on the ONS 15454 ETSI Step 5 Tighten the screws Step 6 Continue with the NTP G7 Install the Power and Ground on page 68 Stop You have completed this procedure Power and Ground Description Ground the equipment according to Telcordia standards or local practices The following sections describe power and ground for the ONS ...

Page 98: ...to MIC A P and to MIC C T P shipped with the ONS 15454 ETSI Two hole grounding lug shipped with the ONS 15454 ETSI Tools Equipment NTP G4 Open and Remove the FMEC Cover ETSI Only on page 60 NTP G6 Install the MIC A P and MIC T C P FMECs ETSI Only on page 66 NTP G5 Remove the Backplane Covers ANSI Only on page 63 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security...

Page 99: ...s on how to wear the ESD wristband refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution Procedure Step 1 Verify that the correct fuse and alarm panel is installed in the top mounting space ETSI only Verify that the fuse rating does not exceed 30A The fuse rating for ANSI chassis must not exceed 30A Step 2 Depending on your type of shelf connect the...

Page 100: ... to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level When installing or replacing the unit the ground connection must always be made first and disconnected last Statement 1046 Warning Do n...

Page 101: ...installed in Slot 23 and the MIC C T P FMEC is installed in Slot 24 of the EFCA Step 2 Attach the connector on the end of the power cable to the power FMEC Step 3 Tighten the screws of the connector on the power cable Step 4 Connect the power cable to the fuse panel or power source Use the pin connections in the following table If the green yellow cable is included in the power cable it must be co...

Page 102: ...ORE Issue 4 and 5 Note If the system loses power or both TCC2 TCC2P TCC3 cards are reset and the system is not provisioned to get the time from a Network Time Protocol Simple Network Time Protocol NTP SNTP server you must reset the ONS 15454 clock After powering down the date defaults to January 1 1970 00 04 15 To reset the clock see the Turn Up a Node chapter in the Cisco ONS 15454 DWDM Configura...

Page 103: ... connection surfaces but always keep them clean and free of contaminants Caution When terminating power return and frame ground do not use soldering lug screwless push in connectors quick connect or other friction fit connectors Caution Step 5 Strip 1 2 inch 12 7 mm of insulation from all power cables that you will use Step 6 Crimp the lugs onto the ends of all power leads When terminating battery...

Page 104: ...ating procedure NTP DLP G19 Turn On and Verify Office Power This task measures the power to verify correct power and returns for the ONS 15454 shelf Purpose Voltmeter Tools Equipment ETSI Connect the office ground to chassis For detailed instructions on grounding refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms DLP G17 Connect Office Power to the ONS 1...

Page 105: ...B side of the shelf place the black test lead of the voltmeter to the frame ground Place the red test lead to the BAT2 B side battery connection red cable Verify that it reads between 40 5 VDC and 57 VDC Then place the red test lead of the voltmeter to the RET2 B side return ground black cable and verify that no voltage is present Step 5 Return to your originating procedure NTP Shelf Voltage and T...

Page 106: ...ature Temperature of the shelf in degrees Celsius Step 3 Click the Reset button to refresh the voltage and temperature values Stop You have completed this procedure Fan Tray Assembly The fan tray assembly is located at the bottom of the ONS 15454 shelf The fan tray is a removable drawer that holds fans and fan control circuitry for the ONS 15454 The front door can be left in place or removed befor...

Page 107: ...n ADM 10G GE_XP 10GE_XP GE_XPE 10GE_XPE ML MR 10 and CE MR 10 Caution The 15454 FTA3 T fan tray assembly can only be installed in ONS 15454 Release 3 1 and later shelf assemblies 15454 SA ANSI P N 800 19857 15454 SA HD P N 800 24848 The fan tray assembly includes a pin that prevents it from being installed in ONS 15454 shelf assemblies released before ONS 15454 Release 3 1 15454 SA NEBS3E 15454 SA...

Page 108: ...an tray Units for ONS 15454 Cards 15454E CC FTA ETSI shelf 15454 CC FTA ANSI shelf 15454E FTA 48V ETSI shelf 15454 FTA3 T ANSI shelf ONS 15454 Cards Yes Yes TCC2 TCC2P Yes Yes AIC I Yes Yes MS ISC 100T Yes Yes AEP Yes Yes MIC A P Yes Yes MIC C T P Yes Yes TCC3 Cisco ONS 15454 Hardware Installation Guide 78 Installing the ONS 15454 M12 ANSI and ETSI Shelf Fan tray Units for ONS 15454 Cards ...

Page 109: ...C Yes Yes OPT AMP C Yes Yes OPT RAMP C Yes Yes OPT RAMP CE Yes Yes 32MUX O Yes Yes 32DMX O Yes Yes 4MD xx x Yes Yes TDC CC Yes Yes TDC FC Yes Yes PSM Yes Yes AD 1C xx x Yes Yes AD 2C xx x Yes Yes AD 4C xx x Yes Yes AD 1B xx x Yes Yes AD 4B xx x Yes Yes 32 WSS Yes Yes 32 DMX Yes Yes 32 WSS L Yes Yes 32 DMX L Yes Yes MMU Cisco ONS 15454 Hardware Installation Guide 79 Installing the ONS 15454 M12 ANS...

Page 110: ... TXP_MR_2 5G Yes Yes TXPP_MR_2 5G Yes Yes MXP_2 5G_10G Yes Yes TXP_MR_10E Yes Yes MXP_2 5G_10E Yes Yes MXP_MR_2 5G Yes Yes MXPP_MR_2 5G Yes Yes TXP_MR_10E_C Yes Yes TXP_MR_10E_L Yes Yes MXP_2 5G_10E_C Yes Yes MXP_2 5G_10E_L Yes Yes MXP_MR_10DME_C Yes Yes MXP_MR_10DME_L Yes No GE_XP 10GE_XP Yes No ADM 10G Yes No GE_XPE 10GE_XPE Yes No OTU2_XP Yes No 40G MXP C Cisco ONS 15454 Hardware Installation G...

Page 111: ...ns are low medium and high If the TCC2 TCC2P TCC3 card fails the fans automatically shift to high speed The temperature measured by the TCC2 TCC2P TCC3 sensors appears on the LCD screen Fan Failure If one or more fans fail on the fan tray assembly replace the entire assembly You cannot replace individual fans The red Fan Fail LED on the front of the fan tray illuminates when one or more fans fail ...

Page 112: ...all the Fan Tray Assembly This procedure installs the fan tray assembly Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G3 Open and Remove the Front Door on page 56 NTP G7 Install the Power and Ground on page 68 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Do not operate an ONS ...

Page 113: ... appears blank remove the unit from the shelf wait for at least 5 seconds and reinsert the unit into the shelf Note Procedure Step 1 Install the air filter The air filter can be installed internally between the fan tray and shelf or externally by mounting the air filter bracket on the bottom of the shelf Slide the air filter into the bracket Although the air filter can work with older fan trays if...

Page 114: ...esponding receptacle on the assembly Do not force a fan tray assembly into place This can damage the connectors on the fan tray assembly and or the connectors on the back panel of the shelf Caution Figure 42 Installing the Fan Tray Assembly on the ONS 15454 ETSI Cisco ONS 15454 Hardware Installation Guide 84 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G8 Install the Fan Tray Assembly ...

Page 115: ...rovide an additional 48 dry alarm contacts for the ONS 15454 ANSI 32 inputs and 16 outputs The AEP is a printed circuit board assembly that is installed on the backplane The following figure shows the AEP board the left connector is the input connector and the right connector is the output connector The AIC I without an AEP already contains direct alarm contacts These direct AIC I alarm contacts a...

Page 116: ...tor MOS alarm output can operate by definable alarm condition a maximum open circuit voltage of 60 VDC and a maximum current of 100 mA See the External Alarms and Controls section of the Install the Control Cards chapter in the Cisco ONS 15454 DWDM Configuration Guide for further information The following figure shows the wire wrapping connections on the shelf backplane used to connect to the AEP ...

Page 117: ...ack AEP_ 5 AE_ 5 A2 White VBAT VBAT A3 Slate VB VB A4 Violet AE_CLK_P AE_CLK_P A5 Blue AE_CLK_N AE_CLK_N A6 Green AE_DOUT_P AE_DIN_P A7 Yellow AE_DOUT_N AE_DIN_N A8 Orange AE_DIN_P AE_DOUT_P A9 Red AE_DIN_N AE_DOUT_N A10 Brown The following figure is a circuit diagram of the alarm inputs Inputs 1 and 48 are shown in the example Cisco ONS 15454 Hardware Installation Guide 87 Installing the ONS 1545...

Page 118: ...ND 2 ALARM_IN_4 29 ALARM_IN_3 3 GND 30 ALARM_IN_5 4 ALARM_IN_6 31 GND 5 ALARM_IN_8 32 ALARM_IN_7 6 GND 33 ALARM_IN_9 7 ALARM_IN_10 34 GND 8 ALARM_IN_12 35 ALARM_IN_11 9 GND 36 ALARM_IN_13 10 ALARM_IN_14 37 GND 11 ALARM_IN_16 38 ALARM_IN_15 12 GND 39 ALARM_IN_17 13 ALARM_IN_18 40 GND 14 ALARM_IN_20 41 ALARM_IN_19 15 Cisco ONS 15454 Hardware Installation Guide 88 Installing the ONS 15454 M12 ANSI an...

Page 119: ... 26 The following figure is a circuit diagram of the alarm outputs Outputs 1 and 16 are shown in the example Figure 48 Alarm Output Circuit Diagram Use the pin numbers in the following table to connect to the external elements being switched by external controls Table 10 Pin Association for Alarm Output Pins SignalName AMP Champ Pin Number SignalName AMP Champ Pin Number COM_0 27 1 Cisco ONS 15454...

Page 120: ...COM_6 36 10 37 COM_7 11 NO_8 38 NO_7 12 COM_8 39 13 40 COM_9 14 NO_10 41 NO_9 15 COM_10 42 16 43 COM_11 17 NO_12 44 NO_11 18 COM_12 45 19 46 COM_13 20 NO_14 47 NO_13 21 COM_14 48 22 49 COM_15 23 50 NO_15 24 GND1 51 25 GND2 52 NO_0 26 Cisco ONS 15454 Hardware Installation Guide 90 Installing the ONS 15454 M12 ANSI and ETSI Shelf ONS 15454 ANSI Alarm Expansion Panel ...

Page 121: ...13 Remove the Lower Backplane Cover on page 64 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level The AIC I card provides direct alarm contacts external alarm inputs and external control outputs In the ANSI shelf these AIC I alarm contacts are routed through the backplane to wire wrap pins accessible from the back of the shelf When you install an AEP the ...

Page 122: ...ng two standoffs on either side of the backplane as shown in the following figure Step 3 Position the AEP board over the standoffs Cisco ONS 15454 Hardware Installation Guide 92 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G9 Install the Alarm Expansion Panel ANSI Only ...

Page 123: ...the wire wrap pins on the backplane The following figure shows where the cable wires are connected Table 11 Pin Assignments for the AEP on page 94 shows AEP and AIC I signals that each wire carries b Plug the other end of the AEP cable into AEP connector port Cisco ONS 15454 Hardware Installation Guide 93 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G9 Install the Alarm Expansion Panel ANS...

Page 124: ...ed AE_DIN_N AE_DOUT_N A10 Brown Step 6 Continue with the ONS 15454 ANSI Alarm Timing LAN and Craft Pin Connections on page 94 Stop You have completed this procedure ONS 15454 ANSI Alarm Timing LAN and Craft Pin Connections Pin connections are provided on the ONS 15454 ANSI backplane For information about ONS 15454 ETSI connections see the ONS 15454 ETSI Front Mount Electrical Connection on page 65...

Page 125: ...d pin that corresponds to the pin field used The AIC I requires a shelf running Software R3 4 0 or later The backplane of the ANSI shelf contains a wire wrap field with pin assignment according to the layout in Figure 52 Cisco ONS 15454 Backplane Pinouts Release 3 4 or Later on page 96 The shelf might be an existing shelf that has been upgraded to Software R3 4 or later In this case the backplane ...

Page 126: ...2 Cisco ONS 15454 Backplane Pinouts Release 3 4 or Later Cisco ONS 15454 Hardware Installation Guide 96 Installing the ONS 15454 M12 ANSI and ETSI Shelf ONS 15454 ANSI Alarm Timing LAN and Craft Pin Connections ...

Page 127: ...e contacts are in the ENVIR ALARM IN external alarm and ENVIR ALARM OUT external control pin fields These alarms are in the ENVIR ALARMS category you must have the AIC I card installed to use the ENVIR ALARMS Alarm contacts are Normally Open N O meaning that the system closes the alarm contacts when the corresponding alarm conditions are present Each alarm contact consists of two wire wrap pins on...

Page 128: ... connection use 100 ohm shielded BITS clock cable pair 22 or 24 AWG 0 51 mm 0 020 inch or 0 64 mm 0 0252 inch twisted pair T1 type Note Table 12 BITS External Timing Pin Assignments Function Tip and Ring Contact External Device Output to external device Primary ring A3 BITS 1 Out First external device Output to external device Primary tip B3 BITS 1 Out Input from external device Secondary ring A4 ...

Page 129: ...rt on the TCC2 TCC2P TCC3 faceplate to create a VT100 emulation window to serve as a TL1 craft interface to the ONS 15454 ANSI Use a straight through cable to connect to the EIA TIA 232 port The following table shows the pin assignments for the CRAFT pin field You cannot use the craft backplane pins and the EIA TIA 232 port on the TCC2 TCC2P TCC3 card simultaneously Note To use the serial port cra...

Page 130: ...tic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution Procedure Step 1 For an ONS 15454 ETSI shelf complete the following tasks as necessary Complete the DLP G20 Install Alarm Wires on the MIC A P ETSI Only on page 101if you want to provision external alarms and or controls with the AIC I card Complete the DLP G21 Install Timing Wires on the MIC C T P ETSI Only on page 10...

Page 131: ... on the ONS 15454 ETSI so that you can provision external environmental alarms and controls with the AIC I card Purpose DB 62 connector 0 51 mm or 0 64 mm 22 or 24 AWG wires Tools Equipment NTP G6 Install the MIC A P and MIC T C P FMECs ETSI Only on page 66 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Using 0 51 mm or 0 64 mm 22 or ...

Page 132: ... 16 Extra alarm 2 EXALM2 17 Extra alarm 3 EXALM3 18 Extra alarm 3 EXALM3 19 Extra alarm 4 EXALM4 20 Extra alarm 4 EXALM4 21 Extra alarm 5 EXALM5 22 Extra alarm 5 EXALM5 23 Extra alarm 6 EXALM6 24 Extra alarm 6 EXALM6 25 Ground FGND 26 Extra alarm 7 EXALM7 27 Extra alarm 7 EXALM7 28 Extra alarm 8 EXALM8 29 Extra alarm 8 EXALM8 30 Extra alarm 9 EXALM9 31 Extra alarm 9 EXALM9 32 Extra alarm 10 EXALM1...

Page 133: ... alarm AUDALM0 47 Normally open major audible alarm AUDALM1 48 Normally open major audible alarm AUDALM1 49 Normally open critical audible alarm AUDALM2 50 Normally open critical audible alarm AUDALM2 51 Ground FGND 52 Normally open remote audible alarm AUDALM3 53 Normally open remote audible alarm AUDALM3 54 Normally open minor visible alarm VISALM0 55 Normally open minor visible alarm VISALM0 56...

Page 134: ...e to the appropriate connector on the faceplate of the MIC C T P Step 2 Gently push the cable with the 1 0 2 3 miniature coax connector down until the cable connector slides into the 1 0 2 3 miniature coax connector on the faceplate with a click The MIC C T P provides 1 0 2 3 miniature coax connectors that are used for timing input and output The top connectors are for A BITS 1 timing and the bott...

Page 135: ... mm or 0 64 mm 22 or 24 AWG wire preferably CAT 5 Tools Equipment NTP G6 Install the MIC A P and MIC T C P FMECs ETSI Only on page 66 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Rather than using the LAN connection port on the MIC C T P you can use the LAN connection port on the TCC2 TCC2P TCC3 card if preferred Use either the MIC C T P connection ...

Page 136: ...iginating procedure NTP DLP G23 Install Alarm Wires on the Backplane ANSI Only This task installs alarm wires on the backplane so that you can provision external environmental alarms and controls with the AIC I card If you are using the AEP do not perform this task Purpose Wire wrapper 22 or 24 AWG 0 51 mm or 0 64 mm wires 100 ohm shielded BITS clock cable pair 22 or 24 AWG 0 51 mm or 0 64 mm twis...

Page 137: ... wires on the appropriate wire wrap pins according to local site practice Ground the shield of the BITS Input cable at the BITS end For BITS Output wrap the ground shield of the BITS cable to the frame ground pin FG1 located below the column of BITS pins Cisco ONS 15454 Hardware Installation Guide 107 Installing the ONS 15454 M12 ANSI and ETSI Shelf DLP G23 Install Alarm Wires on the Backplane ANS...

Page 138: ...54 Cisco ONS 15454 Backplane Pinouts Release 3 4 or Later Cisco ONS 15454 Hardware Installation Guide 108 Installing the ONS 15454 M12 ANSI and ETSI Shelf DLP G23 Install Alarm Wires on the Backplane ANSI Only ...

Page 139: ...ir T1 type wrap the clock wires on the appropriate wire wrap pins according to local site practice Ground the shield of the BITS input cable at the BITS end For BITS output wrap the ground shield of the BITS cable to the frame ground pin FG1 located beneath the column of BITS pins Table 12 BITS External Timing Pin Assignments on page 98 lists the pin assignments for the BITS timing pin fields Tabl...

Page 140: ...2 TCC2P TCC3 if preferred Use either the backplane connection or the TCC2 TCC2P TCC3 front connection You cannot use the LAN backplane pins and the LAN connection port on the TCC2 TCC2P TCC3 simultaneously however it is possible for you to make a direct connection from a computer to the LAN connection port on the TCC2 TCC2P TCC3 while the LAN backplane pins are in use as long as the computer that ...

Page 141: ...e pairs flipped a LAN Connection Polarity Reversed LAN POL REV condition is raised This condition usually occurs during an upgrade or initial node deployment To correct the situation ensure that your Ethernet cable has the correct mapping of the wire wrap pins Note Step 2 Return to your originating procedure NTP DLP G26 Install the TL1 Craft Interface Wires ANSI Only This task installs the TL1 cra...

Page 142: ...ation prevents access to the node or causes a loss in connectivity Note Table 20 Craft Interface Pin Assignments Function Contact PinField Receive A1 Craft Transmit A2 Ground A3 DTR A4 Step 3 Return to your originating procedure NTP NTP G11InstallanExternalWire WrapPanelontheAEP ANSI Only This procedure connects an external wire wrap panel to the ONS 15454 ANSI AEP to provide the physical alarm co...

Page 143: ...AEP Cover Step 2 Insert and tighten the eight screws to secure the AEP cover to the AEP Step 3 Connect the cables from the external wire wrap panel to the AMP Champ connectors on the AEP The following table lists the alarm input pin assignments Cisco ONS 15454 Hardware Installation Guide 113 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G11 Install an External Wire Wrap Panel on the AEP ANS...

