Preparing the Site
Installing the Wall-Mount Kit
At the installation site, verify the following:
• The wall or H-frame is installed and plumb.
• The wall or H-frame meets the cabinet mounting requirements.
Trench out conduit paths to the wall or H-frame from the cable feeder location. Place the cable conduits into
the conduit trench. At the wall or H-frame, allow the conduit to extend above ground to the approximate height
of the base platform. Refer to the wall mounting guidelines for conduit sizes and locations.
Route the earth ground wire through the conduit trench (from the ground electrode). Pull six feet of wire above
ground and position it adjacent to the wall or H-frame. Backfill the conduit trench with soil.
Step 1:
Step 2:
Step 3:
Prepare the site for installation of a wall-mount kit. A general practice is described below for reference. Adapt the
instructions as needed for local requirements, practices, or conditions.
To prepare the site for a wall mount installation
Install the Clearfield wall-mount kit onto a wall or H-frame as
described below. Adapt the instructions as needed for local
requirements, practices, or conditions.
The primary components of the kit are identified at right.