background image

ClearCube Technology, Inc.      3700 W Parmer Lane      Austin, Texas 78727      (512) 652-3500      www.clearcube.com

 

G0200

97

 Rev C, 1.2.06.05.2013

Page 2 of 3

brackets, two back brackets, and mounting hardware. The 
optional ClearCube Chassis Rapid-Mount (CRM) kit fits 
standard four-post racks with square mounting holes for 
snap-in rack nuts.

Installing the Ground Strap

After installing the A3100 chassis, use the included 10-32 
screws to attach the ground strap to the ground point on the 
right-hand side of the AC tray and to the rack or cabinet in 
which the A3100 chassis is installed. Ensure that the rack or 
chassis is properly grounded. See the figure below.

Power Inputs and Failover Power Feature

Be sure to connect the chassis ground strap (as explained in 
the section above) before connecting power.

As shown in the figure below, the A3100 chassis has four 
power receptacles: two for each half of the chassis providing 
power and redundant power.

• Receptacles A and B power Blade PCs in slots one

 

through five.

• Receptacles C and D power Blade PCs in slots six 

through ten.

The picture below shows the A3100 power receptacles.

Power indicator LEDs are below each power receptacle. 
LEDs are illuminated when receptacles receive power.

To enable the A3100 failover power feature, connect power 
to all power inputs:

• Receptacles A and C provide primary power.

• Receptacles B and D provide failover power. Connect the 

cords in receptacles B and D to a backup power supply, 
such as a different power circuit or to a UPS.

See 

A–Series Setup and Installation Guide

 for more 

information about chassis power inputs and about using the 
chassis without the failover power feature.

Installing and Removing A–Series Blade PCs

To install an A–Series Blade PC

1.

Open the chassis front bezel by pressing in on the latch 
located on the upper-right side of the chassis.

NOTE

To screw the ground strap to a rack, insert a 
snap-in rack nut. A rack nut is not provided in 
the kit.

CAUTION: High Leakage Current

Connect chassis earth ground before supplying 
AC power to chassis.

Ground Strap

AC Tray

CAUTION

Never lift an A3100 chassis with Blade PCs installed.

NOTE

When pressing the latch to open the front 
bezel, hold the bezel with one hand to ensure 
that the bezel does not fall.

Power Receptacles for 

Blades 6 to 10

Power Receptacles 

for Blades 1 to 5

A

B

C

D

Reviews: