Chapter 8 — Inspection and Maintenance
8-16
Part No. 750-184
R. FUEL OIL METERING VALVE
In the event that a leak occurs in the packing of the metering valve, the
packing nut should be snugged gradually to stop the leak.
!
Caution
Do not over tighten the metering valve packing nut. Exces-
sive tightening of the packing nut prevents free movement
of the metering stem. Failure to follow these instructions
can cause damage to the equipment.
If replacement of the metering valve packing is necessary, procure
kit P/N
880-370
and install in accordance with the following procedure.
1. Shut off the oil flow. Be sure no pressure shows on the gauge.
2. Match-mark the cam hub and drive shaft. Match marking will enable
replacement of the cam in its original position and result in a minimum
of cam adjustment when the burner is refired.
3. Clamp or hold the metering stem in the down position.
4. Loosen the setscrews in the cam hub and rotate, or move the cam to a
position where it does not interfere with stem removal.
5. Withdraw the metering valve stem and spring. Do not drop or mishandle.
Check for nicks or scratches. Check that the pin holding the metering
portion is not protruding. Back off the packing gland.
6. Remove the capscrews holding the jack shaft support bracket so that the
bracket can be moved. It may also be necessary to loosen the supporting
bracket on the far end of the shaft.
7. Remove the existing packing and guides. Do not reuse the packing and
guides.
8. Lightly coat the stem with the lubricant provided with the packing kit.
Place the new packing, O-rings and guides onto the stem. The beveled
face of the guides and the teflon rings must face upward, with the
exception of the upper brass guide which is faced down. Be sure that the
O-rings are properly located.
9. Using the stem as a guide, insert the assembled packing into the cavity,
then withdraw the stem.
10.In the event the packing is too high, remove one teflon packing from each
side of the middle brass guide as needed.
Under no circumstances eliminate the two teflon packings on only one side
of the brass guide.
11.Replace the gasket, put the support in place, and secure all fastenings.
12.Replace the metering stem and spring. Lightly lubricate the stem to
facilitate insertion and easy movement. Use care when inserting so that
the orifice and the stem are not damaged.
13.Snug the packing gland, but only sufficiently to place slight tension on
the packing. The stem must move freely from the force of the spring.
14.Work the stem up and down several times to ensure that it moves freely.
Summary of Contents for CB Ohio Special 100 HP
Page 2: ...ii ...
Page 8: ...viii ...
Page 42: ...Chapter 2 Burner Operation and Control 2 22 Part No 750 184 ...
Page 116: ...Chapter 6 Adjustment Procedures 6 28 Part No 750 184 ...
Page 126: ...Chapter 8 Inspection and Maintenance 8 6 Part No 750 184 ...
Page 153: ...Chapter 9 Parts Part No 750 184 9 3 Insulated Front Head Model CB LE ...
Page 154: ...Chapter 9 Parts 9 4 Part No 750 184 Insulated Front Head Interior Model CB LE ...
Page 155: ...Chapter 9 Parts Part No 750 184 9 5 Insulated Inner Door Model CB OS ...
Page 156: ...Chapter 9 Parts 9 6 Part No 750 184 Insulated Rear Head CB LE ...
Page 157: ...Chapter 9 Parts Part No 750 184 9 7 Insulated Rear Head CB LE ...
Page 158: ...Chapter 9 Parts 9 8 Part No 750 184 Insulated Rear Head CB OS ...
Page 159: ...Chapter 9 Parts Part No 750 184 9 9 Dry Oven Model CB LE ...
Page 161: ...Chapter 9 Parts Part No 750 184 9 11 Motor Impeller Model CB LE ...
Page 162: ...Chapter 9 Parts 9 12 Part No 750 184 Front Head Linkage ...
Page 170: ...Chapter 9 Parts 9 20 Part No 750 184 Control Cabinet Hawk ICS ...
Page 171: ...Chapter 9 Parts Part No 750 184 9 21 Control Panel Standard ...
Page 172: ...Chapter 9 Parts 9 22 Part No 750 184 Entrance Box ...
Page 173: ...Chapter 9 Parts Part No 750 184 9 23 Front Head Electrical CB LE ...
Page 174: ...Chapter 9 Parts 9 24 Part No 750 184 Front Head Electrical CB LE ...
Page 175: ...Chapter 9 Parts Part No 750 184 9 25 Front Head Electrical CB OS ...
Page 176: ...Chapter 9 Parts 9 26 Part No 750 184 Front Head Electrical CB OS ...
Page 179: ...Chapter 9 Parts Part No 750 184 9 29 Heavy Oil Piping 60 Steam CB LE ...
Page 180: ...Chapter 9 Parts 9 30 Part No 750 184 Heavy Oil Piping 60 Steam CB LE SEE TABLE NEXT PAGE ...
Page 181: ...Chapter 9 Parts Part No 750 184 9 31 Common Oil Parts Heavy Oil ...
Page 182: ...Chapter 9 Parts 9 32 Part No 750 184 Side Mounted Air Compressor Piping ...
Page 183: ...Chapter 9 Parts Part No 750 184 9 33 Air Compressor Piping CB OS ...
Page 185: ...Chapter 9 Parts Part No 750 184 9 35 Light Oil Piping ...
Page 186: ...Chapter 9 Parts 9 36 Part No 750 184 Light Oil Air Piping Front Head ...
Page 187: ...Chapter 9 Parts Part No 750 184 9 37 Light Oil Air Piping Front Head PAGE 9 31 ...
Page 191: ...Chapter 9 Parts Part No 750 184 9 41 Gas Train 125 150 HP ...
Page 193: ...Chapter 9 Parts Part No 750 184 9 43 Gas Train 200 HP ...
Page 195: ...Chapter 9 Parts Part No 750 184 9 45 Steam Pressure Controls ...
Page 196: ...Chapter 9 Parts 9 46 Part No 750 184 Hot Water Temperature Controls ...
Page 197: ...Chapter 9 Parts Part No 750 184 9 47 Water Column ...
Page 198: ...Chapter 9 Parts 9 48 Part No 750 184 Water Column ...
Page 199: ...Chapter 9 Parts Part No 750 184 9 49 Fireside Gaskets CB LE ...
Page 200: ...Chapter 9 Parts 9 50 Part No 750 184 Fireside Gaskets CB OS ...