Page 144: ...GND 39 ALARM_IN_17 13 ALARM_IN_18 40 GND 14 ALARM_IN_20 41 ALARM_IN_19 15 GND 42 ALARM_IN_21 16 ALARM_IN_22 43 GND 17 ALARM_IN_24 44 ALARM_IN_23 18 GND 45 ALARM_IN_25 19 ALARM_IN_26 46 GND 20 ALARM_IN_28 47 ALARM_IN_27 21 GND 48 ALARM_IN_29 22 ALARM_IN_30 49 GND 23 50 ALARM_IN_31 24 GND1 51 ALARM_IN_ 25 GND2 52 ALARM_IN_0 26 The following table lists the alarm output external control pin assignmen...

Page 145: ...38 NO_7 12 COM_8 39 13 40 COM_9 14 NO_10 41 NO_9 15 COM_10 42 16 43 COM_11 17 NO_12 44 NO_11 18 COM_12 45 19 46 COM_13 20 NO_14 47 NO_13 21 COM_14 48 22 49 COM_15 23 50 NO_15 24 GND1 51 25 GND2 52 NO_0 26 The following figure illustrates the alarm input connectors Cisco ONS 15454 Hardware Installation Guide 115 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G11 Install an External Wire Wrap ...

Page 146: ...ector The following figure illustrates the alarm output connectors Cisco ONS 15454 Hardware Installation Guide 116 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP G11 Install an External Wire Wrap Panel on the AEP ANSI Only ...

Page 147: ... the ONS 15454 ETSI FMEC cover Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G4 Open and Remove the FMEC Cover ETSI Only on page 60 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Cisco ONS 15454 Hardware Installation Guide 117 Installing the ONS 15454 M12 ANSI and ETSI Shelf NTP...

Page 148: ...er Step 4 Attach the ground wire to the shelf Step 5 Attach the washer and nut Step 6 Attach the cover to the shelf using the screws on the top of the cover Step 7 Continue with the NTP G14 Install DWDM Equipment on page 123 Stop You have completed this procedure NTP G13 Install the Rear Cover ANSI Only The following procedure explains how to install the rear cover on an ONS 15454 ANSI shelf Purpo...

Page 149: ...ith the screw slots on the mounting brackets making the screws easy to locate Tip Step 2 Loosen the top and bottom screws on one edge of the backplane to provide room to slide the mounting brackets into place using the U shaped screw slots on each end Step 3 Slide one of the mounting brackets into place and tighten the screws Step 4 Repeat Steps 2 and 3 for the second mounting bracket Step 5 Attac...

Page 150: ... patch panels or fiber storage trays in either 1rack unit RU or 2 RU sizes 1RU Fiber storage tray and 64 channel patch panel 2 RU Y cable patch panel 64 channel patch panel 80 channel patch panel and mesh patch panel 4 or 8 degree Or alternatively 3 ONS 15454 shelves 2 DCUs 6 standard patch panel trays or fiber storage trays or 3 deep patch panel trays in either 1 RU or 2 RU sizes 1RU Fiber storag...

Page 151: ...anel 4 or 8 degree See the following figure for a typical rack layout Use the rack layout generated by Cisco TransportPlanner to determine your exact shelf layout Note Cisco ONS 15454 Hardware Installation Guide 121 Installing the ONS 15454 M12 ANSI and ETSI Shelf Typical DWDM Rack Layouts ...

Page 152: ...el or fiber storage tray below the ONS 15454 shelf you must install the air ramp between the shelf and patch panel tray fiber management tray or leave one rack unit RU space open Cisco ONS 15454 Hardware Installation Guide 122 Installing the ONS 15454 M12 ANSI and ETSI Shelf Typical DWDM Rack Layouts ...

Page 153: ...in this chapter require that you have a network plan calculated for your DWDM network with Cisco Transport Planner Release 9 2 Cisco TransportPlanner is a DWDM planning tool that is available from your Cisco account representative Cisco TransportPlanner prepares a shelf plan for each network node and calculates the power and attenuation levels for the DWDM cards installed in the node For informati...

Page 154: ...ith the rack mounting screw holes one at a time insert and tighten the four screws Step 4 Connect a frame ground to the ground terminal provided on either side of the chassis Use minimum 14 AWG wire Step 5 Return to your originating procedure NTP DLP G28 Install the Fiber Patch Panel Tray This task installs the fiber patch panel tray Install the appropriate L band or C band patch panel tray as nec...

Page 155: ...each patch panel tray you want to install Step 6 Return to your originating procedure NTP DLP G29 Install the Fiber Storage Tray This task installs the fiber storage tray The fiber storage tray stores slack fiber optic cable Purpose 2 Phillips Dynamometric screwdriver Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1...

Page 156: ...the DLP G3 Reverse the Mounting Bracket to Fit a 19 inch 482 6 mm Rack ANSI Only on page 33 as required Step 3 Align the chassis with the rack mounting screw holes insert the four screws and tighten Any paint between the EAP mounting ears and the frame of the metal rack must be removed The area must then be cleaned and coated with an antioxidant Caution Step 4 Repeat Steps 1 to 3 for the second EA...

Page 157: ... minimum for frame grounding Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 The FlexLayer shelf requires 1 RU in a standard 19 inch 482 6 mm or 23 inch 584 2 mm rack Locate the RMU space specified in your site plan Step 2 A set of mounting brackets are included with the FlexLayer mounting kit one set each for 19 i...

Page 158: ...5216 FLB 2 31 1 ITU 100 GHz 2 Ch FlexMod 1531 90 and 1532 68 15216 FLB 2 32 6 ITU 100 GHz 2 Ch FlexMod 1534 25 and 1535 04 15216 FLB 2 35 0 ITU 100 GHz 2 Ch FlexMod 1535 82 and 1536 61 15216 FLB 2 36 6 ITU 100 GHz 2 Ch FlexMod 1538 19 and 1538 98 15216 FLB 2 38 9 ITU 100 GHz 2 Ch FlexMod 1539 77 and 1540 56 15216 FLB 2 40 5 ITU 100 GHz 2 Ch FlexMod 1542 14 and 1542 94 15216 FLB 2 42 9 ITU 100 GHz ...

Page 159: ...e you want to install Step 5 Return to your originating procedure NTP DLP G32 Install the Y Cable Protection Modules in the FlexLayer Shelf This task installs the Y cable protection modules in the FlexLayer shelf Purpose 2 Phillips Dynamometric screwdriver Y cable module s Multi Mode Y Cable Protection FlexModule s 15216 CS MM Y or Single Mode Y Cable Protection FlexModule s 15216 CS SM Y as appro...

Page 160: ...odule s 15454 YCM SM LC as appropriate Cisco TransportPlanner Internal Connections Report Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 According to the Cisco TransportPlanner Internal Connections Report determine which slots you will use to install the Y cable modules Step 2 Open the drawer of the tray by pushin...

Page 161: ...equired Required As Needed Onsite Onsite Remote Provisioning or higher Security Level During this procedure wear grounding wrist straps to avoid ESD damage to the card Do not directly touch the backplane with your hand or any metal tool or you could shock yourself Statement 94 Warning Always use the supplied ESD wristband when working with a powered ONS 15454 For detailed instructions on how to we...

Page 162: ...the TCC2 TCC2P or TCC3 Card This task installs redundant TCC2 TCC2P TCC3 cards The first card you install in the ONS 15454 must be a TCC2 TCC2P TCC3 card and it must initialize before you install any cross connect or traffic cards Cross connect cards are only required in hybrid nodes Purpose Two TCC2 TCC2P TCC3 cards Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite O...

Page 163: ...een PWR LEDs turn on for 10 seconds The PWR LEDs then turn red for 2 to 3 minutes before going to steady green While the PWR LEDs are red for two to three minutes the ACT STBY turn on The boot up process is complete when the PWR LEDs turn green and the ACT STBY remains on The ACT STBY LED will be green if this is the first TCC2 card installed and amber if this is the second TCC2 card installed It ...

Page 164: ...LEDs then turn red for 2 to 3 minutes before going to steady green During this time the ACT STBY MJ and MN LEDs might turn on followed by the SNYC LED briefly The boot up process is complete when the PWR LEDs turn green and the yellow ACT STBY remains on The ACT STBY LED will be green if this is the first TCC3 card installed and yellow if this is the second TCC3 card installed It might take up to ...

Page 165: ... up sequence However after the red FAIL LED turns on for about 5 seconds the FAIL LED and the ACT STBY LED begin to flash alternately for up to 30 minutes while the new software loads onto the active TCC2 TCC2P TCC3 card After loading the new software the upgraded TCC2 TCC2P TCC3 card s LEDs repeat the appropriate bootup sequence and the amber ACT STBY LED turns on Tip If you insert a card into a ...

Page 166: ...r a different card no LEDs turn on Note If the red FAIL LED is on continuously or the LEDs act erratically the card is not installed properly Remove the card and repeat all the steps Note Step 5 Return to your originating procedure NTP DLP G309 Install the MS ISC 100T Card This task installs redundant MS ISC 100T cards The MS ISC 100T card is required for a multishelf node configuration It provide...

Page 167: ...D turns on for 15 to 20 seconds The red FAIL LED blinks for approximately 3 minutes The red FAIL LED turns on for approximately 6 minutes The green ACT or ACT STBY LED turns on The SF LED can persist until all card ports connect to their far end counterparts and a signal is present If the red FAIL LED does not turn on check the power Note If you insert a card into a slot provisioned for a differen...

Page 168: ... to upgrade the number of shelves Assign VLAN ID as VLANint to Port 21 of the Cisco Catalyst 2950 switch and connect to Port 1 of the Cisco Catalyst 3560 switch This topology supports both the non secure and secure mode configuration ONS 15454 Multishelf Node Controller ONS 15454 M6 and ONS 15454 Subtending Shelves When an ONS 15454 is used as the node controller a mix of ONS 15454 and ONS 15454 M...

Page 169: ...ort of the MS ISC 100T card located on the right side of the node controller shelf Slots 12 to 17 and the other end into the front panel RJ 45 connector of the TCC2 TCC2P TCC3 card in Slot 11 c Using the 19 69 in 0 5 m CAT 5 LAN cable plug one connector into the PRT port of the MS ISC 100T card located on the left side of the node controller shelf Slots 1 to 6 and plug the other connector into the...

Page 170: ...into the SSC1 port on the left EAP b Using a cross over CAT 5 LAN cable plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 and plug the other end into the SSC1 port on the right EAP c Repeat Steps a and b for each subtending shelf in the multishelf configuration Use the same SSC port number 2 through 8 on the left and right EAP for each subtending shelf...

Page 171: ...ID protocol rstp Router config bridge public VLAN ID forward time 5 Router config bridge public VLAN ID max age 10 Router config bridge private VLAN ID protocol rstp Router config bridge private VLAN ID forward time 5 Router config bridge private VLAN ID max age 10 Step 2 Enter the following commands to configure the ports DCN 1 and DCN 2 Example Router config interface FastEthernet0 Router config...

Page 172: ...up private VLAN ID Step 5 Enter the following commands to configure port PRT port 10 Example Router config interface FastEthernet10 Router config if no ip address Router config if no ip route cache Router config interface FastEthernet10 1 Router config if encapsulation dot1Q public VLAN ID native Router config if no ip route cache Router config if no snmp trap link status Router config if bridge g...

Page 173: ...ce test for the ONS 15454 ETSI or ONS 15454 ANSI Purpose Voltmeter Tools Equipment Applicable procedures in Installing the ONS 15454 M12 ANSI and ETSI Shelf on page 23 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 If you installed an ONS 15454 ETSI shelf complete the following table by verifying that each applicable procedure was comp...

Page 174: ...4 Multishelf Node on page 152 if you completed NTP G295 Connect the ONS 15454 Multishelf Node and Subtending Shelves to a Catalyst 2950 or Catalyst 3560 on page 146 Step 2 If you installed an ONS 15454 ANSI shelf complete the following table by verifying that each applicable procedure was completed Table 25 ONS 15454 ANSI Shelf Installation Task Summary Completed Description NTP G305 Unpack and In...

Page 175: ...e Voltage on page 146 Step 5 Continue with Connect the PC and Log into the GUI document Stop You have completed this procedure DLP G35 Inspect the Shelf Installation and Connections Use this task to inspect the shelf installation and connections and verify that everything is installed and connected properly Purpose None Tools Equipment None Prerequisite Procedures Required Required As Needed Onsit...

Page 176: ...correct if necessary Battery and ground are reversed to the shelf Battery is open or missing Return is open or missing Step 3 Repeat Steps 1 and 2 for the RET2 and BAT2 of the redundant power supply input Step 4 Return to your originating procedure NTP NTP G295 Connect the ONS 15454 Multishelf Node and Subtending Shelves to a Catalyst 2950 or Catalyst 3560 Use this procedure to connect a multishel...

Page 177: ...atalyst 3560 switches complete the following a Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 7 Plug the other end into Port 2 of the active Catalyst 2950 or Catalyst 3560 b Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 Plug the other...

Page 178: ...Two Cisco Catalyst 3560 switches must be installed in same rack as the node controller shelf refer to the Cisco Catalyst 3560 product documentation for installation instructions Cross over CAT 5 LAN cables 3 plus 2 for each subtending shelf Tools Equipment NTP G15 Install the Common Control Cards on page 131 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote Cisco ONS 15454 ...

Page 179: ...3560 switches a Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 7 Plug the other connector into Port 2 of the active Catalyst 3560 b Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 Plug the other connector into Port 2 of the standby Cata...

Page 180: ...ust be installed in same rack as the node controller shelf refer to the Cisco Catalyst 3560 product documentation for installation instructions Cross over CAT 5 LAN cables 3 plus 2 for each subtending shelf Tools Equipment NTP G15 Install the Common Control Cards on page 131 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Cisco ONS 15454 Hardware Insta...

Page 181: ... in Slot 7 Plug the other connector into Port 2 of the active Catalyst 3560 b Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 Plug the other connector into Port 2 of the standby Catalyst 3560 Step 4 Repeat Step 3a and Step 3b to connect additional subtending shelves using Port 3 through Port 24 on the extended Catal...

Page 182: ...on Note The ONS 15454 works with any VLAN ID type The ONS 15454 M6 works with public VLAN ID of 1 and private VLAN ID of 2 Public and Private VLAN IDs are specified in the multishelf configuration of ONS 15454 node controller Procedure Step 1 At the Cisco IOS command line interface CLI for the Catalyst switch enter the following spanning tree commands Example Switch config spanning tree mode rapid...

Page 183: ...config if spanning tree port priority 0 Switch config interface FastEthernet0 23 Switch config if switchport trunk encapsulation dot1q Switch config if switchport trunk allowed vlan public VLAN ID private VLAN ID Switch config if switchport mode trunk Switch config if spanning tree port priority 0 Step 5 For a 24 port catalyst switch enter the following commands to configure Port 24 Replace port w...

Page 184: ...the EAP to the Node Controller and Subtending Shelf on page 155 shows an example of two installed EAPs and the connection between each EAP and a node controller shelf and a subtending shelf An EAP cable is used to connect the MS ISC 100T card ports to the EAP Figure 69 EAP Cable on page 155 The nine connector ends plug into Ports 0 through 8 of the MS ISC 100T card and the multiport connector plug...

Page 185: ...e 68 Connecting the EAP to the Node Controller and Subtending Shelf Figure 69 EAP Cable Cisco ONS 15454 Hardware Installation Guide 155 Installing the ONS 15454 M12 ANSI and ETSI Shelf Ethernet Adapter Panel ...

Page 186: ...CTC When installed the filler card aids in maintaining proper air flow and EMI requirements Do not use 15454 M FILLER or 15454 M T FILLER filler cards in the Cisco ONS 15454 M12 shelf Note The following figure shows the card faceplate The filler card has no card level LED indicators Blank cards 15454 BLANK can be installed in any empty slot in the shelf CTC does not detect blank cards Cisco ONS 15...

Page 187: ...uns the width of the shelf Figure 71 Managing Cables on the Front Panel on page 158 Plastic horseshoe shaped fiber guides at each side opening of the cable routing channel that ensure that the proper bend radius is maintained in the fibers Figure 72 Fiber Capacity on page 159 Cisco ONS 15454 Hardware Installation Guide 157 Installing the ONS 15454 M12 ANSI and ETSI Shelf Cable Routing and Manageme...

Page 188: ...ch reel Note Optional fiber storage tray recommended for DWDM nodes Optional tie down bar ANSI only The following figure shows the cable management facilities that you can access through the fold down front door including the cable routing channel and the jumper routing fins Figure 71 Managing Cables on the Front Panel Fiber Management The jumper routing fins are designed to route fiber jumpers ou...

Page 189: ...ch 1 6 mm 70 80 90 0 7 inch 2 mm 32 36 40 0 11 inch 3 mm The following table provides the maximum capacity of the fiber channel for one side of an ETSI shelf depending on fiber size and number of Ethernet cables running through that fiber channel Table 27 ETSI Fiber Channel Capacity One Side of the Shelf Maximum Number of Fibers Exiting Each Side Fiber Diameter Two Ethernet Cables One Ethernet Cab...

Page 190: ...eight fibers each entering the drawer or 64 cables with a maximum outer diameter of 2 mm 0 079 in The deep patch panel has the bulkheads organized in 8 packs each housing 8 LC adapters which allows for more room for internal fiber routing as well as more clearance for ingress and egress of the cables The deep patch panel comes with the MPO LC cables preinstalled Because the standard and deep patch...

Page 191: ...d is used with expanded ROADM terminal hub and mesh nodes Expanded hub and ROADM nodes will typically require two 40 channel patch panel modules each terminal nodes require one 40 channel patch panel tray and one 40 channel patch panel tray is needed for mesh nodes for each direction The module fits 19 and 23 inch 482 6 mm and 584 2 mm ANSI racks and 600 mm 23 6 inch x 300 mm 11 8 inch ETSI racks ...

Page 192: ...anel allows up to 4 sides to be used per mesh node while the eight degree patch panel allows up to 8 sides to be used per mesh node The 4 degree patch panel tray can host up to 4 MPO MPO and 4 LC LC cables and the 8 degree patch panel tray can host up to 8 MPO MPO and 8 LC LC cables The module fits 19 and 23 inch 482 6 mm and 584 2 mm ANSI racks and 600 mm 23 6 inch x 300 mm 11 8 inch ETSI racks u...

Page 193: ...ng to the local site practice The PP Mesh is a 2 rack unit RU high Each package includes one set of the following brackets 19 inch 482 6 mm or 23 inch 584 2 mm reversible two way mounting brackets that can be rotated to fit either rack size These reversible brackets are used for EIA and IEC standard racks ETSI brackets that are used for ETSI standard racks Cisco ONS 15454 Hardware Installation Gui...

Page 194: ...an ANSI 19 Configuration This procedure describes the steps to install the PP Mesh on an ANSI 19 configuration Procedure Step 1 Set the mounting brackets to the rack you are using Step 2 Install the right and left ANSI 19 bracket to the unit using the four washer and the screws provided with the installation kit Cisco ONS 15454 Hardware Installation Guide 164 Installing the ONS 15454 M12 ANSI and ...

Page 195: ... two screws on each side Figure 83 Mesh Panel Unit Figure 84 Mesh Panel Unit Front View Step 4 Install the right Vertical cable guide VCG using the washer and the screw provided with the installation kit Cisco ONS 15454 Hardware Installation Guide 165 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 19 Configuration ...

Page 196: ... be installed in bottom position Figure B if the fibers are connected from the bottom Figure 85 Figure A Specifications SerialNumber Rack 1 Vertical Cable Guide 2 Velcro Tie Wrap 3 Cisco ONS 15454 Hardware Installation Guide 166 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 19 Configuration ...

Page 197: ...e 2 Install PP Mesh on an ANSI 23 Configuration This procedure describes the steps to install the PP Mesh on an ANSI 23 configuration Cisco ONS 15454 Hardware Installation Guide 167 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 23 Configuration ...

Page 198: ...provided with the installation kit Figure 87 Right and Left ANSI 23 Bracket Step 3 Install the right Mesh Panel unit in the ANSI 23 rack To ensure safe unit mounting use at least two screws on each side Figure 88 Mesh Panel Unit Cisco ONS 15454 Hardware Installation Guide 168 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 23 Configuration ...

Page 199: ...de can be installed in top position Figure A if the fibers are connected from the top or they can be installed in bottom position Figure B if the fibers are connected from the bottom Figure 90 Figure A Specifications SerialNumber Rack 1 Cisco ONS 15454 Hardware Installation Guide 169 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 23 Configuration ...

Page 200: ... Guide 2 Velcro Tie Wrap 3 Figure 91 Figure B Specifications SerialNumber Rack 1 Vertical Cable Guide 2 Cisco ONS 15454 Hardware Installation Guide 170 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ANSI 23 Configuration ...

Page 201: ...I bracket to the unit using the four washer and the screws provided with the installation kit Figure 92 Right and Left ETSI Bracket Step 3 Install the right Mesh Panel unit in the ETSI rack To ensure safe unit mounting use at least two screws on each side Figure 93 Mesh Panel Unit in ETSI Rack Cisco ONS 15454 Hardware Installation Guide 171 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install ...

Page 202: ...cal Cable Guide The Vertical Cable Guide can be installed in top position left illustration if the fibers are connected from the top or they can be installed in bottom position right illustration if the fibers are connected from the bottom Note Cisco ONS 15454 Hardware Installation Guide 172 Installing the ONS 15454 M12 ANSI and ETSI Shelf Install PP Mesh on an ETSI Configuration ...

Page 203: ...anagement Using the Fiber Storage Tray Cisco recommends installing at least one fiber storage tray in multinode racks to facilitate fiber optic cable management for DWDM applications This tray is usually used to store slack cable from cables installed between cards within a single node Refer to Figure 62 Typical DWDM Equipment Layout in an ONS 15454 ANSI Rack on page 122 for typical mounting locat...

Page 204: ... 0 6 inch 1 6 mm 48 0 7 inch 2 mm 32 0 11 inch 3 mm The following figure shows an example of a fiber management tray with fiber optic cables routed through it You can route cables around the cable rounders entering and exiting from either side as necessary Route fibers as necessary for your site configuration Cisco ONS 15454 Hardware Installation Guide 174 Installing the ONS 15454 M12 ANSI and ETS...

Page 205: ...c material to bundle the cabling and attach it to the bar so that you can more easily route the cable away from the rack The following figure shows the tie down bar the ONS 15454 ANSI and the rack Figure 100 Tie Down Bar on the Cisco ONS 15454 ANSI Shelf Cisco ONS 15454 Hardware Installation Guide 175 Installing the ONS 15454 M12 ANSI and ETSI Shelf Fiber Management Using the Optional ANSI Tie Dow...

Page 206: ...Cisco ONS 15454 Hardware Installation Guide 176 Installing the ONS 15454 M12 ANSI and ETSI Shelf Fiber Management Using the Optional ANSI Tie Down Bar ...

Page 207: ...ojects 1 7 inches 43 18 mm from the front of the rack If the shelf is mounted in the middle position then it projects 5 1 inches 129 54 mm from the front of the rack The shelf mounts in both Electronic Industries Alliance EIA standard and Telcordia standard racks The shelf is a total of 17 2 inches 431 8 mm wide with no mounting ears attached Ring runs are not provided by Cisco and might hinder si...

Page 208: ...n mounting the ONS 15454 M2 shelf in a frame with a nonconductive coating such as paint lacquer or enamel either use the thread forming screws provided with the ONS 15454 M2 shipping kit or remove the coating from the threads to ensure electrical continuity Caution The mounting brackets 19 inch or 23 inch are used to mount the shelf on a 19 inch 482 6 mm rack or a 23 inch 584 2 mm rack Cisco ONS 1...

Page 209: ...ETSI standard equipment rack In an ETSI rack the shelf can be mounted only in the front position The shelf projects 1 7 inches from the front of the rack The shelf is a total of 17 2 inches 431 8 mm wide with no mounting ears attached Cisco does not provide ring runs which might hinder side by side installation of shelves where space is limited The ONS 15454 M2 shelf measures 88 9 mm 3 5 inches hi...

Page 210: ...between the shelves This method of mounting does not restrict the air flow because the air vents are on either sides of the ONS 15454 M2 shelves Wall Mounting the ONS 15454 M2 Shelf The ONS 15454 M2 shelf can be mounted on the wall using the wall mount brackets The type of screws used to mount the brackets on the wall depends on the wall type and are not provided by Cisco After the ONS 15454 M2 sh...

Page 211: ...flow in the front to back direction inside the equipment to be compliant with GR 63 issue 4 requirement The air plenum kit has one horizontal and two vertical air plenums The air that flows from the front top inlet are channelized to the right vertical plenum inside the equipment and then to the exhaust air channel towards the left vertical air plenum The air flow is deflected by 90 degrees and ex...

Page 212: ...d ETSI racks and cabinets The chassis can be installed with brackets in front position only Table 29 Air plenum compatibility with racks and cabinets Front to back air flow Rack Cabinet Supported 1 ANSI 19 inch rack Supported 1 ANSI 19 inch cabinet Supported ANSI 23 inch rack Supported ANSI 23 inch cabinet Supported 1 ETSI cabinet Cisco ONS 15454 Hardware Installation Guide 182 Installing the ONS ...

Page 213: ...the air plenum to orient the air flow from front to back direction in the ONS 15454 M2 shelf Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Screws ANSI 12 24 x 0 50 pan head Phillips screws ETSI M6 0 x 20 pan head Phillips screws Wing head screws 4 Adapter plates One air plenum kit horizontal and vertical air plenums Tools Equipment As needed R...

Page 214: ...tatement 1046 Warning The air plenum is installed on a rack or a cabinet using thread forming screws that remove any paint or non conductive coatings inside the hole threads and establish a metal to metal contact Also clean both surfaces outside the screw points that come in contact so that they are free of paint and other nonconductive coating Apply an appropriate antioxidant compound to the surf...

Page 215: ...be mounted only if the minimum opening is 20 600 inches to install the vertical air plenums behind the front rails Note Procedure Step 1 Place the horizontal air plenum above the shelf slot in the ANSI 19 inch cabinet or rack Step 2 Insert the wing head screws provided with the kit and tighten to a torque value of 11 5 in lb 1 3 N m Figure 107 Installing the horizontal air plenum in the ANSI 19 in...

Page 216: ...ow step 3a to 3c Figure 109 Installing the right vertical air plenum Step 5 Install the 19 inch standard brackets on both sides of the chassis in the front position See DLP G582 Mounting the 19 inch Brackets on the ONS 15454 M2 Shelf for ANSI Rack Configuration on page 197 Step 6 Install the ONS 15454 M2 empty chassis below the horizontal plenum Cisco ONS 15454 Hardware Installation Guide 186 Inst...

Page 217: ...slot head screwdriver Small slot head screwdriver Screws 12 24 x 3 4 pan head Phillips mounting screws 4 Wing head screws 4 Adapter plates One air plenum kit horizontal and vertical air plenum Tools Equipment As needed Required As Needed Onsite Onsite Remote None Security Level The airplenums for ANSI 23 inch configuration can be pre assembled outside the cabinet and then installed inside the cabi...

Page 218: ... 111 Installing the adapter plates on the horizontal air plenum Step 3 Place the horizontal air plenum above the shelf slot in the ANSI 23 inch cabinet or rack Step 4 Insert the wing head screws provided with the kit and tighten to a torque value of 11 5 in lb 1 3 N m Cisco ONS 15454 Hardware Installation Guide 188 Installing the ONS 15454 M2 Shelf DLP G764 Install Air Plenum in ONS 15454 M2 Shelf...

Page 219: ...e wing head screws from the internal side of the horizontal plenum as shown in the following figure c Tighten the screws to a torque value of 11 5 in lb 1 3 N m Figure 113 Installing the left vertical air plenum Step 6 Install the vertical plenum to the right of the horizontal air plenum Follow step 5a to 5c Cisco ONS 15454 Hardware Installation Guide 189 Installing the ONS 15454 M2 Shelf DLP G764...

Page 220: ...Shelf for ANSI Rack Configuration on page 197 Step 8 Install the ONS 15454 M2 empty chassis below the horizontal plenum Figure 115 Installing the ONS 15454 M2 chassis below the horizontal air plenum Step 9 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 190 Installing the ONS 15454 M2 Shelf DLP G764 Install Air Plenum in ONS 15454 M2 Shelf for ANSI 23 inch Conf...

Page 221: ...lenum kit horizontal and vertical air plenum Tools Equipment As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Install the ETSI adapter plates on the horizontal air plenum Step 2 Align the screws to fix the adapter plates to the horizontal air plenum Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m as shown in the following figure Cisc...

Page 222: ...ue value of 11 5 in lb 1 3 N m Figure 117 Installing the horizontal air plenum in the ETSI configuration Step 5 Install the vertical air plenum to the left of the horizontal air plenum a Insert the vertical plenum in the free space between the horizontal plenum and cabinet Cisco ONS 15454 Hardware Installation Guide 192 Installing the ONS 15454 M2 Shelf DLP G765 Install Air Plenum for ONS 15454 M2...

Page 223: ...5a to 5c Figure 119 Installing the right vertical air plenum Step 7 Install the ANSI 19 inch mounting brackets on both sides of the chassis in front position See DLP G588 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 208 Step 8 Install the ONS 15454 M2 empty chassis below the horizontal plenum Cisco ONS 15454 Hardware Installati...

Page 224: ...an head Phillips mounting screws Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Stability hazard The rack stabilizing mechanism must be in place or the rack must be bolted to the floor before you slide the unit out for servicing Failure to stabili...

Page 225: ...he maximum recommended ambient temperature of 131 F 55 C Statement 1047 Warning Take care when connecting units to the supply circuit so that wiring is not overloaded Statement 1018 Warning To prevent bodily injury when mounting or servicing this unit in a rack you must take special precautions to ensure that the system remains stable The following guidelines are provided to ensure your safety War...

Page 226: ...n on page 203 DLP G587 Mounting the Bracket with Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 205 DLP G588 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 208 Step 2 Complete the necessary mounting task as applicable DLP G589 Mount the ONS 15454 M2 Shelf on a Rack One Person on page 20...

Page 227: ...h a nonconductive coating such as paint lacquer or enamel either use the thread forming screws provided with the ONS 15454 M2 ship kit or remove the coating from the threads to ensure electrical continuity Caution The mounting brackets can be installed in the front or the middle position of the chassis Note Procedure Step 1 Place the wider side of the 19 inch mounting bracket flush against the she...

Page 228: ...5454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M2 to prevent loosening deterioration and electromechanical corrosion of the hardware and joined material Caution When mounting the ONS 15454 M2 in a frame with a nonconductive coating such as paint lacquer or enamel ei...

Page 229: ...lf for a 23 inch 584 2 mm ANSI Configuration Step 5 Return to your originating procedure NTP DLP G584 Mounting the Bracket with Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ANSI Rack Configuration This task mounts the 23 inch brackets with air deflectors front to back on the ONS 15454 M2 shelf for ANSI rack configuration In an ANSI rack the air deflectors can be mounted only in the 2...

Page 230: ...es on the left back air deflector with the screw holes on the chassis Step 6 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m See Diagram 2 of Figure 123 Mounting the Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ANSI Rack Configuration on page 201 Step 7 Place the air deflector covers on the front and rear ends of the chassis as shown in Diagram 3 of Figure ...

Page 231: ...n the screw holes on the 23 inch mounting bracket with the screw holes on the left side of the chassis Step 15 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Figure 123 Mounting the Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ANSI Rack Configuration Figure 124 Mounting the Brackets on the ONS 15454 M2 Shelf for ANSI Rack Configuration Cisco ONS 15454 Hard...

Page 232: ...ation and electromechanical corrosion of the hardware and joined material Caution When mounting the ONS 15454 M2 in a frame with a nonconductive coating such as paint lacquer or enamel either use the thread forming screws provided with the ONS 15454 M2 ship kit or remove the coating from the threads to ensure electrical continuity Caution Procedure Step 1 Place the mounting bracket flush against t...

Page 233: ...r Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M2 to prevent loosening deterioration and electromechanical corrosion of the hardware and joined material Caution The air deflectors can ...

Page 234: ...f for ETSI Rack Configuration on page 205 Step 7 Place the air deflector covers on the rear ends of the chassis as shown in Diagram 2 of Figure 126 Mounting the Air Deflectors Front to Front on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 205 Step 8 Align the screw holes on the air deflector covers with the screw holes on the chassis Step 9 Insert the screws and tighten them to a tor...

Page 235: ...ot head screwdriver Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M2 to prevent loosening deterioration and electromechanical corrosion of the hardware and joined material Caution The a...

Page 236: ...ign the screw holes on the air deflector covers with the screw holes on the chassis Step 9 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m See Diagram 4 of Figure 127 Mounting the Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 207 Step 10 Place the mounting bracket flush in the front position see Diagram 1 of Figure 128 Mountin...

Page 237: ...ts with Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ETSI Rack Configuration Step 16 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 207 Installing the ONS 15454 M2 Shelf DLP G587 Mounting the Bracket with Air Deflectors Front to Back on the ONS 15454 M2 Shelf for ETSI Rack Configuration ...

Page 238: ... deflector with the screw holes on right side of the chassis Step 3 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 4 Place the air deflector cover on the rear end of the chassis Step 5 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m See Diagram 2 of Figure 129 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M2 Shelf...

Page 239: ...s directly to mount the ONS 15454 M2 shelf Note Step 13 Align the screw holes with the screw holes of the mounting bracket and the chassis Step 14 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m See Diagram 4 of Figure 129 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M2 Shelf for ETSI Rack Configuration on page 209 Figure 129 Mounting the Bracke...

Page 240: ...power supply the fuse rating must not exceed 15A For an AC power supply the fuse rating must not exceed 10A 15A or 20A For North America the branch circuit protection must be rated 20A The overcurrent short circuit protection must be in accordance with local and national electrical codes Step 2 Ensure that the shelf is mounted on the appropriate rack equipment 23 inches 584 2 mm or 19 inches 482 6...

Page 241: ...ue value of 22 in lb 2 5 N m Step 6 When the shelf is secured to the rack install the remaining two mounting screws on either sides of the shelf Step 7 Return to your originating procedure NTP DLP G590 Mount the ONS 15454 M2 Shelf on the Wall This task explains how to mount the ONS 15454 M2 shelf on the wall Purpose 2 Phillips Dynamometric screwdriver 6 pan head Phillips mounting screws Tools Equi...

Page 242: ...15A or 20A For North America the branch circuit protection must be rated 20A The overcurrent short circuit protection must be in accordance with local and national electrical codes Step 2 Mount the bracket on the wall as shown in Figure 131 Wall Mounting of the ONS 15454 M2 Shelf on page 213 To mount the bracket on a non concrete wall choose the bracket holes based on the wall structure At least f...

Page 243: ...unting an ONS 15454 M2 in a Rack on page 211 The fire protective drip tray is present in the wall mount accessory kit provided by Cisco Step 6 Insert the screws and tighten them see diagram 2 of Figure 130 Mounting an ONS 15454 M2 in a Rack on page 211 Cisco ONS 15454 Hardware Installation Guide 213 Installing the ONS 15454 M2 Shelf DLP G590 Mount the ONS 15454 M2 Shelf on the Wall ...

Page 244: ...and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Verify that the proper fuse panel has been installed If a fuse panel is not present you must install one according to manufacturer instructions For a DC power supply the fuse rating must not exceed 15A Cisco ONS 15454 Hardware Installation Guide 214 Ins...

Page 245: ...eturn to your originating procedure NTP Front Door The front door of the ONS 15454 M2 provides access to the shelf and air filter There are two types of front doors that act as protective panels standard door and deep front panel The deep front panel provides additional space in front of the shelf to accommodate cables that do not fit inside the standard door The deep front panel does not have a h...

Page 246: ...ns on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms NTP G267 Install the Power Module in the ONS 15454 M2 Shelf on page 230 NTP G268 Install the Fan Tray Assembly in the ONS 15454 M2 Shelf on page 235 NTP G271 Install the Power and Ground to the ONS 15454 M2 Shelf on page 239 NTP G291 Attach Wires to Timing LAN and Craft Pi...

Page 247: ...Reinstall the door after installing all the other modules Note Step 4 Place the ground strap cable on the door and the chassis and tighten the nuts Figure 137 Ground Strap Cable Standard Door Cisco ONS 15454 Hardware Installation Guide 217 Installing the ONS 15454 M2 Shelf NTP G269 Install the Standard Door of the ONS 15454 M2 Shelf ...

Page 248: ...Install the Standard Door of the ONS 15454 M2 Shelf on page 216 Connect the chassis to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Complete the DLP G594 Open the Stan...

Page 249: ...4 M2 shelf has an ESD plug input and is shipped with an ESD wrist strap The ESD plug input is located on the outside of the shelf on the right side It is labeled ESD on the top and bottom Always wear an ESD wrist strap and connect the strap to the ESD plug when working on the ONS 15454 M2 For detailed instructions on how to wear the ESD wristband refer to the http www cisco com en us docs optical ...

Page 250: ...ct the chassis to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Unscrew the nut holding the ground cable to the shelf Remove the nut Step 2 Remove the ground cable fro...

Page 251: ...te direction Step 4 Remove the door from its hinges as shown in the following figure Figure 142 Removing the Standard Door Step 5 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 221 Installing the ONS 15454 M2 Shelf DLP G595 Remove the Standard Door of the ONS 15454 M2 Shelf ...

Page 252: ... Craft Pin Connections in ONS 15454 M2 on page 254 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use the deep front panel when ONS SC 10G C pluggables are installed on ONS 15454 M2 shelf Note The deep front panel does not have a hinge and cannot be rotated like a standard door Rotating the deep front panel can damage the deep front panel shelf hinges...

Page 253: ...e Figure 144 Loosening the Deep Front Panel screws Step 3 Place the deep front panel close to the shelf so that the shelf notches and the deep front panel retention features are in line see the following figure Cisco ONS 15454 Hardware Installation Guide 223 Installing the ONS 15454 M2 Shelf NTP G343 Install the Deep Front Panel of the ONS 15454 M2 Shelf ...

