background image

NOTE:

 Tek screws are self-drilling and no pilot hole is 

usually required. If you have trouble getting a Tek screw 
to "bite", try another Tek screw (or you can drill a 3/16" 
pilot hole). 

6.  On the sides of the rafter, position the top strap of 

the end clamp to rest on the Tek screw as shown in 
Figure 4. This prevents the clamp from slipping 
when the purlin supports any weight. 

 

Figure 4.

 End Clamp Resting on Tek Screw 

7.  Slide two purlin end clamps on bottom side of each 

end rafter into the positions at least 2-4" away from 
the rafter bottom, as shown in Figure 6, to leave 
room for the short tee connector added later. 

8.  Slip five cross connectors over each inside rafter at 

the same end clamp positions shown in Figure 2. 

9.  Leave screws loose on the cross connectors so you 

can slide in the purlins later. 

10.  On the sides of the rafter, position the top strap of 

the cross connectors to rest on the Tek screw as 
shown in 

Figure 7

. This prevents the clamp from 

slipping when the purlin supports any weight. 

ASSEMBLE THE FRAME 

Gather the Parts 

• 

All Rafter Assemblies 

• 

Pipe 1.315"x75" Swaged 17GA (10) (#131S075) 

• 

Pipe 1.315"x73.5" Plain 17GA (5) (#131P0735) 

• 

Strut 5' (4) (#QH1304) 

• 

Band Clamps (4) (#QH1400) 

Assembly Procedure 

1.  Stand one end rafter (one with the band clamps 

attached) and brace it in place as shown in 
Figure 5. Check that the rafter is standing up  

straight (plumb). Position the bolt side of end clamp 
to the inside of the frame. 

 

Figure 5. 

Standing Rafters 

2.  Insert the plain ends of 75" purlin pipes into the end 

purlin clamps at the bottoms of the end rafter and 
tighten the clamps. 

! CAUTION:

 To prevent cover damage, the ends of the 

purlins should extend no more than ½" past the end 
clamp. The bolt side of the end clamps must go toward 
the “inside” of the shelter (the same side as the purlin) 
as shown in Figure 6. 

 

Figure 6. 

Purlin Inserted into End Clamp 

3.  Position an inside rafter from the end rafter using an 

on-center rafter-to-rafter spacing of 43 ¼". Have 
your partner hold the rafter in position while you 
tighten the cross connectors at the bottom of the 
second rafter. 

4.  Slide a purlin through cross connector at the top of 

second rafter and also through the end clamp at the 
top of the end rafter. Verify that the rafter is properly 
spaced and plumb and tighten the cross connector 
at the top of the 2

nd

 rafter. 

 

Figure 7.

 Cross Connector Assembly 

Tek screw 

End clamp

Outside of 
shelter 

Purlin 

Rafter 

Outside of 
shelter

Inside of 
shelter 

2-4"

½"

Purlin 

Rafter 

Tek 
Screw

Cross 

Connector

Visit www.ClearSpan.com for additional products and customer assistance.

5 of 12

Summary of Contents for PB02000R4N

Page 1: ...Span Round Style Mini Garage Use these instructions for the following round style mini garage SKU PB02000R4N 10 Wide x 8 High x 18 Long 2006 ClearSpan All Rights Reserved Reproduction is prohibited without permission Revision date July 2006p ...

Page 2: ...assemble the structure The following suggestions and precautions will help you determine whether your selected location is the best location Never erect the structure under power lines Identify whether underground cables and pipes are present before preparing the site or anchoring the structure Location should be away from structures that could cause snow to drift on or around the frame Do not pos...

Page 3: ...your shelter Conduit An assembly of pipes used to secure the main cover and end panels if equipped Purlins and some strut assemblies also consist of connected pipes to form a conduit Each pipe joint of a conduit assembly is secured with a self tapping Tek screw Coupler or Fitting A part of the frame assembly where legs purlins and rafter pipes are inserted and secured In most instances 3 way and 4...

Page 4: ...IFY PARTS The following steps will ensure that you have all the necessary parts before you begin to assemble the frame 1 Unpack the contents of the shipment and place where you can easily inventory the parts See Parts Included in Shipment if you are not familiar with a part name 2 Make sure you have all parts listed on the Bill of Materials Spec Sheet If anything is missing or you have questions c...

Page 5: ...10 Round Raft Position 2 10R1302 Pipe 1 315 10 Round Raft Position 3 10R1303 Band Clamps QH1400 Purlin End Clamps 102855 Cross Connectors 102479 Tek Screws FA4482B Nut Setter 3 8 x 2 9 16 Magnetic 1 100441 Assembly Procedure NOTE To prevent twisting assemble rafters on a level surface 1 Connect the pipes together as shown in Figure 2 to form an arched rafter lying on the ground Figure 2 Assembling...

Page 6: ...0 Assembly Procedure 1 Stand one end rafter one with the band clamps attached and brace it in place as shown in Figure 5 Check that the rafter is standing up straight plumb Position the bolt side of end clamp to the inside of the frame Figure 5 Standing Rafters 2 Insert the plain ends of 75 purlin pipes into the end purlin clamps at the bottoms of the end rafter and tighten the clamps CAUTION To p...

Page 7: ...he second end rafter and secure as previously described 11 Attach struts between the end rafter just installed and bottom purlins as you did at the other end of the frame SQUARE THE SHELTER Gather the Parts Measuring tape Tek Screws FA4482B Assembly Procedure 1 Square the frame by measuring diagonally corner to corner and align all rafters as shown in Figure 9 Figure 9 Squaring the Frame 2 Secure ...

Page 8: ...Procedure 1 If the corners of your end panels have not been cut out follow this procedure a Lay an end panel out on a clean flat surface b Place the end conduit assembly centered side to side on top of the hem as shown in Figure 11 c With scissors trim the corner of the end panel on the dotted line shown in Figure 11 so the short tee is exposed when it is placed inside the hem d Repeat Steps A C a...

Page 9: ...abric Clips CC6212 Tek Screws FA4482B Measuring Tape Scissors Assembly Procedure 1 While standing inside the shelter start at the peak of the end rafters and pull the solid plain end panel over the top of the rafter so the material edge is on the inside of the rafter 2 Secure the solid end panel in place at the top center of end rafter with a fabric clip and Tek screw 3 Moving outward in both dire...

Page 10: ... ratchets are installed on only one side of the shelter because this model uses D ring straps installed later on the opposite side of the shelter Figure 16 Fastening Ratchets to Rafters 4 Assemble two 18 cover conduits Start each conduit assembly with one plain pipe and add swaged pipes to arrive at the correct length Secure each pipe joint with a Tek screw and wrap the joint with duct tape CAUTIO...

Page 11: ...the end panels locate the black straps already attached near the bottom corners of the cover NOTE If any of your corner straps were shipped with a D ring attached as shown in Figure 21 you must cut the D ring off with scissors because it is not used on this model 5 Have a partner help you tighten both corner straps on the front and rear ends of cover by each simultaneously pulling on the straps 6 ...

Page 12: ...tightened Your completed Round Style Mini Garage should now be fully assembled and anchored Continue to the Shelter Care and Maintenance section for further instructions SHELTER CARE AND MAINTENANCE Proper care and maintenance of your shelter is important The following items identify areas that must be periodically checked to ensure that your shelter is maintained properly Regularly check the roof...

Page 13: ...Customer Notes Visit www ClearSpan com for additional products and customer assistance 12 of 12 ...

Reviews: