Preparing the Cabinet for Installation
Open the front and side cabinet doors.
From the side compartment, remove the isolation mat and the bag containing the installation hardware. Set
them aside for use during installation.
Prepare the battery compartment as follows:
a.
Remove the battery compartment door.
b.
Remove the optional battery heater, if present:
• Disconnect the power cord from the supply lead on the left compartment wall.
• Remove the battery heater from the battery tray. Set it aside for later re-installation.
Prepare the AC load center as follows:
a.
Remove the four screws from the AC load center’s front (breaker) panel, and then remove the panel from the
load center housing. Retain the hardware for re-installation.
b.
Loosen the coupling nut at the bottom of the housing to allow AC wires to pass into the load center.
Remove the nuts from the four bolts securing the cabinet to the pallet:
Local power configuration: The bolts are located at the bottom four corners of the battery compartment.
On the cable entry ducts, trim the rubber cone gaskets to the OSP cable diameter that will enter the cabinet
(when installed). Be careful not to trim too much, as the gaskets should fit snugly around the cable.
When the tasks above are complete, the cabinet is ready for installation.
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
Complete the following preparations before installing the cabinet.
To prepare the cabinet for installation