Page 254: ...op of the shelf see Figure 145 Moving Deep Front Panel and Shelf in line on page 224 b Align the deep front panel pins present at the bottom of the panel with the shelf hinges see the following figure Figure 146 Aligning the Deep Front Panel and Shelf The following figure shows the deep front panel aligned with the shelf Cisco ONS 15454 Hardware Installation Guide 224 Installing the ONS 15454 M2 S...

Page 255: ...ently applying outward pressure to the panel Figure 148 Engaging the Deep Front Panel and Shelf Step 6 Lock the deep front panel by tightening the screws to a torque value of 6 5 in lb 0 75 N m Step 7 Connect the other end of the ground strap cable to the ground point present on the deep front panel exterior Cisco ONS 15454 Hardware Installation Guide 225 Installing the ONS 15454 M2 Shelf NTP G343...

Page 256: ...lf on page 222 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level The deep front panel does not have a hinge and cannot be rotated like a standard door Rotating the deep fr...

Page 257: ...the deep front panel screws and slide them outwards using the plastic tabs as shown in the following figure to open the deep front panel Figure 151 Moving the deep front panel to disengage Step 3 Move the deep front panel away from the shelf see the following figure Cisco ONS 15454 Hardware Installation Guide 227 Installing the ONS 15454 M2 Shelf NTP G331 Remove the Deep Front Panel of the ONS 154...

Page 258: ...en the ground nut on the shelf b Remove the lug and tighten the nut on the shelf to a torque value of 11 5 in lb 1 3 N m Stop You have completed this procedure Power Modules The ONS 15454 M2 system contains the following pluggable power modules AC power module DC power module Cisco ONS 15454 Hardware Installation Guide 228 Installing the ONS 15454 M2 Shelf Power Modules ...

Page 259: ...h or 0 64 mm 0 0252 inch twisted pair T1 type Note Refer to Telcordia SR NWT 002224 for rules about provisioning timing references Note AC Power Module The AC power module converts the AC input current to DC output current Each AC power module has One AC single phase three poles line L Neutral N and Protective Earth PE input connector One RJ 45 port for EMS connection One USB port to support passi...

Page 260: ...LED indicates that the battery is connected but an alarm is present due to secondary fuse break 48 V The DC power module does not support the lamp test procedure The fork or ring terminals used on the DC power modules are not available from Cisco but they are available commercially Ensure that the hole size of the fork terminal or ring terminal is greater than 3 5 mm and width is less than or equa...

Page 261: ... this procedure DLP G592 Install the AC Power Module in the ONS 15454 M2 Shelf This procedure installs the AC power module in the ONS 15454 M2 system Purpose 2 Phillips screwdriver Tools Equipment NTP G266 Install the ONS 15454 M2 Shelf on page 194 Connect the chassis to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guid...

Page 262: ...e value of 4 in lb 0 45 N m to lock the power module in the chassis see the following figure Figure 155 AC Power Module Installed in the ONS 15454 M2 Shelf Stop You have completed this procedure Cisco ONS 15454 Hardware Installation Guide 232 Installing the ONS 15454 M2 Shelf DLP G592 Install the AC Power Module in the ONS 15454 M2 Shelf ...

Page 263: ...Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Insert the DC power module in Slot A see the following figure Figure 156 Installing the DC Power Module Step 2 Plug the DC power module completely into the chassis Step 3 Tighten the screw to a torque value of 4 in lb 0 45 N m to lock the power m...

Page 264: ...tray assembly is functioning the power line is connected and the power module is functioning properly the LED is green When the power line is connected and if there is no TNC TNCE TSC TNCS 2 TNCS 2O or TSCE card installed in the ONS 15454 M2 shelf then the LED is OFF The shelf controller card controls the conditions that result in triggering the LEDs The LED can be overwritten by the shelf control...

Page 265: ...mperature at the fan tray assembly Fan speed options are low medium and high If the TNC TNCE TSC TNCS 2 TNCS 2O or TSCE card fails the fans automatically shift to high speed The temperature measured by the TNC TNCE TSC TNCS 2 TNCS 2O or TSCE sensors appears on the LCD screen Fan Failure If one or more fans fail on the fan tray assembly replace the entire assembly You cannot replace individual fans...

Page 266: ...ller CTC when the fan tray module is removed from the shelf or when one fan is not working Note During the system startup or fan tray replacement the inventory data of the fan tray assembly and the power module is displayed in the Inventory tab of CTC after a delay of approximately 6 minutes Note To install the fan tray assembly it is not necessary to move any of the fiber routing facilities Note ...

Page 267: ...g it back into the shelf In the event the LCD display on the fan tray assembly appears blank remove the unit from the shelf wait for at least 5 seconds and reinsert the unit into the shelf Note Stop You have completed this procedure Power and Ground Description Ground the equipment according to Telcordia standards or local practices The grounding configuration is mandatory for ANSI and ETSI chassi...

Page 268: ... battery connections 48 VDC Black wire for battery return connections RET The battery return connection is treated as DC I as defined in Telcordia GR 1089 CORE Issue 3 The ground lug must be a dual hole type UL Listed CSA certified and rated to accept the 6 AWG cable Two ground posts with two M5 nuts are provided on the ONS 15454 M2 to accommodate the dual hole lug ETSI Power and Ground For AC pow...

Page 269: ...nding lug shipped with the ONS 15454 M2 Tools Equipment NTP G267 Install the Power Module in the ONS 15454 M2 Shelf on page 230 Connect the chassis to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Sec...

Page 270: ...th upturned lugs These terminations should be the appropriate size for the wires and should clamp both the insulation and conductor Statement 1002 Warning Before performing any of the following procedures ensure that power is removed from the DC circuit Statement 1003 Warning Before working on a chassis or working near power supplies unplug the power cord on AC units Statement 246 Warning This equ...

Page 271: ...protection must not be rated more than 20A The overcurrent short circuit protection must be in accordance with local and national electrical codes Step 2 Depending on the shelf and the power module installed complete the necessary tasks DLP G596 Connect Office Power AC to the ONS 15454 M2 Shelf on page 241 DLP G597 Connect Office Power DC to the ONS 15454 M2 Shelf ANSI Only on page 244 DLP G598 Co...

Page 272: ...d Onsite Onsite Remote None Security Level This product is intended for use on the TN and TT power systems Note When installing or replacing the unit the ground connection must always be made first and disconnected last Statement 1046 Warning This equipment shall be connected to AC mains provided with a surge protective device SPD at the service equipment complying with NFPA 70 the National Electr...

Page 273: ... 15 To reset the clock see the NTP G24 Setting Up Node Identification Information Note Procedure Step 1 Verify that the AC power module is installed in Slot A of the ONS 15454 M2 Step 2 Attach the AC power cable to the cable connector in the AC power module see the following figure Figure 161 Connecting Office Power AC Power Modules Step 3 Close the cable clip to secure the power cable see the fol...

Page 274: ... cable India right exit 15454 M CBL R EU AC power cable EU right exit 15454 M CBL RARG AC power cable ARG right exit 15454 M CBL RAUS AC power cable AUS right exit 15454 M CBL R UK AC power cable UK right exit 15454 M CBL RKOR AC power cable KOR right exit 15454 M ACCBL R AC power cable ANSI 110VAC right exit 15454 M ACCBL R2 AC power cable ANSI 220VAC right exit 15454 M ACL6 R AC power cable for ...

Page 275: ...e ONS 15454 M2 Shelf on page 230 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level When installing or replacing the unit the ground connection must always be made first and disconnected last Statement 1046 Warning Hazardous voltage or energy may be present on DC power terminals Always replace cover when terminals are not in service Be sure uninsulated con...

Page 276: ... cables of the power supply to the Earth ground located at the power supply side Step 2 Connect the office power according to the fuse panel engineering specifications Step 3 Measure and cut the cables as needed to reach the ONS 15454 M2 from the fuse panel Step 4 Dress the power according to local site practice Step 5 Strip 1 2 inch 12 7 mm of insulation from all power cables that you will use St...

Page 277: ...r DC Power Module ANSI Only Step 9 Insert the lugs as shown in the following figure Cisco ONS 15454 Hardware Installation Guide 247 Installing the ONS 15454 M2 Shelf DLP G597 Connect Office Power DC to the ONS 15454 M2 Shelf ANSI Only ...

Page 278: ...he screws to a torque value of 4 in lb 0 45 N m of the terminal block protective cover on the DC power module see the following figure Use only pressure terminal connectors such as ring and fork types when terminating the battery battery return and frame ground conductors Note Figure 165 Connecting Office Power DC Power Modules ANSI Only Cisco ONS 15454 Hardware Installation Guide 248 Installing t...

Page 279: ...c screwdriver Medium slot head screwdriver Small slot head screwdriver Wire wrapper Wire cutters Wire strippers Crimp tool Fuse panel Ground cable 6 AWG stranded The PID of the DC power cable for ETSI left exit is 15454 M2 DCCBL LE Tools Equipment NTP G266 Install the ONS 15454 M2 Shelf on page 194 Connect the chassis to the office ground For detailed instructions on how to ground the chassis refe...

Page 280: ... is not provisioned to get the time from a Network Time Protocol Simple Network Time Protocol NTP SNTP server you must reset the ONS 15454 clock After powering down the date defaults to January 1 1970 00 04 15 To reset the clock see the see the NTP G24 Setting Up Node Identification Information If you are using the TNC TNCE TSC TNCS 2 TNCS 2O or TSCE cards the system clock will run for up to three...

Page 281: ...bars to a bright finish then coat with an antioxidant before you connect them You do not need to prepare tinned solder plated or silver plated connectors and other plated connection surfaces but always keep them clean and free of contaminants Caution When terminating power return and frame ground do not use soldering lug screwless push in connectors quick connect or other friction fit connectors C...

Page 282: ...l the module is completely installed into the chassis Statement 389 Warning To reduce the risk of electric shock switch on the power only after the power cord is completely installed into the power module Statement 390 Warning Procedure Step 1 To power up the node insert the fuse into the fuse position according to site practice The fuse rating must not exceed 15A in case of AC power Step 2 If the...

Page 283: ...ule Statement 390 Warning Procedure Step 1 Using a voltmeter verify the office battery and ground at the following points on the fuse panel a To verify the power place the black test lead of the voltmeter to the frame ground Place the red test lead on the A side connection and verify that it is between 40 5 VDC and 57 6 VDC Place the red test lead on the B side connection and verify that it is bet...

Page 284: ...aft Pin Connections in ONS 15454 M2 This procedure attaches wires to the Timing LAN and Craft Pin connections in the ONS 15454 M2 shelf Purpose Twisted 22 or 24 AWG 0 51 mm or 0 64 mm shielded wires for LAN or craft 75 ohm coaxial cable with DIN 1 0 2 3 miniature coax connector Tools Equipment NTP G267 Install the Power Module in the ONS 15454 M2 Shelf on page 230 Prerequisite Procedures As needed...

Page 285: ...an external LAN connection Stop You have completed this procedure DLP G292 Install Timing Wires in ONS 15454 M2 ANSI This task installs the timing wires in the DC 2 or AC 2 Power Module of ONS 15454 M2 ANSI Purpose 100 ohm wire wrap cable wire wrap tool Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Locate the tim...

Page 286: ...Figure 168 DC 2 Power Module ANSI BITS connectors Cisco ONS 15454 Hardware Installation Guide 256 Installing the ONS 15454 M2 Shelf DLP G292 Install Timing Wires in ONS 15454 M2 ANSI ...

Page 287: ...al source of the timing Repeat step 3 for each cable that is needed Step 4 Return to your originating procedure NTP DLP G293 Install Timing Wires in ONS 15454 M2 ETSI This task installs the timing wires in the AC 2 or DC 2E Power Module of ONS 15454 M2 ETSI Purpose Cisco ONS 15454 Hardware Installation Guide 257 Installing the ONS 15454 M2 Shelf DLP G293 Install Timing Wires in ONS 15454 M2 ETSI ...

Page 288: ...quisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Locate the timing BITS connectors in the DC 2E or AC 2 Power Module as shown in the following two figures Cisco ONS 15454 Hardware Installation Guide 258 Installing the ONS 15454 M2 Shelf DLP G293 Install Timing Wires in ONS 15454 M2 ETSI ...

Page 289: ...Figure 170 DC 2E Power Module ETSI BITS Connectors Cisco ONS 15454 Hardware Installation Guide 259 Installing the ONS 15454 M2 Shelf DLP G293 Install Timing Wires in ONS 15454 M2 ETSI ...

Page 290: ...lick The Power Module provides DIN 1 0 2 3 miniature coax connectors that are used for timing input and output The input connectors for timing provide a 75 ohm termination System cables that can convert timing clocks from 75 ohms to 100 120 ohms are available See ITU T G 813 for rules about provisioning timing references Note Step 4 Connect the other end of the cable to the external source of the ...

Page 291: ...r 0 64 mm 22 or 24 AWG wire or a standard CAT 5 Ethernet cable connect the wires to the RJ 45 connector Step 2 Return to your originating procedure NTP NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card This procedure describes how to install and configure the TNC TNCE TSC or TSCE card Purpose Redundant TNC TNCE TSC TSCE cards on Cisco ONS 15454 M6 shelf required Stand alone TNC TNCE TSC...

Page 292: ...6 Configure UDC and VoIP for the TNC and TNCE Cards on page 266 Stop You have completed this procedure DLP G604 Install the TNC TNCE TSC or TSCE Card ONS 15454 M2 and ONS 15454 M6 only This task installs redundant TNC TNCE TSC TSCE TNCS 2 TNCS 2O cards on the ONS 15454 M6 shelf and a stand alone TNC TNCE TSC TSCE TNCs 2 TNCS 2O card on the ONS 15454 M2 shelf Install and initialize the TNC TNCE TSC...

Page 293: ...lf Note To achieve redundancy two TNC or TNCE cards or two TSC or TSCE cards must be installed in the ONS 15454 M6 shelf Do not install one TNC or TNCE card and a redundant TSC or TSCE card in the same shelf Caution Procedure Step 1 Open the latches ejectors of the first TNC TNCE TSC TSCE TNCS 2 TNCS 2O card that you will install Step 2 Use the latches ejectors to firmly slide the card horizontall...

Page 294: ...ce The alarm clears after the TNC TNCE TSC TSCE card boots completely Note If the FAIL LED is on continuously see the tip in step 8 about the TNC TNCE TSC TSCE TNCS 2 TNCS 2O card automatic upload Note The following figure illustrates the installation of TNC and TNCE cards on ONS 15454 M6 shelf Figure 172 Installing TNC and TNCE cards on ONS 15454 M6 Shelf Step 5 Verify that the ACT STBY LED is gr...

Page 295: ...ence and the amber ACT STBY LED turns on Tip Step 9 Return to your originating procedure NTP DLP G605 Provision PPM and Port for the TNC and TNCE Cards ONS 15454 M2 and ONS 15454 M6 only This task provisions a PPM and port on a TNC and TNCE cards PPMs are created to support the OSC function Purpose None Tools Equipment DLP G46 Log into CTC Prerequisite Procedures As needed Required As Needed Onsit...

Page 296: ...s Purpose None Tools Equipment DLP G46 Log into CTC NTP G38 Provisioning OSC Terminations DLP G605 Provision PPM and Port for the TNC and TNCE Cards on page 265 Prerequisite Procedures As needed Required As Needed Onsite or remote Onsite Remote None Security Level Each TNC and TNCE cards support UDC VoIP configuration You can configure UDC or VoIP on the two SFP ports present on the TNC and TNCE c...

Page 297: ... Step 1 If you installed an ONS 15454 M2 shelf complete the following table by verifying that each applicable procedure was completed Table 31 ONS 15454 M2 ETSI Shelf Installation Task Summary Completed Description NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 NTP G266 Install the ONS 15454 M2 Shelf on page 194 Connect the chassis to the office ground F...

Page 298: ...ly Purpose None Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Make sure all external wiring connections that is power ground alarms and so on are secure If a wire or cable is loose return to the appropriate procedure in this chapter to correct it Step 2 Return to your originating procedure NTP DLP G602 Measure DC ...

Page 299: ...ween 40 5 VDC and 57 6 VDC If there is no voltage check the following and correct if necessary Battery and ground are reversed to the shelf Battery is open or missing Return is open or missing Step 3 Repeat the above steps for the RET2 B and 48V B of the redundant power supply input Step 4 Return to your originating procedure NTP Filler and Blank Cards Filler cards must be installed in unused and ...

Page 300: ... sensors appears on the LCD screen in the ONS 15454 M2 chassis Note The input voltages and temperature of the ONS 15454 M2 chassis are displayed in the Shelf view Provisioning General Voltage Temperature pane in CTC The voltage supplied to the shelf in millivolts is displayed in the Voltage area of the Voltage Temperature pane The temperature of the shelf in degree Celsius is displayed in the Temp...

Page 301: ...259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf on page 332 NTP G329 Remove the Deep Front Panel of the ONS 15454 M6 Shelf on page 339 External Connection Units on page 342 NTP G253 Install the ECU or ECU S Module on page 349 NTP L68 Upgrading to ONS 15454 M6 ECU60 S Module on page 352 Power Modules on page...

Page 302: ...ct type of 19 inch ANSI rack is used for mounting the ONS 15454 M6 shelf as shown in Figure 1 19 inch ANSI Rack Post Recommended for Cisco ONS 15454 M6 and M2 Shelves on page 3 If the shelf is mounted in the front position then it projects 1 7 inches 43 18 mm from the front of the rack If the shelf is mounted in the middle position then it projects 5 1 inches 129 54 mm from the front of the rack T...

Page 303: ...ed with the ONS 15454 M6 shipping kit or remove the coating from the threads to ensure electrical continuity Caution The reversible mounting bracket is used to mount the shelf on a 19 inch or 23 inch 482 6 mm or 584 2 mm rack Mounting a Single Shelf Mounting the ONS 15454 M6 shelf on a rack requires a minimum of 10 4 inches 265 mm of vertical rack space To ensure that the mounting is secure use tw...

Page 304: ...he air vents are on either sides of the ONS 15454 M6 shelves ETSI Rack Installation The ONS 15454 M6 shelf is mounted on a 600 x 600 mm 23 6 x 23 6 inch or 600 x 300 mm 23 6 x 11 8 inch ETSI standard equipment rack In an ETSI rack the shelf can be mounted only in the front position The shelf projects 1 7 inch 43 18 mm from the front of the rack and is a total of 431 8 mm 17 inch wide with no mount...

Page 305: ...6 mm 10 4 inches minimum of vertical rack space To ensure the mounting is secure use two to three M6 mounting screws for each side of the shelf A shelf should be mounted at the bottom of the rack if it is the only unit in the rack In an ETSI rack the brackets are mounted only in the front position If the ONS 15454 M6 shelf is fully loaded then two people should install it However it is possible fo...

Page 306: ... control the air flow Front to Front Only ETSI rack Front to Back For ANSI and ETSI racks Front to Top Only ETSI rack In an ANSI rack the air deflectors are mounted only on the 23 inch rack configuration Air Plenum Air plenum orients the air flow in the front to back direction inside the equipment to be compliant with GR 63 issue 4 requirement The air plenum kit has two horizontal and two vertical...

Page 307: ...following two figures shows the dimensions of the air plenum relative to the cabinet or rack Figure 176 Dimension of Cisco ONS 15454 M6 chassis relative to the air plenum Cisco ONS 15454 Hardware Installation Guide 277 Installing the ONS 15454 M6 Shelf Air Plenum ...

Page 308: ...o back air flow Rack Cabinet Supported ANSI 19 inch rack Supported ANSI 19 inch cabinet Supported ANSI 23 inch rack Supported ANSI 23 inch cabinet Supported ETSI cabinet A minimum opening of 20 600 inches is required to install the vertical air plenum behind the front rails The ANSI 19 inch two post rack that is compatible with air plenum installation is available from Telect with part number 1254...

Page 309: ...ews ETSI M6 0 x 20 pan head Phillips screws Wing head screws 8 Adapter plates One air plenum kit horizontal and vertical air plenums Tools Equipment As needed Required As Needed Onsite Onsite Remote None Security Level Before performing any of the following procedures ensure that power is removed from the DC circuit Statement 1074 Warning Before working on a chassis or working near power supplies ...

Page 310: ...rew points that come in contact so that they are free of paint and other nonconductive coating Apply an appropriate antioxidant compound to the surfaces Warning Procedure Depending on the rack or cabinet complete the necessary task DLP G766 Install Air Plenum for ONS 15454 M6 Shelf in ANSI 19 inch Cabinet on page 280 DLP G767 Install Air Plenum in ONS 15454 M6 Shelf for ANSI 23 inch Configuration ...

Page 311: ...lot in the ANSI 19 inch cabinet Step 2 Insert the wing head screws provided with the kit and tighten to a torque value of 11 5 in lb 1 3 N m as shown in the following figure Figure 179 Installing the bottom horizontal air plenum in the ANSI 19 inch cabinet Step 3 Install the vertical air plenum to the left of the horizontal air plenum a Insert the vertical plenum in the free space between the hori...

Page 312: ...um Follow step 3a to step 3c Figure 181 Installing the right vertical air plenum Step 5 Install the horizontal air plenum above the vertical plenums Follow step 3a to step 3c Cisco ONS 15454 Hardware Installation Guide 282 Installing the ONS 15454 M6 Shelf DLP G766 Install Air Plenum for ONS 15454 M6 Shelf in ANSI 19 inch Cabinet ...

Page 313: ...ntal air plenums where the chassis will be installed The length must be not less than 10 5 inches 267 mm If the length is less adjust the position of the top horizontal plenum Step 8 Install the ONS 15454 M6 empty chassis between the two horizontal plenums Figure 183 Installing the ONS 15454 M6 chassis between the horizontal air plenum Step 9 Return to your originating procedure NTP Cisco ONS 1545...

Page 314: ... cabinet and then installed inside the cabinet See DLP G768 Install Pre assembled Air Plenums in ANSI 23 inch Configuration on page 287 Note Procedure Step 1 Install the ANSI 23 inch adapter plates on the horizontal air plenum Step 2 Align the screws to fix the adapter plates to the shelf Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Figure 184 Installing the adapter p...

Page 315: ...he wing head screws from the internal side of the horizontal plenum as shown in the following figure c Tighten the screws to a torque value of 11 5 in lb 1 3 N m Figure 186 Installing the left vertical air plenum Step 6 Install the vertical plenum to the right of the horizontal air plenum Follow step 5a to step 5c Cisco ONS 15454 Hardware Installation Guide 285 Installing the ONS 15454 M6 Shelf DL...

Page 316: ...assis in front position See DLP G562 Mounting the Brackets on the ONS 15454 M6 Shelf for ETSI Rack Configuration on page 304 Step 10 Check the length between the top and bottom horizontal air plenums where the chassis will be installed The length must be not less than 10 5 inches 267 mm If the length is less adjust the position of the top horizontal plenum Step 11 Install the ONS 15454 M6 empty ch...

Page 317: ...enum Tools Equipment As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Install the ANSI 23 inch adapter plates on the horizontal air plenums Step 2 Align the screws to fix the adapter plates to the shelf Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 3 Place a horizontal air plenum as the base Step 4 Install the vertical air ple...

Page 318: ...Figure 190 Pre assembling the air plenums Step 8 Install the ANSI 23 inch adapter plates on the horizontal air plenums Step 9 Install the wing head screws provided with the kit and tighten to a torque value of 11 5 in lb 1 3 N m Cisco ONS 15454 Hardware Installation Guide 288 Installing the ONS 15454 M6 Shelf DLP G768 Install Pre assembled Air Plenums in ANSI 23 inch Configuration ...

Page 319: ...the length is less adjust the position of the top horizontal plenum Step 12 Install the empty ONS 15454 M6 chassis between the horizontal plenums Step 13 Return to your originating procedure NTP DLP G769 Install Air Plenum for ONS 15454 M6 Shelf in ETSI Configuration This task installs the air plenum for the ONS 15454 M6 shelf in the ETSI configuration Purpose Cisco ONS 15454 Hardware Installation...

Page 320: ...rizontal air plenums Step 2 Align the screws to fix the adapter plates to the shelf Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Figure 192 Installing the adapter plates on the horizontal air plenum Step 3 Place the horizontal plenum below the chassis slot in the ETSI cabinet Step 4 Install the wing head screws provided with the kit and tighten to a torque value of 11...

Page 321: ...ead screws from the internal side of the horizontal plenum as shown in the following figure c Tighten the screws to a torque value of 11 5 in lb 1 3 N m Figure 194 Installing the left vertical air plenum Step 6 Install the vertical air plenum to the right of the horizontal air plenum Follow step 5a to step 5c Cisco ONS 15454 Hardware Installation Guide 291 Installing the ONS 15454 M6 Shelf DLP G76...

Page 322: ...brackets on both sides of the chassis in front position See DLP G562 Mounting the Brackets on the ONS 15454 M6 Shelf for ETSI Rack Configuration on page 304 Step 10 Check the length between the top and bottom horizontal air plenums where the chassis will be installed The length must be not less than 10 5 inches 267 mm If the length is less adjust the position of the top horizontal plenum Cisco ONS...

Page 323: ...Card Slot 7 Flow CFM Deflector Configuration Case 13500 RPM 40 C and 55 C 9600 RPM 27 C 13500 RPM 40 C and 55 C 9600 RPM 27 C 21 14 9 22 4 16 No deflectors Side to Side 10 6 9 11 2 8 2 Inlet and Outlet ETSI Front to Rear 18 4 12 7 16 8 12 2 Only Inlet ETSI Front to Side 14 7 10 6 18 7 13 4 Inlet and Outlet ANSI Front to Rear 19 7 14 1 20 7 14 8 Only Inlet ANSI Front to Side BulkChassisFlow CFM Def...

Page 324: ...Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Stability hazard The rack stabilizing mechanism must be in place or the rack must be bolted to the floor before you slide the unit out for servicing Failure to stabilize the rack can cause the rack to...

Page 325: ...en mounting this unit in a partially filled rack load the rack from the bottom to the top with the heaviest component at the bottom of the rack If the rack is provided with stabilizing devices install the stabilizers before mounting or servicing the unit in the rack Statement 1006 To prevent airflow restriction allow clearance around the ventilation openings to be at least 1 inch 25 4 mm Statement...

Page 326: ...task as applicable DLP G674 Verify the ONS 15454 M6 Shelf for AC Power Module Installation on page 297 DLP G675 Verify the ONS 15454 M6 Shelf for DC Power Module Installation on page 298 Step 2 Complete the necessary task as applicable DLP G560 Mounting the Reversible Brackets on the ONS 15454 M6 Shelf for ANSI Rack Configuration on page 299 Cisco ONS 15454 Hardware Installation Guide 296 Installi...

Page 327: ...eople on page 317 DLP G568 Mount Multiple ONS 15454 M6 Shelves on a Rack on page 318 Step 4 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Step 5 Continue with NTP G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 Stop You have comple...

Page 328: ...urpose None Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Verify the position of the mechanical locking system on the rear side of the chassis To use the DC power module the screw must be close to the DC silk screen text see the ...

Page 329: ...ck configuration Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M6 to prevent looseni...

Page 330: ...ration on page 301 The narrow side of the mounting bracket should be towards the front of the shelf For a 23 inch 584 2 mm configuration place the narrow side of the mounting bracket flush against the shelf see Figure 202 Mounting the Brackets on the ONS 15454 M6 shelf for a 23 inch 584 2 mm ANSI Configuration on page 301 The widest side of the mounting bracket should be towards the front of the s...

Page 331: ...ting the brackets for a 23 inch 584 2 mm configuration Figure 202 Mounting the Brackets on the ONS 15454 M6 shelf for a 23 inch 584 2 mm ANSI Configuration Cisco ONS 15454 Hardware Installation Guide 301 Installing the ONS 15454 M6 Shelf DLP G560 Mounting the Reversible Brackets on the ONS 15454 M6 Shelf for ANSI Rack Configuration ...

Page 332: ...tor flush against the right side of the chassis see Diagram 1 of Figure 203 Mounting the Air Deflectors Front to Back on the ONS 15454 M6 Shelf for the ANSI rack Configuration on page 303 Step 2 Align the screw holes on the right front air deflector with the screw holes on the right side of the chassis Step 3 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 4 Place t...

Page 333: ...the 23 inch mounting bracket flush in the front position see Diagram 1 of Figure 204 Mounting the Brackets with Air Deflectors Front to Back on the ONS 15454 M6 Shelf for ANSI Rack Configuration on page 304 or in the middle position see Diagram 3 of Figure 204 Mounting the Brackets with Air Deflectors Front to Back on the ONS 15454 M6 Shelf for ANSI Rack Configuration on page 304 against the left ...

Page 334: ...In an ETSI rack the mounting brackets are installed only in the front position Note Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Cisco ONS 1545...

Page 335: ...ocedure Step 1 Place the mounting bracket flush against the shelf as shown in the following figure Step 2 Align the mounting bracket screw holes against the shelf screw holes Step 3 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 4 Repeat steps 1 through 3 for the mounting bracket on the opposite side Figure 205 Mounting the Brackets on the ONS 15454 M6 Shelf for ET...

Page 336: ...and electromechanical corrosion of the hardware and joined material Caution Procedure Step 1 Place the right front air deflector flush against the right side of the chassis see the following figure Step 2 Align the screw holes on the right front air deflector with the screw holes on the right side of the chassis Figure 206 Mounting the Air Deflectors Front to Front on the ONS 15454 M6 Shelf for ET...

Page 337: ... Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M6 to prevent loosening deterioration and electromechanical corrosion of the hardware and joined material Caution Procedure Step 1 Place the right front air deflector flush against the right side of the chassis see Diagram 1 of Figure 207 Mounti...

Page 338: ... screw holes on the mounting bracket with the screw holes on the left side of the chassis Step 9 Insert the screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 10 Place the mounting bracket flush in the middle position see Diagram 1 of Figure 208 Mounting the Bracket with Air Deflectors Front to Back on the ONS 15454 M6 Shelf for ETSI Rack Configuration on page 309 or the front po...

Page 339: ...n the ONS 15454 M6 shelf for ETSI rack configuration Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Tools Equipment NTP G305 Unpack and Inspect the ONS 15454 ONS 15454 M2 and ONS 15454 M6 Shelves on page 20 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Cisco ONS 15454 Hardware Installation Guide 3...

Page 340: ...ector flush against the right side of the chassis see Diagram 1 of Figure 209 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M6 Shelf for ETSI Rack Configuration Front Position on page 311 Step 4 Align the screw holes on the right front air deflector with the screw holes on right side of the chassis Step 5 Insert the screws and tighten them to a torque value of 11 5 in lb 1...

Page 341: ...gn the screw holes on the right front air deflector with the screw holes on the right side of the chassis Step 14 Insert M4 pan head screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 15 Place the mounting bracket flush in the middle position on the right front air deflector see Diagram 2 of Figure 210 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M6 Shel...

Page 342: ...Configuration Middle Position on page 312 Step 22 Align the screw holes on the mounting bracket with the screw holes on the left top air deflector Step 23 Insert M4 flat head screws and tighten them to a torque value of 11 5 in lb 1 3 N m Figure 210 Mounting the Bracket with Air Deflectors Front to Top on the ONS 15454 M6 Shelf for ETSI Rack Configuration Middle Position Step 24 Return to your ori...

Page 343: ...te Remote None Security Level Use only the fastening hardware provided with the ONS 15454 M6 to prevent loosening deterioration and electromechanical corrosion of the hardware and joined material Caution It is recommended to maintain a space of one RU between two chassis in a rack for cable management Note Hot and cold aisle airflow management must be planned for the installation Note Procedure St...

Page 344: ...the mounting bracket with the screw holes on the right front air deflector Step 6 Insert M4 flat head screws and tighten them to a torque value of 11 5 in lb 1 3 N m Step 7 Place the mounting bracket flush in the middle or front position on the left side of the chassis see Diagram 2 of Figure 212 Mounting the Bracket with Air Deflectors Front to Side on the ONS 15454 M6 Shelf for ETSI Rack Configu...

Page 345: ...ion Front Position Step 10 Return to your originating procedure NTP DLP G566 Mount the ONS 15454 M6 Shelf on a Rack One Person This task allows one person to mount the shelf on a rack When the chassis is installed in the middle position in an ETSI rack the cabinet doors must be kept open if present Note Purpose Cisco ONS 15454 Hardware Installation Guide 315 Installing the ONS 15454 M6 Shelf DLP G...

Page 346: ...upply the fuse rating must not exceed 10A 15A or 20A For North America the branch circuit protection must be rated 20A The overcurrent short circuit protection must be in accordance with local and national electrical codes Step 2 Ensure that the shelf is mounted on the appropriate rack equipment 23 inches 584 2 mm or 19 inches 482 6 mm for ANSI racks The recommended 19 inch ANSI rack for the ONS 1...

Page 347: ...bly Tighten the screw to a torque value of 22 in lb 2 5 N m Step 6 When the shelf is secured to the rack install the remaining two mounting screws on either sides Use at least one set of the horizontal screw slots on the shelf to prevent slippage Note Step 7 Return to your originating procedure NTP DLP G567 Mount the ONS 15454 M6 Shelf on a Rack Two People This task allows two people to mount the ...

Page 348: ...I racks 600 x 600 mm 23 6 x 23 6 inch or 600 x 300 mm 23 6 x 11 8 inch for ETSI racks Step 3 Lift the shelf to the desired position in the rack If the rack is empty place the shelf at the bottom of the rack The placement of the shelf is dependent on where you want to install the new equipment in the rack To ensure proper cooling of the ONS 15454 M6 shelf make sure that the space in front of the ai...

Page 349: ...ocedure Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space If a fuse and alarm panel is not present you must install one according to manufacturer s instructions For a DC power supply the fuse rating must not exceed 40A For AC power supply the fuse rating must not exceed 20A Step 2 Mount the first shelf in the bottom of the rack using the DLP G566 Mount...

Page 350: ...tray fan tray assembly and LCD screen There are two types of front doors that act as protective panels standard door and deep front panel The deep front panel provides additional space in front of the shelf to accommodate cables that do not fit inside the standard door It also provides more space for fiber bend radius and to manage the line card connections The Cisco ONS 15454 Hardware Installatio...

Page 351: ...ape that is present on top of the door Note You must remove the door before proceeding with the shelf installation The ONS 15454 M6 door can be opened by loosening the front screws and pushing the latch in the opposite direction You can remove the front door to provide unrestricted access to the front of the shelf An erasable label is pasted on the inside of the front door You can use the label to...

Page 352: ... M6 The following figure shows the label that is placed on top of ONS 15454 M6 Figure 218 ONS 15454 M6 Label Figure 219 ONS 15454 M6 Front Door Label Cisco ONS 15454 Hardware Installation Guide 322 Installing the ONS 15454 M6 Shelf Front Door ...

Page 353: ...the Power Modules in the ONS 15454 M6 Shelf on page 355 NTP G255 Install the LCD Module in the ONS 15454 M6 Shelf on page 366 NTP G256 Install Power and Ground to the ONS 15454 M6 Shelf on page 370 NTP G257 Install the Fan Tray Assembly in the ONS 15454 M6 Shelf on page 388 NTP G290 Install the Cable and Fiber Modules on page 391 NTP G312 Attach Wires to Alarm Timing LAN and Craft Pin Connections ...

Page 354: ...lace the retention feature on the pin present on the chassis See Diagram 2 of Figure 221 Mounting the Mechanical Stop on page 325 Step 7 Raise the door to slide the pin See Diagram 3 of Figure 221 Mounting the Mechanical Stop on page 325 Step 8 Slide the mechanical stop to lock the door position and tighten the screws See Diagram 4 of Figure 221 Mounting the Mechanical Stop on page 325 Reinstall t...

Page 355: ...Figure 221 Mounting the Mechanical Stop Cisco ONS 15454 Hardware Installation Guide 325 Installing the ONS 15454 M6 Shelf NTP G258 Install the Standard Door of the ONS 15454 M6 Shelf ...

Page 356: ...6 on the door and the chassis and tighten the nuts to a torque value of 11 5 in lb 1 3 N m to lock the cable Step 10 Tighten the door screws to a torque value of 6 5 in lb 0 75 N m to close the standard door as shown in the following figure Cisco ONS 15454 Hardware Installation Guide 326 Installing the ONS 15454 M6 Shelf NTP G258 Install the Standard Door of the ONS 15454 M6 Shelf ...

Page 357: ...n page 294 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Complete the DLP G576 Open the Standard Door of the ONS 15454 M6 Shelf on page 328 Cisco ONS ...

Page 358: ...mote None Security Level The ONS 15454 M6 shelf has an ESD plug input and is shipped with an ESD wrist strap The ESD plug input is located on the outside of the shelf on the left side It is labeled ESD on the top and bottom Always wear an ESD wrist strap and connect the strap to the ESD plug when working on the ONS 15454 M6 For detailed instructions on how to wear the ESD wristband see the Electro...

Page 359: ...open The retention feature maintains the door in the horizontal position for line card insertion see the following figure Cisco ONS 15454 Hardware Installation Guide 329 Installing the ONS 15454 M6 Shelf DLP G576 Open the Standard Door of the ONS 15454 M6 Shelf ...

Page 360: ...576 Open the Standard Door of the ONS 15454 M6 Shelf on page 328 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Unscrew the nut holding the ground cable to the shelf Remove the nut Step 2 Remove the ground cable from the shelf see the following figure Cisco ONS 15454 Hardware Installation Guide 330 Installing the ONS 15454 M6 Shelf DL...

Page 361: ...ve the retention feature from the pin present on the chassis Step 6 Pull the hinge pins holding the door to the chassis in the opposite direction see the following figure Step 7 Remove the door from its hinges see the following figure Cisco ONS 15454 Hardware Installation Guide 331 Installing the ONS 15454 M6 Shelf DLP G577 Remove the Standard Door of the ONS 15454 M6 Shelf ...

Page 362: ... Shelf This procedure installs the deep front panel of the ONS 15454 M6 shelf Purpose 2 Phillips Dynamometric screwdriver Socket 6 32 standard and socket wrench to tighten or loosen the ground nut Tools Equipment Cisco ONS 15454 Hardware Installation Guide 332 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 363: ...larm Timing LAN and Craft Pin Connections in Cisco ONS 15454 M6 on page 397 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Use the deep front panel when ONS SC 10G C pluggables are installed on ONS 15454 M6 shelf Note When the deep front panel is installed the total chassis depth is 12 9 inches The deep front panel extends from the rack by 1 8 inches ...

