Now we are starting to assemble Polycarbonate panels and glazing bar.
1.
Sliding PC panel #B between cross bar part #V042 and side sill beam with PVC anti-dust strip P7 on bottom.
2.
Connect curved glazing bar #V943 with ridge and hanging basket bar, and tighten it.
3.
Inserting polycarbonate panel # I1 into the alu. Frame channel and curve it along the curved alu. Channel.
4.
You could squeeze PC panel up and down, and adjust the depth of inserting of cross bar part #V042 on horizontal rail.
Very Important:
3 #a1 Bolts will need to be slid into each glazing bar for ridge cantilever & hanging basket bar & horizontal
rail, 1 #a8 bolt be slid into each glazing bar for connect side sill in advance, and finger tightened for later use. Please note: At
this stage you will need to insert an extra bolt into each glazing bar either side of a vent opening. So you will have to dec ide
now where your roof vents are positioned so that you can work out the correct number of bolts in each glazing bar.
And slide
roof vent to decided position from Ridge immediately, otherwise glazing bar will block its slide after glazing bar is
fixed.
V042
Hanging
basket b
ar
Horizon
tal rail
assembling cross bar part
#V042 on horizontal rail
PC panel bottom
with PVC anti-
dust strip P7
B
I1
tighten first
V943
You should attach glazing bar #V943 with ridge
and hanging basket bar first.
Separate curved glazing bar #V943 a little from
bottom, and make an angle and then insert PC
panel into alu. Frame channel.
a1
a2
a1
a2
V943
012
V943
breach
If you forgot sliding extra
bolts into glazing bar or
corner bar channels in
advance, please add it
through this breach.