64
Sweep the pad free of dirt and debris.
Install the isolation mat onto the base platform.
Using two people, lift the cabinet (with battery compartment) or battery compartment riser onto the base plat-
form, aligning the mounting holes in the base with the counterpart holes in the platform.
Pull the earth ground wire into the cabinet or riser through one of the cable entry ducts.
Anchor the cabinet or riser to the base platform as follows:
a.
Get (4) anchor bolts, (4) flat washers, and four lock washers from the installation kit.
b.
Install one anchor bolt, one flat washer and one lock washer into each of the four mounting holes.
c.
Tighten the bolts to secure the cabinet or riser to the pad.
Verify that the doors open and close freely. If necessary, use shims to level the cabinet or riser.
Apply silicone caulking to the bottom perimeter of the cabinet or riser.
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
Step 6:
Step 7:
To install the cabinet (or riser) on a wall or H-frame
Note:
To complete the installation, install the top bracket to secure the cabinet to the wall or H-frame. See Installing the
Mounting Fixture on a Wall/H-Frame for instructions.