Page 364: ...el screws and slide them outwards using the plastic tabs Step 3 Place the deep front panel close to the shelf so that the shelf notches and the deep front panel retention features are in line as shown in the following figure Cisco ONS 15454 Hardware Installation Guide 334 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 365: ...on features of the deep front panel with the right and left notches present on the top of the shelf see the following figure b Align the deep front panel pins present at the bottom of the panel with the shelf hinges see the following figure Cisco ONS 15454 Hardware Installation Guide 335 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 366: ...l Pins and Shelf hinges The following figure shows the deep front panel aligned with the shelf Cisco ONS 15454 Hardware Installation Guide 336 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 367: ...s to engage the retention features and the pins with the shelf notches and hinges see the following figure Verify the engagement by gently applying outward pressure to the panel Cisco ONS 15454 Hardware Installation Guide 337 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 368: ...m Step 7 Connect the other end of the ground strap cable to the ground point present on the deep front panel exterior see the following figure Figure 233 Connecting ground strap cable to the ground point Cisco ONS 15454 Hardware Installation Guide 338 Installing the ONS 15454 M6 Shelf NTP G327 Install the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 369: ...for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level The deep front panel does not have a hinge and cannot be rotated like a standard door Rotating the deep front panel can damage the deep front panel shelf hinges other devices and cables placed below the ONS 15454 M6 shelf Caution When the deep front panel is installed ...

Page 370: ...abs to open the deep front panel as shown in the following figure Figure 235 Moving the deep front panel to disengage Step 3 Move the deep front panel away from the shelf see the following figure Cisco ONS 15454 Hardware Installation Guide 340 Installing the ONS 15454 M6 Shelf NTP G329 Remove the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 371: ...ure Figure 237 Removing the ground strap cable a Loosen the ground nut on the shelf b Remove the lug and tighten the nut on the shelf to a torque value of 11 5 in lb 1 3 N m Cisco ONS 15454 Hardware Installation Guide 341 Installing the ONS 15454 M6 Shelf NTP G329 Remove the Deep Front Panel of the ONS 15454 M6 Shelf ...

Page 372: ...l connections of ONS 15454 M6 present on the ECU are 12 remote inventory standard USB connections 2 BITS OUT connections 2 subminiature version B SMB connectors for ETSI and 4 wire wrap pins for ANSI 2 BITS IN connections 2 SMB connectors for ETSI and 4 wire wrap pins for ANSI 6 multishelf connections 1 element management system EMS connection 1 craft terminal connection 2 VoIP or 2 user data chan...

Page 373: ...ls on the left side connector 1 SCSI with 26 poles for digital I O signals on the right side connector The following figure shows the ECU2 connectors Figure 240 Connectors on ECU2 Faceplate The ECU2 should not be used when the shelf is powered at 60 VDC nominal input voltage Note ECU 60V The ECU 60V is used when the shelf is powered at 60 VDC nominal input voltage The external connections of ONS 1...

Page 374: ...S connectors Figure 242 Connectors on the ONS 15454 M6 ECU S Faceplate 1 SCSI with 26 poles for TNC relay contact including ACO signal and digital I O signals 1 USB 2 0 ports Ports A1 A2 A3 A4 and USB 3 0 port Port A5 2 VOIP UDC port RJ 45 port 3 EMS port RJ 45 port 4 Three MSM ports 5 BITS1 input and output ports 6 BITS2 input and output ports 7 Three MSM ports 8 Craft terminal port 9 VOIP UDC po...

Page 375: ...onnections 2 subminiature version B SMB connectors for ETSI and 4 wire wrap pins for ANSI 10 MHz IN and OUT and PPS IN and OUT hardware ready 2 BITS IN connections 2 SMB connectors for ETSI and 4 wire wrap pins for ANSI 6 multishelf connections 1 element management system EMS connection 1 craft terminal connection 1 time of day ToD connection hardware ready 2 VoIP or 2 user data channel UDC connec...

Page 376: ...eases prior to 10 5 2 The external connections present on the NCS 2006 ECU60 S are 2 USB 3 0 connections The USB 3 0 port on the left of the faceplate is detected as A5 The USB 3 0 port on the left of the faceplate is detected as B5 8 USB 2 0 connections 4 USB 2 0 on the left of the faceplate are detected as A1 A2 A3 A4 4 USB 2 0 ports on the right of the faceplate are detected as B1 B2 B3 B4 In r...

Page 377: ...lves cannot be extended through the node controller Note ECU60 S does not support alarm connections Note See Table 36 SCSI Alarm Cable 15454 M ALMCBL and SCSI Alarm Patch Cable 15454 M AEXPCBL Connector Details on page 400 and Table 37 SCSI Alarm Wire Wrap Cable 15454 M ALMCBL2 Connector Details on page 401 for pin details of the alarm connectors Passive Unit Inventory Interfaces The passive unit ...

Page 378: ... to connect the ONS 15454 M6 shelf to other ONS 15454 or ONS 15454 M6 shelves that are a part of the multishelf configuration There are six MSM ports on the ECU modules three ports on the left side and three ports on the right side The MSM ports on the left side correspond to the TNC TNCE TSC TSCE card in Slot 1 and those on the right side correspond to the TNC TNCE TSC TSCE card in Slot 8 Three M...

Page 379: ...dia GR 1089 NEBS standard for electromagnetic compatibility and safety connect the serial high speed WAN interface ports only to intra building or unexposed wiring or cable The intrabuilding cable must be shielded and the shield must be grounded at both ends The intra building port s of the equipment or subassembly must not be metallically connected to interfaces that connect to the OSP or its wir...

Page 380: ...g with a powered ONS 15454 M6 For detailed instructions on how to wear the ESD wristband see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution If the USB device connected to the ECU module is not detected when the ONS 15454 M6 shelf assembly is powered on plug out remove the ECU module and insert it again Note Procedure Step 1 Insert the ECU module in th...

Page 381: ...he ECU module installed in the ONS 15454 M6 shelf Figure 245 ONS 15454 M6 Shelf with ECU module Installed Stop You have completed this procedure Cisco ONS 15454 Hardware Installation Guide 351 Installing the ONS 15454 M6 Shelf NTP G253 Install the ECU or ECU S Module ...

Page 382: ... ONS 15454 M6 shelf as described in the NTP G253 Install the ECU or ECU S Module on page 349 Step 6 Power on the 15454 M6 DC V03 power module as described in the NTP G256 Install Power and Ground to the ONS 15454 M6 Shelf on page 370 Stop You have completed this procedure Power Modules The ONS 15454 M6 system contains pluggable and redundant power modules for AC and DC power The AC and DC power mo...

Page 383: ... of a card causes the power consumption to exceed the limit of 1200W The 15454 M6 AC2 has a maximum capacity of1500 W for 230 Vin and 1200 W for 110 Vin Changing the AC Power Module It is possible to change the power modules of the ONS 15454 M6 system from 15454 M6 AC to 15454 M6 AC2 and vice versa without powering down the ONS 15454 M6 system While changing the power modules ensure that only one ...

Page 384: ...ceed 1920 W The PWR CON LMT alarm is raised in the Alarms tab in CTC when the installation or pre provisioning of a card causes the power consumption to exceed the limit of 1920 W The total power consumption of the shelf is calculated by the controller card and displayed in CTC in the Provisioning Power Monitor tab For details about power calculation see Power Calculation on page 478 Note The term...

Page 385: ... 1 Complete the necessary task as applicable DLP G569 Install the AC Power Module in the ONS 15454 M6 Shelf on page 355 DLP G757 Replacing 15454 M6 AC With 15454 M6 AC2 Power module on page 358 DLP G758 Replacing 15454 M6 AC2 With 15454 M6 AC Power module on page 359 DLP G570 Install the DC Power Module in the ONS 15454 M6 Shelf on page 360 DLP G737 Replacing 15454 M6 DC With 15454 M6 DC20 Power M...

Page 386: ... None Security Level The node can temporarily work with both 15454 M6 AC and 15454 M6 AC2 power module units installed on the ONS 15454 M6 shelf However during regular operation the shelf must have either the 15454 M6 AC or 15454 M6 AC2 power module but not both Caution Insert the AC power module in Slot A or Slot B or both see the following figure Tip While inserting the AC power module apply ins...

Page 387: ...wer modul5es can be installed in Slot A and Slot B However only one power module can sustain the functioning of the entire ONS 15454 M6 system In that case insert a power filler module in the empty slot for example see Figure 250 Installing a Power Filler Module on page 363 Note For information on the power module air filter see NTP G114 Inspect and Replace the Air Filter on page 435 Note Cisco ON...

Page 388: ...helf on page 327 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Refer to Power Calculation on page 478 to ascertain the power consumption of the shelf Note Always use the supplied ESD wristband when working with a powered ONS 15454 M6 For detailed instructions on how to wear the ESD wristband see the Electrostatic Discharge and Grounding Guide for Cisc...

Page 389: ...Perform Steps 1 to 5 for the other power module installed in slot A To ensure that the controller card calculates the shelf power consumption correctly reset the controller card For details about performing card reset see the NTP G106 Resetting Cards Using CTC procedure in the Cisco ONS 15454 DWDM Network Configuration Guide Note Return to your originating procedure NTP DLP G758 Replacing 15454 M6...

Page 390: ...the mixed power mode with both 15454 M6 AC and 15454 M6 AC2 power modules installed Card provisioning and installation must be done only after both the slots have the same type of power modules Note Step 6 Perform steps 1 to 5 for the other power module installed in slot A Step 7 Return to your originating procedure NTP DLP G570 Install the DC Power Module in the ONS 15454 M6 Shelf This procedure ...

Page 391: ...e but not both Caution Procedure Step 1 Insert the DC power module in Slot A or Slot B or both see the following figure Figure 248 Installing the DC Power Modules Step 2 Plug the DC power module completely into the chassis Step 3 Tighten the screw to a torque value of 4 in lb 0 45 N m to lock the power module in the chassis see the following figure Cisco ONS 15454 Hardware Installation Guide 361 I...

Page 392: ...the functioning of the entire ONS 15454 M6 system In that case insert a power filler module in the empty slot see the following figure Note The following figure shows a DC power module installed in Slot A and a power filler module installed in Slot B Cisco ONS 15454 Hardware Installation Guide 362 Installing the ONS 15454 M6 Shelf DLP G570 Install the DC Power Module in the ONS 15454 M6 Shelf ...

Page 393: ...4 M6 DC With 15454 M6 DC20 Power Module This procedure replaces the 15454 M6 DC with 15454 M6 DC20 power module Purpose 2 Phillips Dynamometric screwdriver Tools Equipment NTP G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Cisco ONS 15454 Hardware Installation Guide 363 Instal...

Page 394: ...the ONS 15454 M6 chassis Step 4 Remove the power connections from the standby power module Step 5 Install power on the 15454 M6 DC power module as described in the NTP G256 Install Power and Ground to the ONS 15454 M6 Shelf on page 370 While replacing the power modules do not provision or install any line cards when the ONS 15454 M6 chassis is in the mixed power mode Card provisioning and installa...

Page 395: ...on the shelf must either have the 15454 M6 DC or 15454 M6 DC20 power module but not both Caution Always use the supplied ESD wristband when working with a powered ONS 15454 M6 For detailed instructions on how to wear the ESD wristband see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution Procedure Step 1 Disconnect the power source and remove the power c...

Page 396: ...ther a critical major or minor alarm is present anywhere on the ONS 15454 M6 shelf The shelf controller card controls the conditions that result in triggering the LEDs The LEDs can be overwritten by the shelf controller card TNC TNCE TSC or TSCE in all the three states OFF red green The LCD unit supports the lamp test procedure and the LEDs changes its color or state If the LCD unit is removed fro...

Page 397: ...rocedure Step 1 Insert the LCD module in the central slot between the power slots of the chassis see the following figure Figure 251 Installing the LCD Module Step 2 Push the LCD module into the chassis such that the backplane connector is completely engaged see the above figure Step 3 Tighten the screw to a torque value of 4 in lb 0 45 N m to lock the unit see the following figure Cisco ONS 15454...

Page 398: ...S Platforms Note ANSI Power and Ground The ONS 15454 M6 has redundant AC and DC power modules For redundant AC power feeds install both the AC power modules and use the two power cables right and left cables shipped with the ONS 15454 M6 and one ground cable For an AC power supply the fuse rating must not exceed 10A 15A or 20A For North America the branch circuit protection must be rated 20A The o...

Page 399: ...treated as DC I as defined in Telcordia GR 1089 CORE Issue 3 The ground lug must be a dual hole type UL Listed CSA certified and rated to accept the 6 AWG cable Two ground posts with two M5 nuts are provided on the ONS 15454 M6 to accommodate the dual hole lug Only use the power cables shipped with the ONS 15454 M6 shelf Note ETSI Power and Ground The ONS 15454 M6 for ETSI has 48 VDC or 60 VDC pow...

Page 400: ...the ONS 15454 M6 Tools Equipment NTP G524 Install the Power Modules in the ONS 15454 M6 Shelf on page 355 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level To ensure safet...

Page 401: ...with upturned lugs These terminations should be the appropriate size for the wires and should clamp both the insulation and conductor Statement 1002 Warning Before performing any of the following procedures ensure that power is removed from the DC circuit Statement 1003 Warning Before working on a chassis or working near power supplies unplug the power cord on AC units Statement 246 Warning This e...

Page 402: ...or detailed instructions on how to wear the ESD wristband see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Caution Procedure Step 1 Verify that the correct fuse and alarm panel is installed in the top mounting space For a a DC power supply the fuse rating must not exceed 40A For an AC power supply the fuse rating must not exceed 10A 15A or 20A For North Ame...

Page 403: ...tranded The PIDs of the power cables are listed in Table 33 PIDs for AC Power Cables on page 376 Tools Equipment NTP G252 Install the ONS 15454 M6 Shelf on page 294 NTP G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Ci...

Page 404: ...ring lug connectors screwless push in connectors quick connect connectors or other friction fit connectors Caution If the system loses power or if both the TNC TNCE TSC or TSCE cards are reset you must reset the ONS 15454 M6 clock After powering down the date defaults to January 1 1970 00 04 15 To reset the clock see the NTP G24 Setting Up Node Identification Information procedure in the Cisco ONS...

Page 405: ...54 Cable Clip to Secure the Power Cable For Slot A power module the power cable exits from the left side For Slot B power module the power cable exits from the right side see the following figure Note Cisco ONS 15454 Hardware Installation Guide 375 Installing the ONS 15454 M6 Shelf DLP G571 Connect Office Power AC to the ONS 15454 M6 Shelf ...

Page 406: ...er Cables PID Cable 15454 M CBL L JPN AC power cable Japan left exit 15454 M CBL R JPN AC power cable Japan right exit 15454 M CBL L CHI AC power cable China left exit 15454 M CBL R CHI AC power cable China right exit 15454 M CBL L IND AC power cable India left exit 15454 M CBL R IND AC power cable India right exit 15454 M CBL L EU AC power cable EU left exit 15454 M CBL R EU AC power cable EU rig...

Page 407: ...M ACL6 L AC power cable for data center left exit 15454 M ACL6 R AC power cable for data center right exit DLP G572 Connect Office Power DC to the ONS 15454 M6 Shelf ANSI Only This task connects DC power to the ONS 15454 M6 ANSI Only Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdriver Wire wrapper Wire cutters Wire strippers Crimp tool Open end wren...

Page 408: ...ct against short circuit overcurrent and ground faults Ensure that the protective devices are properly rated and comply with national and local codes Caution The battery return connection is treated as DC I as defined in Telcordia GR 1089 CORE Issue 5 Note If the system loses power or both the TNC TNCE TSC or TSCE cards are reset and the system is not provisioned to get the time from a Network Tim...

Page 409: ... lugs onto the ends of all the power leads Step 7 Verify that the DC power module is installed in Slot A or Slot B or both of the ONS 15454 M6 shelf Step 8 Remove the terminal block protective covers from the DC power modules see the following figure Figure 256 Connecting Office Power DC Power Modules ANSI Only Step 9 Unscrew the nuts from the terminal block see the following figure Cisco ONS 1545...

Page 410: ...he terminal block protective covers on the DC power modules see the following figure For Slot A power module the power cable exits from the left side For Slot B power module the power cable exits from the right side Note Use only pressure terminal connectors such as ring and fork types when terminating the battery battery return and frame ground conductors Note Cisco ONS 15454 Hardware Installatio...

Page 411: ...frame ground do not use soldering lug screwless push in connectors quick connect or other friction fit connectors Caution Step 13 Return to your originating procedure NTP DLP G573 Connect Office Power DC to the ONS 15454 M6 Shelf ETSI Only This task connects power to the ONS 15454 M6 shelf ETSI Only Purpose 2 Phillips Dynamometric screwdriver Medium slot head screwdriver Small slot head screwdrive...

Page 412: ...ssue 5 Note The ONS 15454 M6 relies on the protective devices in the building installation to protect against short circuit overcurrent and ground faults Ensure that the protective devices are properly rated and comply with national and local codes Caution If the system loses power or both TNC TNCE TSC or TSCE cards are reset and the system is not provisioned to get the time from a Network Time Pr...

Page 413: ... see the following figure Figure 259 Connecting Office Power DC Power Modules ETSI Only Step 4 Attach the DC ETSI power cable to the cable connector in the DC power module see the following figure Step 5 Tighten the screws to a torque value of 4 in lb 0 45 N m to secure the cable see the following figure Cisco ONS 15454 Hardware Installation Guide 383 Installing the ONS 15454 M6 Shelf DLP G573 Con...

Page 414: ...ound with an appropriate antioxidant compound Bring all unplated connectors braided strap and bus bars to a bright finish then coat with an antioxidant before you connect them You do not need to prepare tinned solder plated or silver plated connectors and other plated connection surfaces but always keep them clean and free of contaminants Caution When terminating power return and frame ground do n...

Page 415: ... Security Level Do not apply power to the shelf until you complete all the installation steps Caution To ensure safety of personnel and equipment do not connect any power cables into the power module until the module is completely installed into the chassis Statement 389 Warning To reduce the risk of electric shock switch on the power only after the power cord is completely installed into the powe...

Page 416: ... Onsite Remote None Security Level Do not apply power to the shelf until you complete all the installation steps Caution To ensure safety of personnel and equipment do not connect any power cables into the power module until the module is completely installed into the chassis Statement 389 Warning To reduce the risk of electric shock switch on the power only after the power cord is completely inst...

Page 417: ...d 72 0 VDC Then place the red test lead of the voltmeter to the RET2 B side return ground black cable and verify that no voltage is present To view the shelf voltage and temperature see the NTP G230 View Shelf Voltage and Temperature on page 76 Note If the ONS 15454 M6 shelf is being powered at 60 VDC nominal voltage the door must be kept closed during regular operation Note Step 4 Return to your ...

Page 418: ...ay assembly in the ONS 15454 M6 system Purpose Small slot head screwdriver Tools Equipment NTP G252 Install the ONS 15454 M6 Shelf on page 294 NTP G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 Connect the chassis to the office ground For detailed instructions on how to ground the chassis see the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS ...

