3-39
Cisco UCS C220 M4 Server Installation and Service Guide
OL-32473-01
Chapter 3 Maintaining the Server
Installing or Replacing Server Components
b.
Align the connector on the riser with the socket on the motherboard. At the same time, align the two
slots on the back side of the bracket with the two pegs on the inner chassis wall.
c.
Push down gently to engage the riser connector with the motherboard socket. The metal riser bracket
must also engage the two pegs that secure it to the chassis wall.
d.
Reconnect the SAS cable to its connector on the RAID controller card.
Step 4
Replace the top cover.
Step 5
Replace the server in the rack, replace cables, and then power on the server by pressing the
Power
button.
Figure 3-20
Cisco Modular RAID Controller Riser (Internal Riser 3) Location
1
Cisco modular RAID controller riser
assembly (top of bracket)
2
Cisco modular RAID controller card in riser
353099
FAN 6
FAN 5
FAN 4
FAN 3
FAN 2
FAN 1
CPU 2
CPU 1
PSU 2
PSU 1
PCIe Riser 1
PCIe Riser 2
SD 1
SD 2
2
1