background image

Annual Maintenance Procedure 

FOR USE WITH CD10, CD10/AD, CD12 & CD12/AD 

 

 

 

 

 

 ClearWater Tech, LLC.

    

 

 

 

 

 

 

 

 

     Page 2 

 1.800.262.0203 • 805.549-9724  
 850-E Capitolio Way, San Luis Obispo, CA 93401 • email: service@cwtozone.com • www.cwtozone.com      

LIT228  Rev.100912 

Reaction Chamber Removal and 

Disassembly: 

Note: Read through all the steps before disassembling the reaction 

chamber.   

Step 1:  

Make sure all power to the ozone generator has been 

disconnected according to the “System Shutdown Procedures” 

outlined above.  

Step 2: 

Disconnect the high voltage lead from the reaction chamber(s). 

Step 3:

  Disconnect the tubing connections on both ends of the reaction 

chamber(s).  

Step 4: 

Remove the 4 nuts securing each chamber and remove the 

reaction chamber from ozone generator. 

Step 5: 

Make note or mark the position of the end caps and their elbow 

fittings on the reaction chambers, during re-assembly the end 

caps will need to return to original positions.  The orientation of the end caps and the chamber itself is different between the two CD12 chambers.

  

Step 6: 

Remove retaining screws and washers from the two end caps (3 each). 

Step 7:

  Using a gentle back-and-forth twisting motion, remove the non-high voltage end cap (the one 

without 

the high voltage attachment screw) from the heat 

sink/cathode assembly. A flat-head screwdriver may be used to gently pry the end cap off, as long as equal pressure is applied to each side of the end cap. 

Step 8: 

Remove the high voltage end cap and dielectric from the heat sink/cathode assembly. 

Step 9: 

The high voltage end cap can be removed by holding the glass and turning the end cap counter-clockwise approximately 6 turns.  Pull the end cap off the glass.  

Push the contact brush out of the dielectric glass. A screwdriver can be used to push the brush, and pliers to pull it out once the opposing end is exposed. 

Step 10: 

Inspect the dielectric, end caps and cathode for breakage, corrosion or debris; then follow the assembly and re-installation steps below. 

 

Reaction Chamber Assembly and Re-installation: 
 

Step 1: 

Remove o-rings from end caps, clean the dielectric glass, end caps and interior of the stainless steel cathode cylinder.  Use denatured alcohol, shop towels to 

clean and be sure to remove all old o-ring debris.  A 1” ball hone can be used to clean the major debris out of the cathode if there is heavy buildup. 

Step 2: 

Prepare the end caps for re-assembly by replacing the o-rings. Thread the hex brush adapter nut, with contact brush attached, onto the end of the high voltage 

end cap (cap with the high voltage attachment screw) center screw.  Re-tape the threads of the elbow fittings if needed. 

Step 3: 

Using a gentle twisting motion, press the 

non

-high voltage end cap onto the heat sink/cathode assembly until

 

flush with the heat sink cooling fins. Turn the end 

cap to the correct orientation. 

Step 4: 

Slide the three end cap retaining screws with washers through the holes in the non-high voltage end cap, aligning them with the heat sink screw bosses. Thread 

screws into screw bosses until heads are snug against the end cap. 

Step 5: 

Next we focus on assembling the rest of the subcomponents, before installing them into the reaction chamber.

 

Slowly

 insert the brush (installed onto the high 

voltage end cap) into the dielectric glass. 

Note: 

Go slowly in order to prevent or minimize bending the center wire of the brush during this procedure.  It is 

normal for the bristles to bend flat against the dielectric glass.  Fully seat the dielectric glass into the high voltage end cap.  Clean the glass with denatured 

alcohol once more, and do not retouch the glass without re-cleaning.

 

Step 6: 

Hold the reaction chamber upright on a flat surface, empty high voltage side up.  Grasp the high voltage end cap and lower the glass into the reaction chamber.  

Press directly downwards on the high voltage end cap to fully seat the dielectric assembly; the end caps should be flush with the heat sink cooling fins.  Turn 

the end cap to the correct orientation.

 

Step 8: 

Slide the three end cap retaining screws with washers through the holes in the end cap, aligning them with the heat sink screw bosses. Thread screws into screw 

bosses until heads are snug against the end cap. 

Step 9

:  Re-install the complete reaction chamber assembly into the ozone generator by securing the reaction chamber to its mounts, securing delivery line and 

connecting the high voltage insulated wire. 

 

 