13
CLEARSPAN
™
POLY BUILDINGS
Revision date: 05.19.09
FINAL FRAME CHECK
1. Return to the frame connections and verify that all bolts
are tight.
2. Verify that each purlin splice is secured with a Tek
screw.
3. Verify that each purlin is secured to the end clamp and
cross connector and that each cross connector and
end clamp is secured to the rafter. See diagram below.
4. Inspect the frame for sharp areas that could damage
the cover. If found, file smooth and cover with layers of
duct tape to protect the cover.
5. Verify that all bolts are positioned with the heads to the
outside of the frame. Tape the bolts and rafter joints
before
installing the cover.
Cross Connector
to Rafter Tek
Screw
Purlin to Cross
Connector Tek Screw
Rafter
Purlin
ATTENTION:
Position the Tek
screws so they will
not touch the cover
once it is installed.
INSTALL THE MAIN COVER RATCHETS
Attach all QH1061 side ratchets
on the outside of the pony
wall.
Gather the parts:
• Ratchets (#QH1061)
• Tek screws (#FA4482B): Tek screws may not be the
correct fastener for some pony wall constructions. See
the note in Step 1.
Due to the different materials used
to construct pony walls, the customer is responsible for
supplying the required fasteners. Consult the advice of
a qualified professional contractor if needed.
Complete the following steps to secure the ratchets to the
pony wall.
1. Locate four (4) ratchets (#QH1061) and attach these
to the outside ends of the pony wall as shown in the
diagram below. Attach each ratchet using a Tek screw
(FA4482B).
(Fasteners for pony walls constructed
of material such as concrete, stone, or wood are not
included and must be purchased separately. Consult a
contractor if needed.)
4. Measure approximately 6"-12" down from the top of the
pony wall and attach as shown below.
Install ratchets immediately across from each other
below the same rafter.
The main point is to space the ratchets as evenly as
possible and opposite one another below
the same
rafter
to best stretch and secure the main cover.
5. After installing all side ratchets and a final check of
the frame is complete, continue with the main cover
installation.
6"-12"
Photo shows straps and cover already installed, these
items are installed later in the instructions.
2. Locate the remaining ratchets and divide the quantity in
half. Use half for each side of the shelter.
3. Evenly space the remaining QH1061 ratchets along the
outside of the pony wall.
ATTENTION:
Consult the Side Profile Diagram in the
Quick Start Section for ratchet locations.
Distance shown by the arrow above is approximately
6" to 8" from center of the end rafter to the center of
the ratchet.
Inside of Shelter
End (front or
back) of the
pony wall.
6"-8"
Consult a
construction
professional to
determine the best
fasteners for your
pony wall.