CLEARSPAN
™
SUPER MOO-TEL
14
Revision date: 03.16.12
Ground Level
4" x 4" Tubes
4" x 4" Tubes
Dimensions shown above are inside-to-inside.
12'
12'
ATTENTION:
Use the 1/2" x 5-1/2" bolts (#104188B) to
secure the #105351 mounting brackets and #105243
mounting plates. Refer to the End Wall Diagrams (Quick
Start Guide) for additional details.
END WALL INSTALLATION
Consult the end wall diagrams in the Quick Start section of
these instructions
before
you begin.
Assistance is required to assemble the end wall. Lifts
designed to reach the top of the end rafter are also needed.
Consult a qualified construction professional if you are not
familiar with the construction of similar frame structures.
Install the Door Frame Tubes (Jambs) and Header
The following steps describe one way to assemble the door
frame of the end wall. Repeat the steps for the other end
wall.
1. At ground level, measure
between the legs of the end
rafter
to locate the center of the end wall. Use a plumb
line to identify the center of the end rafter and mark that
location on the ground as well. (See Quick Start guide.)
Center the door in the end wall.
NOTE:
Marking the center of the end wall allows multiple measurements to be made as needed.
2. Using the dimensions on the End Wall Frame diagrams, locate the positions of the
vertical door frame members
for
the door. The width of the door determines the frame dimensions for the door opening.
Consult the diagrams and
documentation sent with the door for additional framing details.
3. Dig a 12" diameter hole
at the locations found in previous step
to a depth that is below the geographic frost line.
4. Set two (2) 4" x 4" x 12' tubes aside for the two (2) headers and use the remaining 4" x 4" tubes to assemble the four
(4) vertical door frame members. Attach the tubes to the end rafter. (See Quick Start guide for additional details.)
ATTENTION:
Each tube will extend into the hole dug in Step 3.
Tube length depends on door width and hole depth.
5. After the vertical door frame members are plumb and the correct distance apart,
brace the tubes in position
. Use the
End Wall Diagram—Front to space the vertical door frame members.
When installed correctly, the tubes are directly
below the end rafter.
6. Add concrete to the hole. Concrete should remain 2"- 4" below ground level so that it does not interfere with
construction and installation of other end wall components.
Allow the concrete to set.
7. Add the header to complete one door frame and repeat the steps for the remaining end wall.
Section of the assembled
End Wall Frame.
Concrete
Ground Level
*Not shown to scale.
Ground Level
Vertical Door Frame
Tube (jamb): 4" square
frame tube encased in
concrete.