Page 419: ...t the fan tray assembly inside the left slot fan tray slot of the ONS 15454 M6 chassis see the following figure Figure 261 Installing the Fan Tray Assembly Step 2 Push the fan tray assembly such that the backplane connector is engaged completely Step 3 Tighten the screws to a torque value of 4 in lb 0 45 N m to lock the fan tray assembly into the chassis see the following figure Cisco ONS 15454 Ha...

Page 420: ...is 1 5 inches The fiber guide can be replaced with a cable guide to route the CAT 5 Ethernet cables The maximum number of 2 mm diameter patch cords that can be managed is 144 or alternatively 72 CAT5 cables To manage extra length fiber and fan out a dedicated fiber storage unit and patch panel unit can be installed inside the rack The maximum capacity of the fiber channel for one side of the shelf...

Page 421: ...enuator outside the shelf from any port of a card Note Cable and Fiber Routing Cable and fiber routing accommodates all the high density cards for line card connections in ONS 15454 M6 The exit of the fibers and cables is split into two channels The line card from slot 1 to 4 exits from the lower right side and the line card from 5 to 8 exit from the upper right side See the following figure Figur...

Page 422: ...Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Loosen the screws on the fiber module present on the right side of the ONS 15454 M6 assembly See the following figure Step 2 Loosen the screw present on the air filter locking feature of the ONS 15454 M6 shelf Step 3 Remove the air filter locking feature by holding the air ...

Page 423: ...Needed Onsite Onsite Remote None Security Level Procedure Step 1 Insert the air filter locking feature on the cable module See the following figure Step 2 Attach the slot label identity on the cable module with screws Step 3 Mount the cable module on the chassis and tighten the screws to a torque value of 4 in lb 0 45 N m to attach the cable module to the ONS 15454 M6 shelf Cisco ONS 15454 Hardwar...

Page 424: ...n extra length of ECU cable is available to allow cable management during extraction of the power module See Diagram 1 of Figure 269 Sequence to Remove the Power Module on page 397 It is also possible to manage the extraction of the power module without adding the extra length of ECU cable by reducing the number of cables in the right exit area see Diagram 1 of Figure 267 Cable Management on page ...

Page 425: ...ories kit Step 3 To route the optical patch cords or copper cables do the following as necessary a Route the optical patch cords from the line cards through the fiber or cable module as shown in the following figure Cisco ONS 15454 Hardware Installation Guide 395 Installing the ONS 15454 M6 Shelf DLP G655 Route and Lock Cables ...

Page 426: ...is See Diagram 2 of Figure 269 Sequence to Remove the Power Module on page 397 b Move the ECU cables away from the chassis Ensure that the alarm cable with the plastic bend radius controller is not moved See Diagram 3 of Figure 269 Sequence to Remove the Power Module on page 397 c Remove the power module See Diagram 4 of Figure 269 Sequence to Remove the Power Module on page 397 Cisco ONS 15454 Ha...

Page 427: ...or 0 64 mm shielded wires for LAN or craft 75 ohm coaxial cable with DIN 1 0 2 3 miniature coaxial connector Alarm 26 pins SCSI cable The PIDs of the SCSI cables are listed in Table 35 PIDs for SCSI Cables on page 398 Tools Equipment NTP G253 Install the ECU or ECU S Module on page 349 Prerequisite Procedures As needed Required As Needed Cisco ONS 15454 Hardware Installation Guide 397 Installing t...

Page 428: ...is procedure Table 35 PIDs for SCSI Cables WireDimension Length PID Cable 28 AWG 20 Meter 15454 M ALMCBL SCSI alarm cable 28 AWG 1 Meter 15454 M AEXPCBL SCSI alarm patch cable 24 AWG 20 Meter 15454 M ALMCBL2 SCSI alarm wire wrap cable Some wire wrap tools require a minimum of 24 AWG wires to prevent breakage Ensure that the SCSI alarm wire wrap cable is used for 24 AWG wires When the SCSI alarm wi...

Page 429: ...perator assigns to a definite wire color and name through the Craft Terminal Note Step 2 Tighten the screws of the SCSI connector to a torque value of 4 in lb 0 45 N m using 2 Philips Dynamometric screwdriver See Diagram 2 of Figure 270 Installing the ECU Alarm Cable Left Exit Option on page 400 or Figure 271 Installing the ECU Alarm Cable Right Exit Option on page 400 Step 3 Bend the cable at an ...

Page 430: ...SCSI Alarm Patch Cable 15454 M AEXPCBL Connector Details Input Output Alarms Left Connector Input Alarms Right Alarm Connector Color Code PinNumber Minor Audible Alarm Input Pair 1 Black Brown 1 Major Audible Alarm Input Pair 2 Black Red 2 Cisco ONS 15454 Hardware Installation Guide 400 Installing the ONS 15454 M6 Shelf DLP G295 Install Alarm Wires in ONS 15454 M6 ...

Page 431: ...ut Pair 2 Red Black 15 Critical Audible Alarm Input Pair 3 Orange Black 16 Remote Audible Alarm Input Pair 4 Yellow Black 17 Minor Visual Alarm Input Pair 5 Green Black 18 Major Visual Alarm Input Pair 6 Blue Black 19 Critical Visual Alarm Input Pair 7 Blue White 20 Remote Visual Alarm Input Pair 8 Orange White 21 Input Pair 9 Green White 22 Alarm Cutoff ACO Input Pair 10 Brown White 23 24 Output ...

Page 432: ...een 9 Alarm Cutoff ACO Input Pair 10 White Brown 10 11 12 13 Minor Audible Alarm Input Pair 1 Brown Black 14 Major Audible Alarm Input Pair 2 Red Black 15 16 Remote Audible Alarm Input Pair 4 Yellow Black 17 Minor Visual Alarm Input Pair 5 Green Black 18 Major Visual Alarm Input Pair 6 Blue Black 19 20 Remote Visual Alarm Input Pair 8 Orange White 21 Input Pair 9 Green White 22 Alarm Cutoff ACO In...

Page 433: ...gnments for ANSI Figure 272 ECU module ANSI Wire wrap Pins Table 38 ECU module Pin Assignments ANSI Function Pin Input from external drive IN 1 Output to external drive OUT1 Input from external drive IN 2 Output to external drive OUT2 Step 2 Connect one end of the wire wrap clock cable to the corresponding wire wrap connector on the ECU module and the other end to the external source of the timing...

Page 434: ...se 75 ohm coaxial cable with a DIN 1 0 2 3 miniature coaxial connector The PID for the BITS IN OUT cable is 15454 M TMGCBL Tools Equipment NTP G253 Install the ECU or ECU S Module on page 349 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Connect the clock cable to the corresponding ECU module connector using a coaxial cable with DIN ...

Page 435: ...xternal drive IN 1 Output to external drive OUT1 Input from external drive IN 2 Output to external drive OUT2 Figure 274 ECU module ETSI BITS connectors Figure 275 ECU module ETSI BITS Connectors Cabling Step 2 Gently push the cable connector into the ECU module connector until you hear a click Perform the following steps to mate the connectors Cisco ONS 15454 Hardware Installation Guide 405 Insta...

Page 436: ... used for timing input and output The top connectors are for A BITS 1 timing and the bottom connectors are for B BITS 2 timing In each case the left connector is the input and the right connector is the output The input connectors for timing provide a 75 ohm termination Note Step 3 Connect the other end of the cable to the external source of the timing signal according to Table 39 ECU module Pin A...

Page 437: ...r TSCE card switch over If the ECU module is absent you can connect a CAT 5 Ethernet cable to the LAN port on the TNC TNCE TSC TSCE card to create an external LAN connection You can use the same procedure to connect Multishelf Management ports of several chassis in MSM configurations Note To avoid duplex mismatch between EMS or craft terminal port and external LAN switch port auto negotiation must...

Page 438: ...onnector into the MSM port that corresponds to the TNC TNCE TSC TSCE card in Slot 8 of the ONS 15454 M6 shelf used as the node controller b Plug the other connector into the MSM port that corresponds to the TNC TNCE TSC TSCE card in Slot 8 of the ONS 15454 M6 shelf used as subtending shelf Step 3 Repeat Step 1 and Step 2 to connect the remaining two MSM ports of the ONS 15454 M6 shelf used as the ...

Page 439: ...C TNCE TSC TSCE card in Slot 8 For more information about the ECU module and MSM ports see the External Connection Units on page 342 Note Procedure Step 1 Complete the necessary task as applicable To connect the ONS 15454 M6 as the node controller and ONS 15454 or ONS 15454 M6 as subtending shelves with Catalyst 3560 complete the DLP G682 Connect the ONS 15454 M6 as the Node Controller in a Mixed ...

Page 440: ...e the Cisco Catalyst 3560 product documentation for installation instructions Cross over CAT 5 LAN cables 3 plus 2 for each subtending shelf Tools Equipment NTP G15 Install the Common Control Cards on page 131 NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card on page 261 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level The MSM multishelf mana...

Page 441: ...ot 8 Plug the other end into Port 2 of the standby Catalyst 3560 c Repeat Step 4a and Step 4b for each subtending shelf in the multishelf configuration using Port 3 to Port 20 on the Catalyst 3560 switches Step 5 To connect an ONS 15454 subtending shelf to the Catalyst 3560 switches complete the following a Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtendin...

Page 442: ...with the ONS 15454 M6 as the Node Controller Cisco ONS 15454 Hardware Installation Guide 412 Installing the ONS 15454 M6 Shelf DLP G682 Connect the ONS 15454 M6 as the Node Controller in a Mixed Multishelf Configuration Using the Catalyst 3560 ...

Page 443: ... 3 plus 2 for each subtending shelf Tools Equipment NTP G15 Install the Common Control Cards on page 131 NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card on page 261 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level The MSM multishelf management ports are present on the ECU module The MSM ports located on the left side of the ECU module corre...

Page 444: ...nnector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 Plug the other end into the MSM port of the node controller ONS 15454 M6 shelf that corresponds to the TNC TNCE TSC TSCE card in Slot 8 c Repeat Step 2a and 2b for each subtending shelf in the multishelf configuration using the remaining MSM ports on the node controller ONS 15454 M6 shelf Step 3 To connect an ONS ...

Page 445: ...s using the Catalyst 3560 Purpose Two Cisco Catalyst 3560 switches must be installed in same rack as the node controller shelf refer to the Cisco Catalyst 3560 product documentation for installation instructions Cross over CAT 5 LAN cables Tools Equipment NTP G15 Install the Common Control Cards on page 131 NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card on page 261 Prerequisite Proce...

Page 446: ...into the front panel of the node controller TCC2 TCC2P TCC3 card in Slot 7 Step 2 Using a cross over CAT 5 LAN cable a Plug one connector into Port 1 of the standby Catalyst 3560 b Plug the other connector into the front panel of the node controller TCC2 TCC2P TCC3 card in Slot 11 Step 3 Using a cross over CAT 5 LAN cable a Plug one connector into Port 23 of the active Catalyst 3560 b Plug the oth...

Page 447: ...b Using a cross over CAT 5 LAN cable Plug one connector into the front panel of the subtending shelf TCC2 TCC2P TCC3 card in Slot 11 Plug the other connector into Port 2 of the standby Catalyst 3560 c Repeat Step 5a and 5b for each subtending shelf in the multishelf configuration using Port 3 to Port 20 on the Catalyst 3560 switches Step 6 To daisy chain up to six Catalyst 3560 switches use a cros...

Page 448: ...ONS 15454 as the Node Controller Step 7 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 418 Installing the ONS 15454 M6 Shelf DLP G683 Connect the ONS 15454 as the Node Controller in a Mixed Multishelf Configuration ...

Page 449: ...t side correspond to the TNC TNCE TSC TSCE card in Slot 8 For more information about the ECU module and MSM ports see the External Connection Units on page 342 Note Procedure Step 1 Complete the necessary task as applicable To upgrade the existing ONS 15454 multishelf configuration that has the Cisco Catalyst 2950 switches complete the DLP G687 Upgrade the ONS 15454 Multishelf with the Catalyst 29...

Page 450: ...roller while connecting it to the ONS 15454 M6 subtending shelves and when there are more than 12 subtending shelves Note Procedure Step 1 Disconnect the subtending shelf at Port 21 of the active and standby Catalyst 2950 a Remove the cross over CAT 5 LAN cable from Port 21 of the active Catalyst 2950 b Remove the cross over CAT 5 LAN cable from Port 21 of the standby Catalyst 2950 Step 2 Connect ...

Page 451: ...6 subtending shelf to the Catalyst 3560 switches complete the following a Using a cross over CAT 5 LAN cable Plug one connector into the MSM port of the subtending ONS 15454 M6 shelf that corresponds to the TNC TNCE TSC TSCE card in Slot 1 Plug the other connector into Port 3 of the active Catalyst 3560 b Using a cross over CAT 5 LAN cable Plug one connector into the MSM port of the subtending ONS...

Page 452: ...ands complete the NTP G298 Configure a Cisco Catalyst 2950 or Catalyst 3560 Active and Standby for a ONS 15454 Multishelf Node on page 152 Step 7 Return to your originating procedure NTP Cisco ONS 15454 Hardware Installation Guide 422 Installing the ONS 15454 M6 Shelf DLP G687 Upgrade the ONS 15454 Multishelf with the Catalyst 2950 Switch Configuration ...

Page 453: ...subtending shelves and when there are more than 12 subtending shelves Note The CTC in ONS 15454 M6 shelf view displays the three ports of the MS ISC card and EMS and circuit ports present on the ECU Note Procedure Step 1 Disconnect the ONS 15454 subtending shelf from the EAPs a Remove the cross over CAT 5 LAN cable connecting the ONS 15454 subtending shelf from the SSC8 port of the right EAP b Rem...

Page 454: ...6 subtending shelf to the Catalyst 3560 switches complete the following a Using a cross over CAT 5 LAN cable Plug one connector into the MSM port of the subtending ONS 15454 M6 shelf that corresponds to the TNC TNCE TSC TSCE card in Slot 1 Plug the other connector into Port 3 of the active Catalyst 3560 b Using a cross over CAT 5 LAN cable Plug one connector into the MSM port of the subtending ONS...

Page 455: ...ive and Standby for a ONS 15454 Multishelf Node on page 152 Step 7 Return to your originating procedure NTP NTP G264 Perform the ONS 15454 M6 Shelf Installation Acceptance Test Use this procedure to perform a shelf installation acceptance test for the ONS 15454 M6 Purpose Cisco ONS 15454 Hardware Installation Guide 425 Installing the ONS 15454 M6 Shelf NTP G264 Perform the ONS 15454 M6 Shelf Insta...

Page 456: ...3 Install the ECU or ECU S Module on page 349 NTP G524 Install the Power Modules in the ONS 15454 M6 Shelf on page 355 NTP G255 Install the LCD Module in the ONS 15454 M6 Shelf on page 366 NTP G256 Install Power and Ground to the ONS 15454 M6 Shelf on page 370 NTP G257 Install the Fan Tray Assembly in the ONS 15454 M6 Shelf on page 388 NTP G313 Install and Configure the TNC TNCE TSC or TSCE Card o...

Page 457: ...installed and connected properly Purpose None Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Make sure all external wiring connections on the ECU module that is power ground alarms and so on are secure If a wire or cable is loose return to the appropriate procedure in this chapter to correct it Step 2 Return to you...

Page 458: ...lace the black lead positive on the RET1 and the red lead on the 48 V point Verify a reading between 40 5 VDC and 57 6 VDC If there is no voltage check the following and correct if necessary Battery and ground are reversed to the shelf Battery is open or missing Return is open or missing Step 3 Repeat Step 1 and Step 2 for the RET2 and 48 V of the redundant power supply input Step 4 Return to your...

Page 459: ...nds to the TNC TNCE TSC TSCE card in Slot 1 of the ONS 15454 M6 shelf used as subtending shelf When connecting two shelves using the cross over cables it is possible to have shelves not having controller cards in same slots Use corresponding MSM ports according to the controller card slots Note Step 2 Repeat Step 1 to connect the remaining two MSM ports of the ONS 15454 M6 shelf used as the node c...

Page 460: ...rresponds to the TNC TNCE TSC TSCE card in Slot 1 of the ONS 15454 M6 shelf used as the node controller b Plug the other connector into the MSM port that corresponds to the TNC TNCE TSC TSCE card in Slot 1 of the ONS 15454 M6 shelf used as subtending shelf When connecting two shelves using the cross over cables it is possible to have shelves not having controller cards in same slots Use correspond...

Page 461: ... the ONS 15454 M6 shelf to orient the air flow in a specific direction Air deflectors can be mounted in different positions to control the air flow Front to Front Only ETSI rack Front to Back For ANSI and ETSI racks Front to Top Only ETSI rack In an ANSI rack the air deflectors are mounted only on the 23 inch rack configuration Cisco ONS 15454 Hardware Installation Guide 431 Installing the ONS 154...

Page 462: ...e installed in any empty slot in the shelf CTC does not detect blank cards The following figure shows the faceplate of the blank card filler Figure 286 Blank Card Filler Faceplate Air Filter The ONS 15454 M6 contains a preinstalled reusable air filter 15454 M6 FTF on the right side of the shelf The reusable filter is made up of a gray open cell polyurethane foam that is specially coated to provide...

Page 463: ... the ONS 15454 M6 shelf depending on the I O cards used CTC allows you to choose a cooling profile for ONS 15454 M6 shelf You can change the cooling profile in Shelf view Provisioning General Voltage Temperature pane in CTC The supported cooling profile values are Low Medium and High The default cooling profile value is High You can change the cooling profile depending on the cards used in the she...

Page 464: ...40 DMX C 40 DMX L 32 MUX O 40 MUX C 40 MUX L AR_MXP AR_XP GE XP MXP_2 5G_10E MXP_2 5G_10G 40 WXC C 40 WXC L 80 WXC C AD 1B AD 1C MXP_2 5G_10X MXP_MR_10DME MXP_MR_10DMEX MXP_MR_2 5G MXPP_MR_2 5G AD 2C AD 4B AD 4C MD 4 MMU OPT RAMP C OPT RAMP CE OTU2_XP RAMAN COP RAMAN CTP OPT AMP 17 C OPT AMP C OPT AMP L OPT BST OPT BST E OPT BST L OPT EDFA 17 OPT EDFA 24 OPT PRE OSCM OSC CSM PSM TDC CC TDC FC TXP_...

Page 465: ... 439 NTP G262 Replace the Air Filter of the ONS 15454 M6 Shelf Assembly on page 441 NTP G263 Replace the Air Filter of the AC Power Module in the ONS 15454 M6 Shelf Assembly on page 444 NTP G115 Clean Fiber Connectors on page 445 NTP G40 Replace the Front Door on page 448 NTP G116 Replace the Fan Tray Assembly of the ONS 15454 Shelf Assembly on page 450 NTP G272 Replace the Fan Tray Assembly of th...

Page 466: ...ther side facing up it is recommended that you install it with the metal bracing facing up to preserve the surface of the filter You must install the air filter with the metal bracing facing up with 15454E CC FTA or 15454 CC FTA Caution To install the air filter inside the air ramp unit 15454E AIR RAMP or 15454 AIR RAMP use the ETSI version of the air filter 15454 FTF2 or 15454E FTF4 Note Procedur...

