At the rectifier shelf, open the fuse panel door. Verify that the battery breaker is OFF.
Remove the battery compartment door. See Operating Cabinet Doors for instructions.
Remove the front retainer bracket from the battery tray.
Note:
If you are using the optional battery heater, install the heater before installing batteries. See Installing a
Battery Heater for instructions.
In the battery compartment, disconnect the #8 AWG battery power cables from the power supply leads and set
the cables aside.
Place a string of four batteries partially into the battery compartment, arranged with the terminals accessible
in front.
Note:
You will slide the batteries into the battery tray after installing the cables and protective covers.
Step 1:
Step 2:
Step 3:
Step 4:
Step 5:
To install a single string of 60 Ah or 62 Ah batteries
Note:
If you plan to install a second battery string in the riser compartment, go to the next procedure. If you do not plan to
install a second battery string, locate the Anderson connector for the second battery string and disconnect if required.
Note:
Before installing battery strings, install the rear seismic retainer. Use a seismic protection kit for cabinets located in up
to Zone 4 Earthquake environments.