Standard Economizers
1-4
Part No. 750-266
Figure 1.2 - Installation, horizontal flow unit w/floor support
Figure 1.3 - Installation, horizontal flow unit w/ceiling support
Two (2) supported I-beams or channels can be used where larger economizers are being installed. The
exchanger can then be set on the beams and slid to the lower stack and/or stack adapter for final
securing. Position four (4) tie rods (as specified and supplied by others) which can be used to suspend
units depending on upper support.
C-B economizers are designed to support a maximum of 500 lbs stack weight above the economizer.
Structural integrity of the building should be verified (by others) prior to installing an economizer by
suspending from the ceiling.
Summary of Contents for C1X Series
Page 1: ...Economizers 750 266 1 15 CRE CCE C2X C1X Operation Manual...
Page 2: ......
Page 6: ...vi NOTES...
Page 20: ...Standard Economizers 1 14 Part No 750 266 Figure 1 7 Piping with circulating tank BOILER...
Page 29: ...Condensing Economizers Part No 750 266 2 9 Figure 2 7 Dimension diagram C2X BB...
Page 33: ...Condensing Economizers Part No 750 266 2 13 Figure 2 9 Single boiler with deaerator...
Page 39: ...Condensing Economizers Part No 750 266 2 19 Figure 2 11 Two boilers with deaerator...
Page 51: ...Condensing Economizers Part No 750 266 2 31...
Page 52: ...e mail info cleaverbrooks com Web Address http www cleaverbrooks com...