Assembly
Mounting the frame to the tow
Concrete stones assembly
The CRO 4.0 leaves the factory
assembled. Note that the frame is
fastened to the tow through the upper
hole, which is used on most operations.
Never use the lower hole on a
concrete yard.
When using the lower
hole, check if organic matter
is not being mixed with earth
and if the rotor blades are not
touching the ground.
To fill up the stones with concrete, follow the instructions:
First of all, place the two small stones and then the three larger ones (observing the
equipment from behind) according to the illustration.
Smaller stones:
Filling: NBR 7212 and 12655 concrete.
Volume: 0.293 m³ per stone.
Compression strength (FCK): 13.5 MPA.
Formula: CAP 1:2:3
Water: 20 - 27 liters / cement bag.
Larger stones:
Filling: NBR 7212 and 12655 concrete.
Volume: 0.456 m³ per stone.
Compression strength (FCK): 13.5 MPA.
Formula: CAP 1:2:3
Water: 20 - 27 liters / cement bag.
After filling up all stones, place the lock (A) on
the tubes and fasten using flat washers and cotter
pin to avoid that the stones fall apart.
NOTE When the equipment is going abroad, the concrete stones must be empty.
The approximated weight of each stone must be:
Smaller stone box = 750 kg.
Larger stone box = 1,100 kg.
Lower hole
Lower hole
Upper hole
Upper hole
A