Page 467: ...nlocking the front door Turn the key counterclockwise to unlock the door and clockwise to lock it b Press the door button to release the latch c Swing the door open Step 3 Optional Remove the front door using the DLP G10 Remove the Front Door on page 58 If you do not want to remove the door or it is already removed proceed to Step 4 Figure 287 ANSI Shelf Fan Tray Air Filter in an External Filter B...

Page 468: ... is installed in the external filter brackets slide the new air filter all the way to the back of the brackets b If the filter is installed below the fan tray assembly slide the new air filter into the recessed compartment at the bottom of the shelf assembly Put the front edge of the air filter flush against the front edge of the recessed compartment Push the fan tray back into the shelf assembly ...

Page 469: ...ischarge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures As Needed Required As Needed Remote Onsite Remote Provisioning or higher Security Level The air filters are single use only They must not be cleaned and reused This is a Telcordia NEBS requirement GR 63 CORE Issue 4 Note Air filters must be inspected every month If they are dirty or clogged with dust they mu...

Page 470: ... Figure 290 Replacing the Air Filter Filter grid 2 Air filter 1 Step 3 Separate the cable guides from the air filter as shown in the following figure Cisco ONS 15454 Hardware Installation Guide 440 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf NTP G274 Replace the Air Filter of the ONS 15454 M2 Shelf Assembly ...

Page 471: ...6 Shelf Assembly This procedure replaces the air filter of the ONS 15454 M6 shelf assembly Purpose New air filter Tools Equipment NTP G252 Install the ONS 15454 M6 Shelf on page 294 Connect the chassis to the office ground For detailed instructions on how to ground the chassis refer to the Electrostatic Discharge and Grounding Guide for Cisco CPT and Cisco ONS Platforms Prerequisite Procedures As ...

Page 472: ...front door continue with Step 3 Step 2 Optional Complete the DLP G577 Remove the Standard Door of the ONS 15454 M6 Shelf on page 330 to remove the front door If you do not want to remove the door proceed to Step 3 Step 3 Push the retention feature present on the right side of the shelf assembly to the left side see the following figure Figure 292 Replacing the Air Filter Step 4 Extract the air fil...

Page 473: ...s shown in Figure 293 Extracting the Air Filter on page 443 Note Step 7 Push the retention feature to the right side see the following figure Figure 294 Replacing the Air Filter Step 8 Close the front door If you removed the door complete the NTP G258 Install the Standard Door of the ONS 15454 M6 Shelf on page 323 Cisco ONS 15454 Hardware Installation Guide 443 Maintaining the ONS 15454 M12 ANSI a...

Page 474: ...They must not be cleaned and reused This is a Telcordia NEBS requirement GR 63 CORE Issue 4 Note Air filters must be inspected every month If they are dirty or clogged with dust they must be replaced with a new air filter Note Procedure Step 1 Open the front door of the shelf assembly see DLP G576 Open the Standard Door of the ONS 15454 M6 Shelf on page 328 If the shelf assembly does not have a fr...

Page 475: ...p You have completed this procedure NTP G115 Clean Fiber Connectors This procedure cleans the fiber connectors Purpose Inspection microscope Type A Fiber Optic Connector Cleaner CLETOP reel Optical swab Optical receiver cleaning stick Tools Equipment None Prerequisite Procedures Required Required As Needed Onsite Onsite Remote Cisco ONS 15454 Hardware Installation Guide 445 Maintaining the ONS 154...

Page 476: ...Fiber Adapters on page 447 as necessary To clean multi fiber optic connectors complete the DLP G261 Clean Multi Fiber Optic Cable Connectors on page 446 as necessary Note Stop You have completed this procedure DLP G261 Clean Multi Fiber Optic Cable Connectors This task cleans the multi fiber optic connectors Purpose Cleaning Cartridge for multi fiber optic connectors Tools Equipment None Prerequis...

Page 477: ...en the shutter door Each time you press the lever you expose a clean wiping surface Step 3 Insert the connector into the CLETOP cleaning cassette slot rotate one quarter turn and gently swipe downwards Step 4 Use an inspection microscope to inspect each fiber connector for dirt cracks or scratches If the connector is not clean repeat Steps 1 to 3 Step 5 Insert the fiber connector into the applicab...

Page 478: ...d screwdriver Tools Equipment NTP G259 Open and Remove the Standard Door of the ONS 15454 M6 Shelf on page 327 Prerequisite Procedures Required Required As Needed Onsite Onsite Remote None Security Level Be careful not to crimp any fiber cables that are connected to the MXP TXP cards or DWDM cards Some might not have the fiber boot attached Note Procedure Step 1 Insert the front door into the hing...

Page 479: ...sition when the door is open To move the ground strap into a flat position rotate the terminal lug counterclockwise before tightening the Kepnut Note Step 4 Replace the left cable routing channel if it was removed If not continue with Step 5 Step 5 Using a Phillips screwdriver insert and tighten the screws for the cable routing channel The following figure shows the shelf assembly with the front d...

Page 480: ... Fan Tray Assembly of the ONS 15454 Shelf Assembly This procedure replaces a malfunctioning fan tray assembly Purpose None Tools Equipment NTP G257 Install the Fan Tray Assembly in the ONS 15454 M6 Shelf on page 388 Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote Cisco ONS 15454 Hardware Installation Guide 450 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and O...

Page 481: ...y assembly or AIP replacement is required But the Fan Fail LED on the 15454E CC FTA and 15454 CC FTA will also illuminate when only one power source is connected to the chassis and or any fuse blows In such conditions the Fan Alarm is triggered and the fans run at maximum speed Caution To replace the fan tray assembly it is not necessary to move any of the cable management facilities Note Procedur...

Page 482: ...S 15454 Release 3 1 and later shelf assembly15454 SA HD P N 800 24848 ONS 15454 Release 3 1 and later shelf assembly 5 5A Fan Tray 15454 FTA3 P N 800 19858 xx 15454 FTA3 T P N 800 21448 xx 15454 CC FTA P N 800 27558 xx 2A Fan Tray 15454 FTA2 P Ns 800 07145 xx 800 07385 xx 800 19591 xx 800 19590 xx 6 5A AIP P N 73 7665 01 2A AIP P N 73 5262 01 7 10G cards include the XC10G OC192 and OC48AS 8 2 5G c...

Page 483: ...d hex key for locking and unlocking the front door Turn the key counterclockwise to unlock the door and clockwise to lock it b Press the door button to release the latch c Swing the door open Step 3 Optional Complete the DLP G577 Remove the Standard Door of the ONS 15454 M6 Shelf on page 330 to remove the front door If you do not want to remove the door proceed to Step 4 Step 4 Push the outer side...

Page 484: ...he following figure shows the location of the fan tray on the ONS 15454 ETSI shelf Cisco ONS 15454 Hardware Installation Guide 454 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf NTP G116 Replace the Fan Tray Assembly of the ONS 15454 Shelf Assembly ...

Page 485: ...the NTP G114 Inspect and Replace the Air Filter on page 435 Step 9 Slide the new fan tray into the shelf assembly until the electrical plug at the rear of the tray plugs into the corresponding receptacle on the backplane Step 10 To verify that the tray has plugged into the backplane ensure that the LCD on the front of the fan tray is activated If you removed the door complete the NTP G40 Replace t...

Page 486: ...an tray assembly into place Doing so can damage either the connectors on the fan tray or the connectors on the back panel of the shelf assembly or both Caution The estimated time required to change a fan tray assembly is 2 minutes Note Procedure Step 1 Loosen the screw on the fan tray assembly see the following figure Figure 300 Fan Tray Assembly installed in the ONS 15454 M2 Shelf Assembly Cisco ...

Page 487: ...n Tray Extracted Step 4 Slide the new fan tray assembly into the shelf assembly until the electrical plug at the rear of the tray plugs into the corresponding receptacle on the backplane Step 5 To verify that the tray has plugged into the backplane ensure that the LCD on the front of the fan tray is activated Stop You have completed this procedure Cisco ONS 15454 Hardware Installation Guide 457 Ma...

Page 488: ...aution The estimated time required to change a fan tray assembly is 2 minutes Note Procedure Step 1 Open the front door of the shelf assembly see DLP G576 Open the Standard Door of the ONS 15454 M6 Shelf on page 328 If the shelf assembly does not have a front door continue with Step 3 Step 2 Optional Complete the DLP G577 Remove the Standard Door of the ONS 15454 M6 Shelf on page 330 to remove the...

Page 489: ...re 304 Fan Tray Assembly Extracted Partially with Power Connector Disconnected Step 5 When the fans have stopped pull the fan tray assembly completely out of the shelf assembly see the following figure Cisco ONS 15454 Hardware Installation Guide 459 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf NTP G260 Replace the Fan Tray Assembly of the ONS 15454 M6 Shelf Assem...

Page 490: ...he Standard Door of the ONS 15454 M6 Shelf on page 323 Stop You have completed this procedure NTP G117 Replace the ANSI Shelf Alarm Interface Panel This procedure replaces the AIP on the ONS 15454 ANSI shelf assembly Purpose 2 Phillips screwdriver Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite or remote Onsite Remote Provisioning or higher Security Level Cisco ONS...

Page 491: ... document No hardware should be changed or circuit repair performed until after the software upgrade is complete If you do not need to upgrade software or have completed the software upgrade proceed to Step 3 Step 3 Record the MAC address of the old AIP a Log into the node where you will replace the AIP See the DLP G46 Log into CTC b In node view single shelf mode or multishelf view multishelf mod...

Page 492: ... other steps until the reset is complete Note Step 17 Complete the DLP G250 Reset the TCC2 TCC2P TCC3 TNC TSC Card task in the Cisco ONS 15454 DWDM Configuration Guide to reset the active TCC2 TCC2P TCC3 TNC TSC card Step 18 From the File drop down list choose Exit to exit the CTC session Step 19 Log back into the node In the Login dialog box choose None from the Additional Nodes drop down list St...

Page 493: ...e Cover This procedure replaces the metal cover with the plastic cover located at the bottom rear of the ONS 15454 ANSI shelf Purpose Phillips screwdriver Tools Equipment None Prerequisite Procedures As needed Required As Needed Onsite Onsite Remote None Security Level Procedure Step 1 Use the Phillips screwdriver to unscrew the five retaining screws that hold the metal cover in place Step 2 Grasp...

Page 494: ...m Mode Using LCD For ONS 15454 M2 and 15454 M6 the system mode can be changed from ANSI SONET to ETSI SDH or vice versa Changing the system mode removes the provisioned data and the system reverts to the default configuration Cisco ONS 15454 Hardware Installation Guide 464 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf NTP G795 Change System Mode Using LCD ...

Page 495: ...nu Step 3 Press the Status button to enter the Mode Change Configuration option Controller Status Mode cfg Step 4 On the left hand side of the LCD display the Slot button the ANSI option is displayed On the right hand side of the LCD display the Port button the ETSI option is displayed Step 5 Select the required mode either by pressing the Slot or Port button If the user by mistake chooses the cur...

Page 496: ...Cisco ONS 15454 Hardware Installation Guide 466 Maintaining the ONS 15454 M12 ANSI and ETSI ONS 15454 M2 and ONS 15454 M6 Shelf NTP G795 Change System Mode Using LCD ...

Page 497: ...tion The TCC2P card can be used as a control card in a subtended shelf where the node controller is TCC3 card on ONS 15454 chassis or TNC TNCE TNCS TNCS O cards on ONS 15454 M6 or NCS 20015 chassis The TCC2P card can also be used as a node controller in a stand alone configuration Note The following sections are included ONS 15454 Shelf Specifications on page 467 ONS 15454 M2 Shelf Specifications ...

Page 498: ... field ANSI only Front Mount Electrical Connection FMEC access LAN connector on MIC C T P faceplate ETSI only External LAN Interface The ONS 15454 external LAN interface has these specifications 10BaseT Ethernet Backplane access LAN pin field ANSI only FMEC access LAN connector on MIC C T P faceplate ETSI only TL1 Craft Interface The ONS 15454 TL1 craft interface has these specifications Speed 960...

Page 499: ... ohm 4 leg connector King or ITT are also compatible AMP Champ AMP 552246 1 with 552562 2 bail locks BITS Interface ANSI only The ONS 15454 building integrated timing supply BITS interface has these specifications 2 DS 1 BITS inputs 2 derived DS 1 outputs Backplane access BITS pin field System Timing The ONS 15454 ANSI has these system timing specifications Stratum 3 per Telcordia GR 253 CORE Free...

Page 500: ...ls 3WK3 Combo D power cable connector MIC A P and MIC C T P faceplates Fusing 100 A fuse panel minimum 30 A fuse per shelf Fan Tray The following table lists power requirements for the fan tray assembly Table 44 Fan Tray Assembly Power Requirements BTU Hr Amps Watts Fan Tray Assembly 198 1 21 53 FTA2 295 1 8 86 4 FTA3 T 393 2 4 115 15454E CC FTA 15454 CC FTA System Environmental Specifications The...

Page 501: ...f bandwidth a list of topologies Cisco Transport Controller CTC specifications the LAN Transaction Language One TL1 modem and alarm specifications timing power and environmental specifications and shelf dimensions Bandwidth The ONS 15454 M2 has these bandwidth specifications depending on the applications Total bandwidth 200 Gbps Data plane bandwidth 100 Gbps per slot Configurations The ONS 15454 M...

Page 502: ...emote Inventory The ONS 15454 M2 provides 1 standard USB port located on the power module to retrieve the passive units inventory data BITS Interface The ONS 15454 M2 building integrated timing supply BITS interface has these specifications 1 DS 1 BITS inputs wire wrap for ANSI applications 1 derived DS 1 outputs wire wrap for ANSI applications 1 E1 BITS input DIN 1 0 2 3 for ETSI applications 1 E...

Page 503: ...ns Nominal Input Voltage 48 VDC Power consumption Configuration dependent 35 W Fan Tray and LCD Power requirements Nominal 48 VDC Input Voltage Range 40 5 to 57 6 VDC Power terminals DSUB 2 poles for ETSI applications and terminal block double pole for ANSI applications External fuse must not exceed 15A Total maximum power consumption of 450W with ancillaries controllers and linecards Fan Tray The...

Page 504: ...st of topologies Cisco Transport Controller CTC specifications the LAN Transaction Language One TL1 modem and alarm specifications timing power and environmental specifications and ONS 15454 M6 shelf dimensions Bandwidth The ONS 15454 M6 has the following bandwidth specifications depending on the applications Total bandwidth 600 Gbps Data plane bandwidth 100 Gbps per slot Configurations The ONS 15...

Page 505: ...modem interface has the following specifications Hardware flow control TNC TNCE TSC TSCE EIA TIA 232 DB 9 type connector Alarm Interface The ONS 15454 M6 alarm interface has the following specifications 2 SCSI Connectors located on the ECU or ECU2 Visual Critical Major Minor Remote Audible Critical Major Minor Remote Alarm inputs Common 32 VDC output for all alarm inputs closed contact limited to ...

Page 506: ...ifications Shelf power consumption Configuration dependent 130 W Fan Tray LCD and ECU module Power terminals standard 3 pole AC connector Fuse rating for an AC power supply must not exceed 10 A 15 A or 20 A depending on the standard in various countries For North America the branch circuit protection must be rated 20 A The following table lists power specifications of the AC power modules for the ...

Page 507: ...K LC MR MXP cards and the 15454 M6 ECU 60 card Note 15454 M6 DC 15454 M6 DC20 and 15454 M6 DC40 shelf power consumption configuration dependent 130 W with 15454 M6 FTA Fan Tray LCD and ECU module 140 W with 15454 M6 FTA2 Fan Tray LCD and ECU module When you use the 60V DC power module for ONS 15454 M6 you must go to CTC shelf view Provisioning General Power Monitor and set the following threshold ...

Page 508: ...e power consumption values of the line cards that are considered for power calculation The Actual Power is the power consumed by a line card once it has boot up The Typical Power is the power consumed by a line card when it is physically present in the shelf but deleted in CTC or when it has not boot up due to PWR CON LMT alarm after installation or pre provisioning During power calculation certai...

Page 509: ...Watts Fan Tray Assembly 410 3 120 15454 M6 FTA 445 3 5 130 15454 M6 FTA2 System Environmental Specifications The ONS 15454 M6 for ANSI environment has these specifications Operating temperature 23 to 131 degrees Farenheit 5 to 55 degrees Celsius Operating humidity 5 to 95 percent noncondensing The ONS 15454 M6 for ETSI environment has these specifications Operating temperature 23 to 131 degrees Fa...

Page 510: ...Cisco ONS 15454 Hardware Installation Guide 480 Hardware Specifications Dimensions ...

Page 511: ...patibility alarms 450 interface specifications 469 AMP champ 112 attaching 91 AEP to the backplane 91 B backplane 53 54 64 65 91 94 106 109 110 111 118 463 AEP connections 91 alarm wire connections 106 alarm wire illustration 106 attaching AEP 91 connection overview 94 covers overview 53 installing the rear cover 118 LAN wire connections 110 lower cover description 54 rear cover description 54 rem...

Page 512: ... chassis 123 typical rack layout 120 default para font 26 39 154 detaching the ground strap 58 DWDM 120 123 173 468 configurations 468 fiber tray 173 optional hardware 123 rack layouts 120 topologies 468 E EAP 154 cable 154 descriptionEthernet adapter panel See 154 EIA interface specifications 469 EIA TIA 232 port 111 accessing a TL1 craft interface 111 do not use backplane pins simultaneously 111...

Page 513: ... 448 description 45 installing ground strap retrofit kit 448 label ANSI 45 215 320 opening 57 219 328 front door continued removing 58 220 330 removing ANSI 45 replacing 448 fuse and alarm panel 1 2 4 26 29 71 74 244 252 274 377 386 description 1 2 4 location ANSI 26 274 location ETSI 29 measuring and cutting cables 71 244 377 verifying office battery and ground 74 252 386 G ground 68 74 238 239 2...

Page 514: ...MIC A P FMEC continued installing 66 installing alarm cables 101 pin connections 70 MIC C T P FMEC 66 70 104 105 description 66 installing 66 installing LAN cables 105 installing timing cables 104 pin connections 70 timing connectors 104 modem interface 468 module See card 131 261 mounting 29 36 37 39 180 275 276 315 317 318 multiple nodes in a rack 29 39 276 318 shelf assembly in a rack one perso...

Page 515: ...72 installation overview ETSI 27 179 274 mount a single node ANSI 26 179 273 mount multiple nodes ANSI 26 274 rack continued mounting a single node 36 37 315 317 mounting a single node ETSI 180 275 mounting multiple nodes 39 318 mounting multiple nodes ETSI 29 276 reversible mounting bracket 25 273 typical DWDM layouts 120 rear cover 54 removing 45 58 62 64 65 220 330 435 backplane lower cover 64 ...

Page 516: ... interface specifications 468 pin assignments 111 TNC card 261 265 266 configuring UDC and VoIP 266 installing 261 TNC card continued provisioning PPM and port 265 TransportPlanner See Cisco TransportPlanner 123 TSC card 261 installing 261 turning on office power 74 251 252 385 386 U unpacking the shelf assembly 20 V verifying 20 74 132 146 251 252 262 268 385 386 427 ground 74 252 386 office powe...

Reviews: