MACHINE INSTALLATION
UNCRATING MACHINE
1. Carefully check the shipping crate for signs of
damage. Report damages at once to carrier.
2. Check the contents list. Contact distributor for
missing items.
Contents:
S
2--12 V Batteries (Optional)
S
2--Foam Battery Spacers
S
Battery Tray
S
Battery Cable
S
Squeegee Assembly
3. Roll machine off pallet using the attached ramp.
ATTENTION: Do not roll machine off pallet unless
ramp is used, machine damage may occur.
INSTALLING BATTERIES
WARNING: Fire Or Explosion Hazard.
Batteries Emit Hydrogen Gas. Keep Sparks And
Open Flame Away. Keep Battery Hood Open When
Charging.
FOR SAFETY: When servicing machine, wear
protective gloves and eye protection when
handling batteries and battery cables. Avoid
contact with battery acid.
Battery Specifications:
Two 12 volt, 70Ah/5h Gel (994200), 72Ah/5h lead acid
(1041458), 85Ah/5h lead acid (1041454) deep cycle
batteries.
1. Park the machine on a level surface and remove
the key.
2. Carefully install the batteries into the battery
compartment as shown (Figure 1).
3. Connect the battery cables as shown (Figure 1).
Machine Front
72Ah
RED
BLK
70Ah, 85Ah, 105Ah
RED
BLK
Foam Spacers
FIG. 1
IMPORTANT: Before charging batteries, make sure
the on--board battery charger is properly set for
your battery type (See USING THE ON--BOARD
CHARGER).